October 9, 2019
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
CEBAF for 7 Months
- Calendar for your wall media:191009_CIS.pptx
- SAD Calendar until startup
- Ops is coordinating start-up this time (Spata, Freeman, Aiken, Moser)
- Web gannt view (Internal): http://opsweb/gantt/2019_Fall/fall2019Run-chart.html
- Task View (Internal): http://opsweb/gantt/2019_Fall/fall2019Run-tasks.html
CIS - Status and Strategy to Fall Operations
- Oct 7 - 11 : Gun bake, leak check, lasers ready, laser retro, laser training, laser PQB start
- Oct 14 - 18 : laser PQB continues, Re-assemble instrumentation, HV cables, coordinate with PSS/Ops for HV ON, conditioning?
- Oct 21 - 25 : Make a photocathode, remove SF6 conditioning resistor, crane stuff out, clean up, start making beam w/ PQB checks
- Oct 28 - Nov 1 : Injector setup and PQB checkout
What fits and what doesn't
- Very little else fits
- I don't think we have time for the Load chamber, little time
- Daniel will coordinate removing the big HVPS oil tank
Small shed - lessons learned
- Summary of last ~decade media:CEBAF_Electrodes_2008-2019.pptx
- Priority is restoring CEBAF, but need to evaluate what happened to small shed electrode...
- The sure thing "tee" will be informative, help us find a path forward
- We knew this was a test of Kr processing w/ a NEG coating => maybe we just learned the answer?
- We worry about contamination ... during polishing, during venting, with NEGs, all worth considering, but really how different than usual?
CREX jobs
- Laser Room
- Camera measurements (post fiber change)
- Spinning LP for A/B/C/D: http://opsweb.acc.jlab.org/CSUEApps/atlis/task/19669
- Transition Time recheck
- IA setting zero-finding
- Beam to FC#1
- Cathode Rotation: http://opsweb.acc.jlab.org/CSUEApps/atlis/task/18799
- IA/RTP/RWHP settings for all 4 lasers: http://opsweb.acc.jlab.org/CSUEApps/atlis/task/19670
- Pos Diff Feedback to FC1/FC2: http://opsweb.acc.jlab.org/CSUEApps/atlis/task/18793
- Beam to either FC2/ILD (end of injector)
- 90Hz beam motion fix?
- PQB Health check to FC2
- PQB Health check to ILD
- Beam to HallA
- Adiabatic Damping check?
- Dithering check?
- During Experiments (affects other halls, but also necessary for HallC to ensure we are minimizing their Aq well)
- PITA scans
- RHWP sweeps
- Post Experiment
- Spot size asymmetry measurements: http://opsweb.acc.jlab.org/CSUEApps/atlis/task/19669
LERF
- Nov 1-4 HCO for isotope run (laser, photocathode, high voltage)
- Nov 5-6 : 2 shifts/day commissioning run, ~60 pC @ 4 MHz, < 1 mA
- Dec TBD : another couple shifts, actual isotope run, ~60 pC @ 4 MHz < 1 mA
UITF
- Electrode choice
- Tentative dates for Booster commissioning
- Wien filter testing
- HD Ice run