Line 13: Line 13:
 
:[[DR dipole (15 deg)]] - New 15 deg air core bend dipole replaces pre-existing DS dipole
 
:[[DR dipole (15 deg)]] - New 15 deg air core bend dipole replaces pre-existing DS dipole
 
:[[FX beamline and FY chopper solenoids]] - New double-coil sw/cw capable solenoids with 38 mm (FX) and 46 mm (FY) ID
 
:[[FX beamline and FY chopper solenoids]] - New double-coil sw/cw capable solenoids with 38 mm (FX) and 46 mm (FY) ID
 +
:[[FG spin solenoids]]
 
:[[PSS Kicker (upgraded for 200 kV upgrade)]] - New PSS kicker of reliable design to operate at 200 kV with shorter throw
 
:[[PSS Kicker (upgraded for 200 kV upgrade)]] - New PSS kicker of reliable design to operate at 200 kV with shorter throw
 
:[[WF Wien Filters (200 kV upgrade)]] - Upgraded Wien filters with 20 A magnetic coils and >18 kV electrodes to rotate spin of 200 keV electrons
 
:[[WF Wien Filters (200 kV upgrade)]] - Upgraded Wien filters with 20 A magnetic coils and >18 kV electrodes to rotate spin of 200 keV electrons
Line 29: Line 30:
  
 
;AIPINJ
 
;AIPINJ
 +
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22151 AIPINJ: temporary 5D beam line removal]
 +
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22161 Removal/Er-installation of Part of 5D line in Inj.]
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21911 Gun high voltage conditioning]
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21911 Gun high voltage conditioning]
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21370 Injector Wien Filter - system upgrade (2020 SAD)]
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21370 Injector Wien Filter - system upgrade (2020 SAD)]
Line 43: Line 46:
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21431 Install and Commission Wien filter Power Supplies]
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21431 Install and Commission Wien filter Power Supplies]
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21198 Survey support for Injector Upgrade]
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21198 Survey support for Injector Upgrade]
 +
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22071 DC Power Support for Injector Upgrade]
 +
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22201 STAC5 A1 Aperture Epics Controls]
  
  
Line 63: Line 68:
  
 
;Injector Related SAD Tasks
 
;Injector Related SAD Tasks
 +
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22130 LLRF Diagnostics and Repairs in the Linacs and Injector]
 +
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22100 April 2021 10 Amp System PM Maintenance]
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22020 Annual Crane Inspections Site wide May 17- May 27 2021]
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22020 Annual Crane Inspections Site wide May 17- May 27 2021]
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21316 VME FSD Master Card Commisioning]
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21316 VME FSD Master Card Commisioning]
Line 92: Line 99:
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21103 Change transformer tap settings - oil filled transformers]
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21103 Change transformer tap settings - oil filled transformers]
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21991 Injector Survey Monuments install]
 
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21991 Injector Survey Monuments install]
 +
* '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/20972 Remove Old 45MeV Dump and re-Install at End of SAD]
  
  

Revision as of 18:06, 7 April 2021

Quick Phase 1 Links

ATLIS => Phase 1 ATLIS
8:30 Tools => CIS Phase 1 work plans
HCO => Phase 1 - HCO & Commissioning
Meetings=> AIPINJ - Upgrade Meetings
Schedule Status => media:210125_AIPINJ_Schedule.pdf

Major Phase 1 Beamline Components

200 kV gun - Cathode, anode and high voltage system
200 kV NEG Coated BPM's - New BPM's on beam pipe, NEG coated and absolutely mapped
Y-chamber Laser Window - Evaluating the best window to minimize birefringence under stress
DR dipole (15 deg) - New 15 deg air core bend dipole replaces pre-existing DS dipole
FX beamline and FY chopper solenoids - New double-coil sw/cw capable solenoids with 38 mm (FX) and 46 mm (FY) ID
FG spin solenoids
PSS Kicker (upgraded for 200 kV upgrade) - New PSS kicker of reliable design to operate at 200 kV with shorter throw
WF Wien Filters (200 kV upgrade) - Upgraded Wien filters with 20 A magnetic coils and >18 kV electrodes to rotate spin of 200 keV electrons
QW Wien quadrupoles (200 kV upgrade) - New quads designed for 200 keV energy, w/ improved magnetic field quality
Chopping System (200 kV upgrade) - Choppers get higher power amplifiers, maybe a new chopping chamber
Pre-buncher cavity (200 kV upgrade) - Existing stainless steel pre-buncher replaced by copper cavity for higher power.
NEG coated 2.5 inch OD BPM's - Replacing (2) existing with (3) new BPM's, provide (x,x',y,y') from gun, help tuning
HD steering coils - New steering coils for the A1/A2 aperture cubes, improved design and for 200 keV energy
A1/A2 Aperture Steering Cubes - Reinvented A1/A2 apertures define beam size and PSS kicker destination, include upgraded HD steering coils
Injector upgrade vacuum improvements - Improvements in the vacuum design, use of getter and ion pumps
Beamline viewers
LLRF 3.0 Phase 1

ATLIS Tasks

Open, complete, re-scheduled statuses updated 3/15/21