==CIS Jobs Leading to HCO & Commissioning (Jan 1 - Apr 30) ==  
 
==CIS Jobs Leading to HCO & Commissioning (Jan 1 - Apr 30) ==  
<div class="mw-collapsible mw-collapsed">
 
 
; 15 deg dipole (Scott)
 
* '''(Done/SW/JG - magnet is ready for install & yes, we will use shims)''' Install on beam line after bake out, then align, do we use shims?
 
* Current sensor for HV interlock installed and tested, ready for DC power, to set limits, fault test
 
* Current sensor for FSD installed and tested, calibrated for FSD card, ready for DC power, to set limits, fault test
 
* Update drawings, screens, document
 
 
; Laser jobs (Shukui/Scott)
 
* Complete outrigger box, install, test with laser room shutter, update LSOP
 
* Flush chiller, decide on PM schedule, fill
 
* Re-install/align Pockels cell
 
* Re-install Hall B amp in permanent location
 
* Complete macropulse chassis upgrade (replace 18 VDC + booster with 24 VDC, add protection diode to shutters), test all beam modes
 
* Update drawings, document
 
 
; Gun HVPS jobs (Carlos/Bubba/Scott)
 
* Prep for HV & conditioning (SF6, tank, DILO, cables), check HV interlock made up, HVPS setpoints/controls ready
 
* Regrease ceramic after bake
 
* Make sure back-up electrode is available
 
* Remove old HV parts (150kV glassman, old HV interlock chassis, VME interface card), once we can make HV again ... temp replace with Ortec bias PS (if needed)
 
* Pull additional Anode bias HV cable near Glassman rack, I think that's where we ultimately want to bias PS star ground to HVPS, also to patch to QE scan ammeter
 
* Develop HV commissioning plan/staffing
 
**[[Media:Gun2 Tee electrode 200kV HV codnitoning plan 2021 draft01.pptx]]
 
 
; Wien HVPS (Carlos, Scott, Riad)
 
* '''(Done)''' Add placards to ISB racks
 
* Install HV Switcher chassis at ISB, complete cabling between rack components
 
* Drop/pull HV cables from HV switcher outputs to Wiens
 
* Wien EDM and InjSteer screens updates with HVPS and new PS epics values, tested, ready
 
* Update screens, drawings, document
 
 
; Ion Pump Power Supplies (<strike>Scott</strike>, Marcy, EES)
 
* '''(Done)''' Finalize IP names for songsheet [[media:210209_ion pump names.xlsx]]
 
* Complete mapping between all IP and power supplies (gun to choppers)
 
* Complete UHV power supply upgrade, remove temp PS, spare PS on shelf (identify cabinet area for spares): This is Jim Kortze & co., not planned for this down?
 
* Work with software to reprogram UHV PS EPICS names, can we have unique identifier from old names?
 
* Re-install (2) HV patch boxes, update box labels, pull HV drop cables to patch boxes, updated labels
 
* Update screens, drawings, document
 
 
; Vacuum (Marcy, Phil)
 
* '''(Done)'''Bake gun, fix scheme for Kr processing beforehand
 
* Bake aperture girder beam line, activate NEGs
 
* Bake wien and y chamber girders, activate NEGs
 
** Make cables to activate Y chamber NEG pumps during bakeout (draw up and send to Fab)
 
* Activate beam line NEGs for DP stations downstream of chopper
 
* Hi-pot any FE-er pumps
 
* Set voltage for all pumps
 
* Activate Prep NEG to overboard (done), bake if needed (Joe: see if cathode activates in prep chamber? No water in RGA scan)
 
 
; Valves (Scott, Phil)
 
* '''(Done)'''Work with I&C and software, controls for (3) valves (note - confirm valve type different)
 
* Build, install, test (3) shut-override boxes for valves
 
* UHV vacuum fault (series, yes?) shuts all three gate valves, test
 
* Gun2 valve open required for HV enable; method to jumper/bypass for HV conditioning (i.e. valve closed, but HV enable OK)
 
* Update drawings, document
 
 
; Air, GN2, LCW (Phil, Bubba)
 
