== Program Now - May


Plans and Status rest of SAD

  • Oct 7 - 11 : Gun bake, leak check, lasers ready, laser training, laser PQB start
  • Oct 14 - 18 : laser PQB continues, Re-assemble instrumentation, HV cables, coordinate with PSS/Ops for HV ON, conditioning?
  • Oct 21 - 25 : Make a photocathode, remove SF6 conditioning resistor, crane stuff out, clean up, start making beam w/ PQB checks
  • Oct 28 - Nov 1 : Injector setup and PQB checkout

What fit's and doesn't

  • I don't think we have time for the Load chamber, little time
  • Daniel will coordinate removing the big HVPS oil tank
LERF
Nov 1-4 HCO for isotope run (laser, photocathode, high voltage)
Nov 5-6 : 2 shifts/day commissioning run, ~60 pC @ 4 MHz, < 1 mA
Dec TBD : another couple shifts, actual isotope run, ~60 pC @ 4 MHz < 1 mA
UITF
GTS