==CIS Jobs Leading to HCO & Commissioning (Jan 1 - Apr 30) ==  
 
==CIS Jobs Leading to HCO & Commissioning (Jan 1 - Apr 30) ==  
<div class="mw-collapsible mw-collapsed">
+
* 4/06/21 - Updated punchlist [[media:210406_CIS_HCO.docx]]
 
+
* 3/22/21 - Updated punchlist [[media:210322_CIS_HCO_v2.docx]]
; 15 deg dipole (Scott)
+
* '''(Done/SW/JG - magnet is ready for install & yes, we will use shims)''' Install on beam line after bake out, then align, do we use shims?
+
* Current sensor for HV interlock installed and tested, ready for DC power, to set limits, fault test
+
* Current sensor for FSD installed and tested, calibrated for FSD card, ready for DC power, to set limits, fault test
+
* Update drawings, screens, document
+
 
+
; Laser jobs (Shukui/Scott)
+
* Complete outrigger box, install, test with laser room shutter, update LSOP
+
* Flush chiller, decide on PM schedule, fill
+
* Re-install/align Pockels cell
+
* Re-install Hall B amp in permanent location
+
* Complete macropulse chassis upgrade (replace 18 VDC + booster with 24 VDC, add protection diode to shutters), test all beam modes
+
* Update drawings, document
+
 
+
; Gun HVPS jobs (Carlos/Bubba/Scott)
+
* Prep for HV & conditioning (SF6, tank, DILO, cables), check HV interlock made up, HVPS setpoints/controls ready
+
* Regrease ceramic after bake
+
* Make sure back-up electrode is available
+
* Remove old HV parts (150kV glassman, old HV interlock chassis, VME interface card), once we can make HV again ... temp replace with Ortec bias PS (if needed)
+
* Pull additional Anode bias HV cable near Glassman rack, I think that's where we ultimately want to bias PS star ground to HVPS, also to patch to QE scan ammeter
+
* Develop HV commissioning plan/staffing
+
**[[Media:Gun2 Tee electrode 200kV HV codnitoning plan 2021 draft01.pptx]]
+
 
+
; Wien HVPS (Carlos, Scott, Riad)
+
* '''(Done)''' Add placards to ISB racks
+
* Install HV Switcher chassis at ISB, complete cabling between rack components
+
* Drop/pull HV cables from HV switcher outputs to Wiens
+
* Wien EDM and InjSteer screens updates with HVPS and new PS epics values, tested, ready
+
* Update screens, drawings, document
+
 
+
; Ion Pump Power Supplies (<strike>Scott</strike>, Marcy, EES)
+
* '''(Done)''' Finalize IP names for songsheet [[media:210209_ion pump names.xlsx]]
+
* Complete mapping between all IP and power supplies (gun to choppers)
+
* Complete UHV power supply upgrade, remove temp PS, spare PS on shelf (identify cabinet area for spares): This is Jim Kortze & co., not planned for this down?
+
* Work with software to reprogram UHV PS EPICS names, can we have unique identifier from old names?
+
* Re-install (2) HV patch boxes, update box labels, pull HV drop cables to patch boxes, updated labels
+
* Update screens, drawings, document
+
 
+
; Vacuum (Marcy, Phil)
+
* '''(Done)'''Bake gun, fix scheme for Kr processing beforehand
+
* Bake aperture girder beam line, activate NEGs
+
* Bake wien and y chamber girders, activate NEGs
+
** Make cables to activate Y chamber NEG pumps during bakeout (draw up and send to Fab)
+
* Activate beam line NEGs for DP stations downstream of chopper
+
* Hi-pot any FE-er pumps
+
* Set voltage for all pumps
+
* Activate Prep NEG to overboard (done), bake if needed (Joe: see if cathode activates in prep chamber? No water in RGA scan)
+
 
+
; Valves (Scott, Phil)
+
* '''(Done)'''Work with I&C and software, controls for (3) valves (note - confirm valve type different)
+
* Build, install, test (3) shut-override boxes for valves
+
* UHV vacuum fault (series, yes?) shuts all three gate valves, test
+
* Gun2 valve open required for HV enable; method to jumper/bypass for HV conditioning (i.e. valve closed, but HV enable OK)
+
* Update drawings, document
+
 