* '''(Done)'''Move GN2 near gun lower, hook for air lines, caps for poly hose
 
* '''(Done)'''Add 2nd GN2 near girder, hook for air lines, caps for poly hose
 
* Fabricate, install air manifold w/ cutoff for (8) viewers, (2) valves, (2) spares
 
* (done) Re-install LCW manifold
 
 
; Crash inhibit (Scott, Phil)
 
* Install, test crash inhibit for pcup and viewer (note - fail safe test, i.e. do NOT hook up air to BOTH devices)
 
* Install, test crash inhibit for harp and viewer (note - does this exist, would speak to I&C early on)
 
 
; Apertures & PCup (Phil, Scott)
 
* Scribe new aperture stops, bag, store in tunnel, throw away ALL old stops
 
* Install shoulder bolt on A1, test
 
* Attach current monitoring w/ inline I&C protection boxes
 
* Reconnect LCW, I&C check flow meters clear interlock
 
 
; Electrician jobs (Scott)
 
* Relocate floor outlets (done)
 
* Bond girders (Shaun has holes drilled on girders already for this)
 
* Install cable tray
 
  
; Decarad (Carlos, Scott)
+
* 4/19/21 - Updated punchlist [[media:210419_CIS_HCO.docx]]
* Tally # of heads for gun (Carlos) and beam line (Alicia)
+
* 4/06/21 - Updated punchlist [[media:210406_CIS_HCO.docx]]
* Mount decarad chassis, dress signal/HV cables
+
* 3/22/21 - Updated punchlist [[media:210322_CIS_HCO_v2.docx]]
 
+
</div>
+
  
 
==I&C/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30) ==
 
==I&C/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30) ==
Line 145: Line 66:
  
 
; DC/Magnet Jobs
 
; DC/Magnet Jobs
 +
* Spreadsheet updated 3/15 [[media:210315_Phase1_Magnet_Summary.xlsx]]
 +
::Updated MHD field map due from JM/LL to GC
 +
::Updated MFX (SW/CW) field map due from RS to GC
 
* Spreadsheet updated after further feedback [[media:210301_Phase1_Magnet_Summary_v3.xlsx]]
 
* Spreadsheet updated after further feedback [[media:210301_Phase1_Magnet_Summary_v3.xlsx]]
 
* Spreadsheet updated at 3/1 SAD planning meeting [[media:210301_Phase1_Magnet_Summary_v2.xlsx]]
 
* Spreadsheet updated at 3/1 SAD planning meeting [[media:210301_Phase1_Magnet_Summary_v2.xlsx]]
Line 156: Line 80:
  
 
; Other magnet jobs
 
; Other magnet jobs
*(JM) Complete magnet table I circulated
+
* (JM) Complete magnet table I circulated
*(JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
+
* '''Done'''(JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
*(RS/GC) FG solenoid special hysteresis for Gary
+
* (RS/GC) FG solenoid special hysteresis for Gary
*(RS/MJ) Magnet info for Inj Steer spin calculations
+
* (RS/MJ) Magnet info for Inj Steer spin calculations
*(JM/JG) Decision on spare DR fabrication and alignment
+
* (JM/JG) Decision on spare DR fabrication and alignment
*(LL/JK/JM) PSS kicker -  does MMF have any responsibility here, maybe just PSS?
+
* '''Done''' (LL/JK/JM) PSS kicker -  does MMF have any responsibility here, maybe just PSS?
*(LL/JM) Second QW measurement, what's the scope here?
+
* '''Done''' (LL/JM) Second QW measurement, what's the scope here?
*(JM) When is the rotating coil stand ready?
+
* '''Done''' (JM) When is the rotating coil stand ready?
*(JM/LL) Reconciling MHD discrepancy
+
* (JM/LL) Reconciling MHD discrepancy
*(LL) Report on QW
+
* (LL) Report on QW
*(LL) Report on HD
+
* (LL) Report on HD
*(LL) Report on PSS kicker
+
* (LL) Report on PSS kicker
  
