Open, complete, re-scheduled statuses updated 5/23/21
- AIPINJ
- Open Insertable Upgrade on iocin3 for viewers, faraday cup, and yag viewer
- Open Removal/Er-installation of Part of 5D line in Inj.
- Open Injector Wien Filter - system upgrade (2020 SAD)
- Open Mat'l Handling and Installation for Phase I of Inj. Upgrade
- Open Remove and re-install BPM's Gun to chopper
- Open Pedestal Location Surveys
- Open Install Chopper SSA's
- Open Remove and calibrate current monitoring electronics
- Open Survey support for Injector Upgrade
- Open DC Power Support for Injector Upgrade
- Open Perform Installation work for newly added Injector bpm during 2020 SAD
- Complete Install and Commission Wien filter Power Supplies
- Complete AIPINJ: temporary 5D beam line removal
- Complete "SAD 2020" Injector Harp System - interface controls upgrade
- Complete STAC5 A1 Aperture Epics Controls
- Complete Testing Wien HV Controls at UITF
- Complete Removal of PSS kicker magnet injector segment
- Complete Gun high voltage conditioning
- Complete Chopper SSA LCW
- Complete IOCSE11 & IOCINSE4 BPM Controls Update
- Complete Install PSS jumpers for laser work at the Injector
- Complete Relocate Recepacles Downstairs in Injector Bldg.53
- Complete Install Lifting Plates in Ijn. Ceiling to Support 1/4 CM Swap
- Complete 5D cold cathode gauge repositioning
- Complete Add UHV ion pumps to VBV0I02 interlock chain
- CIS SAD Tasks
- Open New Gun2 loading chamber
- Placeholder for Tim Minga to test laser room smoke detector alarm to MCC/Guard
- Placeholder Fix IHWP readback during SAD
- Complete Injector Macropulse/Tune Mode Generator Modification
- Complete CEBAF Lead Bricks : Collect, Sort, Clean, Paint, Store
- Injector Related SAD Tasks
- Open Penetration Drops
- Open LLRF Diagnostics and Repairs in the Linacs and Injector
- Open April 2021 10 Amp System PM Maintenance
- Open Annual Crane Inspections Site wide May 17- May 27 2021
- Open VME FSD Master Card Commisioning
- Open 429 mHz Amp & Power supply being pulled for repair
- Open 2020 SAD Injector / North Linac 30 Hz System checks
- Open PSS Injector Interface Chassis removal
- Open PSS Injector Segment PLC Upgrade
- Open PSS CAMAC Relay cards replacement with VME versions for Injector and BSY
- Open I&C Injector Camac to Vme and camera upgrade
- Open I&C Upgrade harps to PC104
- Open I&C Accelerator network re-survey
- Open FAC Tunnel Fire Alarm and Suppression Replacement
- Open Apply labels to I&C components during 2020 SAD
- Open Neutron Detector System Installation (SAD 2020)
- Open UHV Power Supply Replacement (ISB)
- Open Trim Utility Chassis Upgrade - All CEBAF Trim Racks
- Open SAD 2020: P.M. of 24V Vacuum Power Supply Chassis
- Open VME crate upgrade to IOCIN3
- Open Insertable CAMAC to VME EPICS Controls upgrade Injector (iocin1->iocin1b)
- Open Software Controls PSS Injector and North Linac changes on iocsoftsafe2
- Open Perform Basic PM of 45 MeV spectrometer Power Supply
- Open 2020 SAD and Beyond CAMAC / VME PM maintenance and repairs
- Open Change transformer tap settings - oil filled transformers
- Open Injector Survey Monuments install
- Open Remove Old 45MeV Dump and re-Install at End of SAD
- Open Leak Repairs inside of HPA cabinets (1L02-8, 1L06-8, 1L09, and 0L04)
- Complete Connect bpm cables inside injector Laser Yellow Box *revised
- Complete B53 (INJ SB) Panelboard PM
- Complete iocin1 - VME crate replacement
- Complete Study - Site Ground Loop
- Completed Shutdown of Panel I-BT in the Injector
- Completed Remove old Sonitrol system hardware from NA and SA
- Complete Install Ion Pump HV cables and mount Junction boxes on cable trays NL and INJ