+
; Air, GN2, LCW (Phil, Bubba)
+
* '''(Done)'''Move GN2 near gun lower, hook for air lines, caps for poly hose
+
* '''(Done)'''Add 2nd GN2 near girder, hook for air lines, caps for poly hose
+
* Fabricate, install air manifold w/ cutoff for (8) viewers, (2) valves, (2) spares
+
* (done) Re-install LCW manifold
+
 
+
; Crash inhibit (Scott, Phil)
+
* Install, test crash inhibit for pcup and viewer (note - fail safe test, i.e. do NOT hook up air to BOTH devices)
+
* Install, test crash inhibit for harp and viewer (note - does this exist, would speak to I&C early on)
+
 
+
; Apertures & PCup (Phil, Scott)
+
* Scribe new aperture stops, bag, store in tunnel, throw away ALL old stops
+
* Install shoulder bolt on A1, test
+
* Attach current monitoring w/ inline I&C protection boxes
+
* Reconnect LCW, I&C check flow meters clear interlock
+
 
+
; Electrician jobs (Scott)
+
* Relocate floor outlets (done)
+
* Bond girders (Shaun has holes drilled on girders already for this)
+
* Install cable tray
+
 
+
; Decarad (Carlos, Scott)
+
* Tally # of heads for gun (Carlos) and beam line (Alicia)
+
* Mount decarad chassis, dress signal/HV cables
+
 
+
</div>
+
  
 
==I&C/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30) ==
 
==I&C/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30) ==
Line 145: Line 64:
  
 
; DC/Magnet Jobs
 
; DC/Magnet Jobs
* Updated spreadsheet '''Mar 1''' [[media:210301_Phase1_Magnet_Summary_v2.xlsx]]
+
* Spreadsheet updated 3/15 [[media:210315_Phase1_Magnet_Summary.xlsx]]
 +
::Updated MHD field map due from JM/LL to GC
 +
::Updated MFX (SW/CW) field map due from RS to GC
 +
* Spreadsheet updated after further feedback [[media:210301_Phase1_Magnet_Summary_v3.xlsx]]
 +
* Spreadsheet updated at 3/1 SAD planning meeting [[media:210301_Phase1_Magnet_Summary_v2.xlsx]]
 +
* Spreadsheet initially [[media:210301_Phase1_Magnet_Summary.xlsx]]
  
 
; Software Jobs
 
; Software Jobs
Line 154: Line 78:
  
 
; Other magnet jobs
 
; Other magnet jobs
*(JM) Complete magnet table I circulated
+
* (JM) Complete magnet table I circulated
*(JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
+
* '''Done'''(JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
*(RS/GC) FG solenoid special hysteresis for Gary
+
* (RS/GC) FG solenoid special hysteresis for Gary
*(RS/MJ) Magnet info for Inj Steer spin calculations
+
* (RS/MJ) Magnet info for Inj Steer spin calculations
*(JM/JG) Decision on spare DR fabrication and alignment
+
* (JM/JG) Decision on spare DR fabrication and alignment
*(LL/JK/JM) PSS kicker -  does MMF have any responsibility here, maybe just PSS?
+
* '''Done''' (LL/JK/JM) PSS kicker -  does MMF have any responsibility here, maybe just PSS?
*(LL/JM) Second QW measurement, what's the scope here?
+
* '''Done''' (LL/JM) Second QW measurement, what's the scope here?
*(JM) When is the rotating coil stand ready?
+
* '''Done''' (JM) When is the rotating coil stand ready?
*(JM/LL) Reconciling MHD discrepancy
+
* (JM/LL) Reconciling MHD discrepancy
*(LL) Report on QW
+
* (LL) Report on QW
*(LL) Report on HD
+
* (LL) Report on HD
*(LL) Report on PSS kicker
+
* (LL) Report on PSS kicker
  
