Difference between revisions of "Phase 1 - HCO & Commissioning"

From Ciswikidb
Jump to navigation Jump to search
Line 23: Line 23:
 
* Pull additional Anode bias HV cable near Glassman rack, I think that's where we ultimately want to bias PS star ground to HVPS, also to patch to QE scan ammeter
 
* Pull additional Anode bias HV cable near Glassman rack, I think that's where we ultimately want to bias PS star ground to HVPS, also to patch to QE scan ammeter
 
* Develop HV commissioning plan/staffing
 
* Develop HV commissioning plan/staffing
 +
**[[Media:Gun2 Tee electrode 200kV HV codnitoning plan 2021 draft01.pptx]]
  
 
; Wien HVPS (Carlos, Scott, Riad)
 
; Wien HVPS (Carlos, Scott, Riad)

Revision as of 09:20, 15 February 2021

Jobs Leading to HCO & Commissioning (Jan 1 - Apr 30)

15 deg dipole (Scott)
  • Install on beam line after bake out, then align, do we use shims?
  • Current sensor for HV interlock installed and tested, ready for DC power, to set limits, fault test
  • Current sensor for FSD installed and tested, calibrated for FSD card, ready for DC power, to set limits, fault test
  • Update drawings, screens, document
Laser jobs (Shukui/Scott)
  • Complete outrigger box, install, test with laser room shutter, update LSOP
  • Flush chiller, decide on PM schedule, fill
  • Re-install/align Pockels cell
  • Re-install Hall B amp in permanent location
  • Complete macropulse chassis upgrade (replace 18 VDC + booster with 24 VDC, add protection diode to shutters), test all beam modes
  • Update drawings, document
Gun HVPS jobs (Carlos/Bubba/Scott)
  • Prep for HV & conditioning (SF6, tank, DILO, cables), check HV interlock made up, HVPS setpoints/controls ready
  • Regrease ceramic after bake
  • Make sure back-up electrode is available
  • Remove old HV parts (150kV glassman, old HV interlock chassis, VME interface card), once we can make HV again ... temp replace with Ortec bias PS (if needed)
  • Pull additional Anode bias HV cable near Glassman rack, I think that's where we ultimately want to bias PS star ground to HVPS, also to patch to QE scan ammeter
  • Develop HV commissioning plan/staffing
Wien HVPS (Carlos, Scott, Riad)
  • (done) Add placards to ISB racks
  • Install HV Switcher chassis at ISB, complete cabling between rack components
  • Drop/pull HV cables from HV switcher outputs to Wiens
  • Wien EDM and InjSteer screens updates with HVPS and new PS epics values, tested, ready
  • Update screens, drawings, document
Ion Pump Power Supplies (Scott, Marcy)
  • (done) Finalize IP names for songsheet media:210209_ion pump names.xlsx
  • Complete mapping between all IP and power supplies (gun to choppers)
  • Complete UHV power supply upgrade, remove temp PS, spare PS on shelf (identify cabinet area for spares)
  • Work with software to reprogram UHV PS EPICS names, can we have unique identifier from old names?
  • Re-install (2) HV patch boxes, update box labels, pull HV drop cables to patch boxes, updated labels
  • Update screens, drawings, document
Vacuum (Marcy, Phil)
  • Bake gun, fix scheme for Kr processing beforehand
  • Bake beam line
  • Activate beam line NEG's
  • Hi-pot any FE-er pumps
  • Set voltage for all pumps
  • Activate Prep NEG to overboard, bake if needed
Valves (Scott, Phil)
  • Work with I&C and software, controls for (3) valves (note - confirm valve type different)
  • Build, install, test (3) shut-override boxes for valves
  • UHV vacuum fault (series, yes?) shuts all three gate valves, test
  • Gun2 valve open required for HV enable; method to jumper/bypass for HV conditioning (i.e. valve closed, but HV enable OK)
  • Update drawings, document
Air, GN2, LCW (Phil, Bubba)
  • Move GN2 near gun lower, hook for air lines, caps for poly hose
  • Add 2nd GN2 near girder, hook for air lines, caps for poly hose
  • Fabricate, install air manifold w/ cutoff for (8) viewers, (2) valves, (2) spares
  • (done) Re-install LCW manifold
Crash inhibit (Scott, Phil)
  • Install, test crash inhibit for pcup and viewer (note - fail safe test, i.e. do NOT hook up air to BOTH devices)
  • Install, test crash inhibit for harp and viewer (note - does this exist, would speak to I&C early on)
Apertures & PCup (Phil, Scott)
  • Scribe new aperture stops, bag, store in tunnel, throw away ALL old stops
  • Install shoulder bolt on A1, test
  • Attach current monitoring w/ inline I&C protection boxes
  • Reconnect LCW, I&C check flow meters clear interlock
Electrician jobs (Scott)
  • Relocate floor outlets
  • Bond girders (Shaun has holes drilled on girders already for this)
  • Install cable tray
Decarad (Carlos, Scott)
  • Tally # of heads for gun (Carlos) and beam line (Alicia)
  • Mount decarad chassis, dress signal/HV cables

Beam Commissioning (May 1 - Jul 2)

Celebration