  
 +
</div>
 +
 +
== System Readiness / HCO Schedule (April '21) ==
 +
<div class="mw-collapsible">
 +
 +
'''For detailed plans for a given day and week, discussed at 830 toolbox meeting every weekday, see [[CIS Phase 1 work plans]]'''
 +
 +
'''Format:''' time: System (# of people)
 +
 +
'''Updated 4/22'''
 +
 +
{| class="wikitable" style="text-align: center"
 +
|-
 +
! style="background-color: #eca1a6" | '''April/May''' !! style="background-color:#eca1a6" | Mon  !! style="background-color:#eca1a6" |  Tue !! style="background-color:#eca1a6" |  Wed !! style="background-color:#eca1a6" |  Thu !! style="background-color:#eca1a6" |  Fri !! style="background-color:#ada397" |  Sa !! style="background-color:#ada397" |  Su
 +
|- style="background-color:#d6cbd3"
 +
| ! style="background-color:#eca1a6" | '''12th - 16th''' || Morning: Valve Controls (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: Valve Controls (1x) <br> Morning: ItoV, Pico, FSD (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: Valve Controls (1x) <br> Morning: ItoV, Pico, FSD (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: ItoV, Pico, FSD (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: ItoV, Pico, FSD (1x) <br> Afternoon: Magnet Hook-Ups (2x) || !! style="background-color:#ada397" | Magnet Hook-Ups (2x) || !! style="background-color:#ada397" | Magnet Hook-Ups (2x)
 +
|- style="background-color:#bdcebe"
 +
| ! style="background-color:#eca1a6" | '''19th - 23rd'''  || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) ||  Morning: Diagnostics Hook-ups <br> ''as possible''; Leak Checks (CIS) <br> Bake Prep (all) <br> Afternoon: Leak Checks <br> Bake Prep (CIS) || Morning: Diagnostics Hook-ups <br> ''as possible'' <br> Bake Prep (all) <br> Afternoon: Bake Prep (all) || !! style="background-color:#ada397" | ''Magnet Hook-Ups/HCO (2x)?'' <br> || !! style="background-color:#ada397" | ''Magnet Hook-Ups/HCO (2x)?''
 +
|- style="background-color:#d6cbd3"
 +
| ! style="background-color:#eca1a6" | '''26th - 30th''' || '''PCup-A1-region Bake''' <br> Opportunistic Hook-ups <br> ''as possible'' || '''PCup-A1-region Bake''' <br> Opportunistic Hook-ups <br> ''as possible'' || '''PCup-A1-region Bake''' <br> Opportunistic Hook-ups <br> ''as possible'' || '''PCup-A1-region Bake''' <br> Opportunistic Hook-ups <br> ''as possible'' || '''PCup-A1-region Bake''' <br> Opportunistic Hook-ups <br> ''as possible'' || !! style="background-color:#ada397" | ''Magnet HCO (2x)?'' || !! style="background-color:#ada397" | ''Magnet HCO (2x)?''
 +
|- style="background-color:#bdcebe"
 +
| ! style="background-color:#eca1a6" | '''3rd - 7th''' || TBD || TBD || TBD || TBD || TBD || !! style="background-color:#ada397" | TBD || !! style="background-color:#ada397" | TBD
 +
|- style="background-color:#bdcebe"
 +
| ! style="background-color:#eca1a6" | '''10th - 14th''' || TBD || TBD || TBD || TBD || TBD || !! style="background-color:#ada397" | TBD || !! style="background-color:#ada397" | TBD
 +
|- style="background-color:#bdcebe"
 +
|}
 +
 +
* BPM = Francis
 +
* Valve Controls = Ketchum
 +
* ItoV, Picoammeters, Gun FSD Interlocks = Francis
 +
* Viewers = Norris
 +
* Harps = Dela Cruz
 +
* Magnet / DC Power = Coleman
 +
* 2B Alignment = S&A, Gould
 +
* PSS = Kowal
  