  
 +
</div>
 +
 +
== System Readiness / HCO Schedule (April '21) ==
 +
<div class="mw-collapsible">
 +
 +
'''For detailed plans for a given day, discussed at 830 toolbox meeting every weekday, see [[CIS Phase 1 work plans]]'''
 +
 +
'''Format:''' time: System (# of people)
 +
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color: #eca1a6" | '''April''' !! style="background-color:#eca1a6" | Mon  !! style="background-color:#eca1a6" |  Tue !! style="background-color:#eca1a6" |  Wed !! style="background-color:#eca1a6" |  Thu !! style="background-color:#eca1a6" |  Fri !! style="background-color:#ada397" |  Sa !! style="background-color:#ada397" |  Su
 +
|- style="background-color:#d6cbd3"
 +
| ! style="background-color:#eca1a6" | '''12th - 16th''' || Morning: Valve Controls (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: Valve Controls (1x) <br> Morning: ItoV, Pico, FSD (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: Valve Controls (1x) <br> Morning: ItoV, Pico, FSD (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: ItoV, Pico, FSD (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: ItoV, Pico, FSD (1x) <br> Afternoon: Magnet Hook-Ups (2x) || !! style="background-color:#ada397" | Magnet Hook-Ups (2x) || !! style="background-color:#ada397" | Magnet Hook-Ups (2x)
 +
|- style="background-color:#bdcebe"
 +
| ! style="background-color:#eca1a6" | '''19th - 23rd'''  || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) ||  Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) || !! style="background-color:#ada397" | Magnet Hook-Ups/HCO (2x) <br> || !! style="background-color:#ada397" | Magnet Hook-Ups/HCO (2x)
 +
|- style="background-color:#d6cbd3"
 +
| ! style="background-color:#eca1a6" | '''26th - 30th''' || Magnet HCO (2x) <br> I&C Float || Magnet HCO (2x) <br> I&C Float || Magnet HCO (2x) <br> 2B Alignment <br> ''Swings: PSS beamline Certs'' || Magnet HCO (2x) <br> 2B Alignment <br> ''Swings: PSS beamline Certs'' || Magnet HCO (2x) || !! style="background-color:#ada397" | Magnet HCO (2x) || !! style="background-color:#ada397" | Magnet HCO (2x)
 +
|- style="background-color:#bdcebe"
 +
|}
 +
 +
* BPM = Francis
 +
* Valve Controls = Ketchum
 +
* ItoV, Picoammeters, Gun FSD Interlocks = Francis
 +
* Viewers = Norris
 +
* Harps = Dela Cruz
 +
* Magnet / DC Power = Coleman
 +
* 2B Alignment = S&A, Gould
 +
* PSS = Kowal
  
 
</div>
 
</div>
Line 174: Line 127:
 
<div class="mw-collapsible mw-collapsed">
 
<div class="mw-collapsible mw-collapsed">
  
[[File:Commissioning_Activities_Rev1.png | 1000px]]
+
=== Documents, Links, Important Dates ===
 +
 
 +
Links:
 +
* [https://wiki.jlab.org/ciswiki/index.php/January_25,_2021_-_Weekly_Commissioning_Meetings 1/25/21 Beam Drivers Preliminary Meeting]
 +
* [https://jeffersonlab.sharepoint.com/sites/CEBAFInjectorSetupProceduresDevelopment Injector Procedures Workspace]
 +
 
 +
Documents:
 +
* 3/16/21 Beam Drivers Meeting Slides [[media:BeamDrivers_Pt2_3.16.21.pdf]]
 +
* Injector Group Beam Commissioning Slides [[file:BeamINJphase1v5.pptx]]
 +
 
 +
* Commissioning Checklist (Grames) [[file:210401_Phase1_Commissioning.docx]]
 +
* (incomplete / in-progress) Commissioning Checklist, ATLiss added [[file:210407 Phase1 Commissioning.docx]]
 +
* Preliminary Commissioning Test Plan Layout [[file:3.31.21 BeamCommissioningPlanLayout AIPINJ-1 firstpass.ods]]
 +
 
 +
Dates:
 +
''updated 4/7/21''
 +
* '''Finalize commissioning plan: April 5th'''
 +
* Injector HCO/SR Complete: 5/2
 +
* Injector Beam Commissioning Begins: 5/3
 +
* NL/Inj -> Stable 2K: 5/21
 +
* Full CEBAF PSS Certification: 5/24 - 6/11
 +
* End of SAD: 7/2
 +
* Resumption of Physics: Mid-August
 +
 
 +
 
 +
=== ATLis Testplans ===
 +
<div class="mw-collapsible mw-collapsed">
 +
''updated 4/7/21''
 +
 
 +
General / Catch-All Test Plans
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22060 22060 Beam Commissioning AIPINJ Phase I (general ATLis)]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21170 Injector Upgrade - Phase 1 Installation (Gun to Chopper)]
 +
 
 +
 
 +
With-Beam Hardware Commissioning Test Plans
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22061 22061 PSS Kicker Tests @ 130keV & 200keV]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22080 22080 AIPINJ: 130/200 keV HVPS vs. PCUP current monitor calibration]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22082 22082 AIPINJ: 130/200 keV lifetime measurements]
 +
* Transmission vs Gun HV
 +
 +
 
