ATLIS => Phase 1 ATLIS
8:30 Tools => CIS Phase 1 work plans
HCO => Phase 1 - HCO & Commissioning
Meetings=> AIPINJ - Upgrade Meetings
Schedule Status => media:210125_AIPINJ_Schedule.pdf

Phase 1 Beamline Components

Gun & Vacuum
200 kV gun - Cathode, anode and high voltage system
Injector upgrade vacuum improvements - Improvements in the vacuum design, use of getter and ion pumps
Y-chamber Laser Window - Evaluating the best window to minimize birefringence under stress
Solenoid Details
Agreed solenoid field direction convention => https://logbooks.jlab.org/entry/3256163
Phase 1 wiring diagram info => media:210419_Magnet_Wiring_v6.docx
FX beamline and FY chopper solenoids - New double-coil sw/cw capable solenoids with 38 mm (FX) and 46 mm (FY) ID
FG spin solenoids
Other Magnets
DR dipole (15 deg) - New 15 deg air core bend dipole replaces pre-existing DS dipole
PSS Kicker (upgraded for 200 kV upgrade) - New PSS kicker of reliable design to operate at 200 kV with shorter throw
WF Wien Filters (200 kV upgrade) - Upgraded Wien filters with 20 A magnetic coils and >18 kV electrodes to rotate spin of 200 keV electrons
QW Wien quadrupoles (200 kV upgrade) - New quads designed for 200 keV energy, w/ improved magnetic field quality
HD steering coils - New steering coils for the A1/A2 aperture cubes, improved design and for 200 keV energy
RF System
Chopping System (200 kV upgrade) - Choppers get higher power amplifiers, maybe a new chopping chamber
Pre-buncher cavity (200 kV upgrade) - Existing stainless steel pre-buncher replaced by copper cavity for higher power.
LLRF 3.0 Phase 1
Diagnostics
NEG coated 2.5 inch OD BPM's - Replacing (2) existing with (3) new BPM's, provide (x,x',y,y') from gun, help tuning
200 kV NEG Coated BPM's - New BPM's on beam pipe, NEG coated and absolutely mapped
A1/A2 Aperture Steering Cubes - Reinvented A1/A2 apertures define beam size and PSS kicker destination, include upgraded HD steering coils
Beamline viewers

ATLIS Tasks

Open, complete, re-scheduled statuses updated 3/15/21

AIPINJ



CIS SAD Tasks



Injector Related SAD Tasks