 
</div>
 
</div>
  
== Beam Commissioning (May 3 - Jul 2) ==
+
== Beam Commissioning Planning ==
 
<div class="mw-collapsible mw-collapsed">
 
<div class="mw-collapsible mw-collapsed">
  
 +
=== Documents, Links, Important Dates ===
  
=== Important Dates ===
+
Links:
''updated 3/1/21''
+
* [https://wiki.jlab.org/ciswiki/index.php/January_25,_2021_-_Weekly_Commissioning_Meetings 1/25/21 Beam Drivers Preliminary Meeting]
* Injector HCO/SR Complete: 5/3
+
* [https://jeffersonlab.sharepoint.com/sites/CEBAFInjectorSetupProceduresDevelopment Injector Procedures Workspace]
 +
 
 +
Documents:
 +
* 3/16/21 Beam Drivers Meeting Slides [[media:BeamDrivers_Pt2_3.16.21.pdf]]
 +
* Injector Group Beam Commissioning Slides [[file:BeamINJphase1v5.pptx]]
 +
 
 +
* Commissioning Checklist (Grames) [[file:210401_Phase1_Commissioning.docx]]
 +
* (incomplete / in-progress) Commissioning Checklist, ATLiss added [[file:210407 Phase1 Commissioning.docx]]
 +
* Preliminary Commissioning Test Plan Layout [[file:3.31.21 BeamCommissioningPlanLayout AIPINJ-1 firstpass.ods]]
 +
 
 +
Dates:
 +
''updated 4/7/21''
 +
* '''Finalize commissioning plan: April 5th'''
 +
* Injector HCO/SR Complete: 5/2
 +
* Injector Beam Commissioning Begins: 5/3
 
* NL/Inj -> Stable 2K: 5/21
 
* NL/Inj -> Stable 2K: 5/21
 
* Full CEBAF PSS Certification: 5/24 - 6/11
 
* Full CEBAF PSS Certification: 5/24 - 6/11
Line 186: Line 160:
  
  
=== Activities ===
 
''updated 3/1/21''
 
  
[[File:Commissioning testplans Rev2.png | 999px]]
+
=== ATLis Testplans ===
 +
<div class="mw-collapsible">
 +
''updated 4/7/21''
  
 +
General / Catch-All Test Plans
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22060 22060 Beam Commissioning AIPINJ Phase I (general ATLis)]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21170 Injector Upgrade - Phase 1 Installation (Gun to Chopper)]
  
=== ATLis Testplans ===
 
''updated 3/1/21''
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21911 21911 Gun high voltage conditioning]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21923 21923 Perform 130keV emittance measurements and matching as part of Injector Upgrade commissioning]
 