 +
Beam Commissioning
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22180 22180 Gun to Chopper Commissioning _130keV / 200keV beam to PCup]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22181 22181 Early Injector Orbit Data Collection Rev. April/May 2021]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22182 22182 Set up beam from PCup to FC1 at 130keV]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22183 22183 Beam steer from FC1 to FC2]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22184 22184 Efficacy of Knobs chosen for spot move correction]
 +
 
 +
 
 +
Optics/RF Test Plans
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21923 21923 Perform 130keV emittance measurements and matching as part of Injector Upgrade commissioning]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22072 22072 Perform 200keV emittance measurements and matching as part of Injector Upgrade commissioning]
 +
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=19784 19784 Test multiwire emittance measurement with beam]
 +
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/22160 22160 Measure optics at various coil fixture rotation angles for MDR1I02]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22190 22190 RF Elements Setup (Injector Upgrade Phase 1), Lasers phases, Prebuncher, and Choppers]
 +
 
 +
Spin/Wien Test Plans
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22090 22090 Mott Hot Checkout]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22091 22091 Spin Dance to Calibrate Upgraded CEBAF Injector 3D Spin Rotator]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22092 22092 Set 3D Spin Rotator: Flip-Right, Flip-Left, and Vertical Polarizarion]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22083 22083 AIPINJ: Test new hysteresis function for spin solenoids (MFG1I04A/B)]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22084 22084 AIPINJ: 130/200 keV E/B calibrations for V-Wien and H-Wien]
 +
* Beam ToF vs Wien Setting, 130keV and 200keV
 +
 
 +
 
 +
Parity Quality Beam Test Plans
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22040 22040 cathode 45deg rotation and spot moves]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22050 22050 130keV sensitivity test]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22051 22051 200keV sensitivity test]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22052 22052 Transmission test gun 200keV]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22053 22053 RTP pos diff feedback convergence FC2 test]
 +
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22120 22120 Chopper scan 130keV]
 +
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22121 22121 Chopper scan 200keV]
 +
 
 +
 
 +
 
 +
</div>
 +
 
 +
=== Activities ===
 +
<div class="mw-collapsible">
 +
''updated 4/7/21''
 +
 
 +
Test Plans Grouped by Type:
 +
 
 +
[[file:Beam commissioning by type.png | 1000px]]
 +
 
  
 
</div>
 
</div>

Latest revision as of 14:38, 9 April 2021

CIS Jobs Leading to HCO & Commissioning (Jan 1 - Apr 30)

I&C/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30)

I&C Jobs
  • What to expect in tunnel?
    • Similar mechanical layout => Gun + 3 girders (Y + Wien + A1/A2)
    • There is now a 3D CAD model from gun to chopper, I can share pics or see Gary Hays or Shaun Gregory
    • Similar utilities => LCW (A1/A2) + Air (Bubba/Phil) + Cable tray (above/below) + 3 cable drops (Y, Laser, Chopper)

* BPMs = Pete estimates 1 person x 5 days for all of the BPM hook-up and pre-beam checkout jobs

    • 10 total - all unrotated
    • 3 new style => NEG coated large bore (2.5" ID); mapped by Musson (Kx/Ky values available)
    • 7 old style => 5.5" long end tapped
  • Viewers
    • 8 total - all chromox except ITV0I02 (YAG)
    • Crash inhibit #1 : ITV0I01 and Polarized Cup IFY0I01
    • Crash inhibit #2 : ITV0I02 and Harp IHA0I02
  • Harps
    • 1 total - IHA0I02 (YAG), on same cross as viewer ITV0I02 (requires crash inhibit)
  • Wien HV
    • Tony status update

* Current Monitoring - Pete estimates 1 person x 3 days for ItoV, Picoammeters, Gun FSD LCW waterflow interlocks)

    • 3 total - same as before (PCUP, A1, A2)
    • PCUP identical as before, just a new location
    • A1 current monitoring as before, linear bellow motion now has STAC5 motor (so remote or manual; has 3 stop positions
    • A2 current monitoring as before, linear bellows manual as before; has 3 stop positions. Used by PSS group for kicker
  • Valves
    • 3 total - all have in-line EPICS shut over ride capability (CIS installs this box)
    • Gun valve - VBV2I01A (new name), otherwise same all metal gate valve
    • Beam line valve - VBV1I07 (same name), same all metal gate valve
    • Beam line valve - VBV0I02 (same name), but now all metal gate valve, requires cable terminations like VBV1I07
    • All 3 valves tied to UHV vacuum fault (100 uA limit)
Software Jobs
  • CED
    • Michele or Gary can gives us an update
  • Apps
    • Injector steering script getting upgrades for Wien/Solenoid controls, also needs update of correctors/bpms
    • Any script that refers to CED elements from Gun to Chopper will need name review, sounds like a big job
  • Screens
    • I guess many screens auto-updated from CED, that's great
    • Like with apps, will need name review; I guess system owners look at their own screens for oddities?
  • What else for software?

Magnet/DC-Power/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30)

DC/Magnet Jobs
Updated MHD field map due from JM/LL to GC
Updated MFX (SW/CW) field map due from RS to GC
Software Jobs
  • CED
  • Apps
  • Screens
  • What else for software?
Other magnet jobs
  • (JM) Complete magnet table I circulated
  • Done(JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
  • (RS/GC) FG solenoid special hysteresis for Gary
  • (RS/MJ) Magnet info for Inj Steer spin calculations
  • (JM/JG) Decision on spare DR fabrication and alignment
  • Done (LL/JK/JM) PSS kicker - does MMF have any responsibility here, maybe just PSS?
  • Done (LL/JM) Second QW measurement, what's the scope here?
  • Done (JM) When is the rotating coil stand ready?
  • (JM/LL) Reconciling MHD discrepancy
  • (LL) Report on QW
  • (LL) Report on HD
  • (LL) Report on PSS kicker


System Readiness / HCO Schedule (April '21)

For detailed plans for a given day, discussed at 830 toolbox meeting every weekday, see CIS Phase 1 work plans

Format: time: System (# of people)

April Mon Tue Wed Thu Fri Sa Su
12th - 16th Morning: Valve Controls (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: Valve Controls (1x)
Morning: ItoV, Pico, FSD (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: Valve Controls (1x)
Morning: ItoV, Pico, FSD (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: ItoV, Pico, FSD (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: ItoV, Pico, FSD (1x)
Afternoon: Magnet Hook-Ups (2x)
Magnet Hook-Ups (2x) Magnet Hook-Ups (2x)
19th - 23rd Morning: BPMs (1x)
Morning: Viewers (1x)
Morning: Harps (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: BPMs (1x)
Morning: Viewers (1x)
Morning: Harps (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: BPMs (1x)
Morning: Viewers (1x)
Morning: Harps (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: BPMs (1x)
Morning: Viewers (1x)
Morning: Harps (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: BPMs (1x)
Morning: Viewers (1x)
Morning: Harps (1x)
Afternoon: Magnet Hook-Ups (2x)
Magnet Hook-Ups/HCO (2x)
Magnet Hook-Ups/HCO (2x)
26th - 30th Magnet HCO (2x)
I&C Float
Magnet HCO (2x)
I&C Float
Magnet HCO (2x)
2B Alignment
Swings: PSS beamline Certs
Magnet HCO (2x)
2B Alignment
Swings: PSS beamline Certs
Magnet HCO (2x) Magnet HCO (2x) Magnet HCO (2x)
  • BPM = Francis
  • Valve Controls = Ketchum
  • ItoV, Picoammeters, Gun FSD Interlocks = Francis
  • Viewers = Norris
  • Harps = Dela Cruz
  • Magnet / DC Power = Coleman
  • 2B Alignment = S&A, Gould
  • PSS = Kowal

Beam Commissioning (May 3 - Jul 2)

Documents, Links, Important Dates

Links:

Documents:

Dates: updated 4/7/21

  • Finalize commissioning plan: April 5th
  • Injector HCO/SR Complete: 5/2
  • Injector Beam Commissioning Begins: 5/3
  • NL/Inj -> Stable 2K: 5/21
  • Full CEBAF PSS Certification: 5/24 - 6/11
  • End of SAD: 7/2
  • Resumption of Physics: Mid-August


ATLis Testplans

updated 4/7/21

General / Catch-All Test Plans


With-Beam Hardware Commissioning Test Plans


Beam Commissioning


Optics/RF Test Plans

Spin/Wien Test Plans


Parity Quality Beam Test Plans


Activities

updated 4/7/21

Test Plans Grouped by Type:

Beam commissioning by type.png


Celebration