  
 +
With-Beam Hardware Commissioning Test Plans
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22061 22061 PSS Kicker Tests @ 130keV & 200keV]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22080 22080 AIPINJ: 130/200 keV HVPS vs. PCUP current monitor calibration]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22082 22082 AIPINJ: 130/200 keV lifetime measurements]
 +
* Transmission vs Gun HV
 +
 +
 +
Beam Commissioning
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22180 22180 Gun to Chopper Commissioning _130keV / 200keV beam to PCup]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22181 22181 Early Injector Orbit Data Collection Rev. April/May 2021]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22182 22182 Set up beam from PCup to FC1 at 130keV]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22183 22183 Beam steer from FC1 to FC2]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22184 22184 Efficacy of Knobs chosen for spot move correction]
 +
 +
 +
Optics/RF Test Plans
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21923 21923 Perform 130keV emittance measurements and matching as part of Injector Upgrade commissioning]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22072 22072 Perform 200keV emittance measurements and matching as part of Injector Upgrade commissioning]
 +
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=19784 19784 Test multiwire emittance measurement with beam]
 +
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/22160 22160 Measure optics at various coil fixture rotation angles for MDR1I02]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22190 22190 RF Elements Setup (Injector Upgrade Phase 1), Lasers phases, Prebuncher, and Choppers]
 +
 +
Spin/Wien Test Plans
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22090 22090 Mott Hot Checkout]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22091 22091 Spin Dance to Calibrate Upgraded CEBAF Injector 3D Spin Rotator]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22092 22092 Set 3D Spin Rotator: Flip-Right, Flip-Left, and Vertical Polarizarion]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22083 22083 AIPINJ: Test new hysteresis function for spin solenoids (MFG1I04A/B)]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22084 22084 AIPINJ: 130/200 keV E/B calibrations for V-Wien and H-Wien]
 +
* Beam ToF vs Wien Setting, 130keV and 200keV
 +
 +
 +
Parity Quality Beam Test Plans
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22040 22040 cathode 45deg rotation and spot moves]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22050 22050 130keV sensitivity test]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22051 22051 200keV sensitivity test]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22052 22052 Transmission test gun 200keV]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22053 22053 RTP pos diff feedback convergence FC2 test]
 +
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22120 22120 Chopper scan 130keV]
 +
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22121 22121 Chopper scan 200keV]
 +
 +
 +
[[file:Beam commissioning by type.png | 1000px]]
 +
 +
</div>
 +
</div>
 +
 +
== Beam Commissioning Schedule ==
 +
 +
<div class="mw-collapsible">
 +
 +
'''Beam Commissioning Week #1'''
 +
 +
{| class="wikitable" style="text-align:center; background-color:#daebe8;"
 +
|- style="font-weight:bold; background-color:#87bdd8;"
 +
! style="background-color:#87bdd8" | DAY Shift
 +
! style="background-color:#87bdd8" | Monday <br />5/3
 +
! style="background-color:#87bdd8" | Tuesday <br />5/4
 +
! style="background-color:#87bdd8" | Wednesday<br />5/5
 +
! style="background-color:#87bdd8" | Thursday <br />5/6
 +
! style="background-color:#87bdd8" | Friday<br />5/7
 +
! style="background-color:#87bdd8" | Sat<br />5/8
 +
! style="background-color:#87bdd8" | Sun<br />5/9
 +
! style="background-color:#87bdd8;" | Notes
 +
|- style="background-color:#cfe0e8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Beam  Commissioning Plans / ATLis
 +
| pre-beam checks, 22180
 +
| 22180
 +
| 22061, 22182
 +
| 22182
 +
| 22181 | 22184
 +
|
 +
|
 +
|
 +
|- style="background-color:#cfe0e8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Scientist #1
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|- style="background-color:#cfe0e8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Scientist #2
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|- style="background-color:#cfe0e8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Ops Inj Support
 +
| Forman
 +
| Forman
 +
| Forman
 +
| Forman
 +
| Forman
 +
|
 +
|
 +
|
 +
|- style="background-color:#cfe0e8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | SSO / AM Sweeper
 +
| Moser / Price
 +
| Moser / Price
 +
| Moser / Price
 +
| Moser / Price
 +
| Moser / Price
 +
|
 +
|
 +
|
 +
|- style="background-color:#CFE0E8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Other MCC Work, Group, +Persons in MCC
 +
| style="background-color:#cfe0e8;" | NL PSS Commissioning, SSG, +2
 +
| NL PSS Commissioning, SSG, +2
 +
| NL PSS Commissioning, SSG, +2
 +
| NL PSS Commissioning, SSG, +2
 +
| NL PSS Commissioning, SSG, +2
 +
| style="background-color:#cfe0e8;" |
 +
| style="background-color:#cfe0e8;" |
 +
| style="background-color:#cfe0e8;" |
 +
|- style="font-weight:bold; background-color:#70aaaf;"
 +
| style="color:#000000;" | SWING Shift
 +
| style="color:#000000;" | 5/3
 +
| style="color:#000000;" | 5/4
 +
| style="color:#000000;" | 5/5
 +
| style="color:#000000;" | 5/6
 +
| style="color:#000000;" | 5/7
 +
| style="color:#000000;" | 5/8
 +
| style="color:#000000;" | 5/9
 +
| Notes
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | Beam Commissioning Plan / ATLis
 +
| 22180
 +
| 22180
 +
| 22182
 +
| 22182, 22181
 +
| 22182 | 22184
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | Scientist #1
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | Scientist #2
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | Ops Inj Support
 +
| Law
 +
| Law
 +
| Law
 +
| Law
 +
| Law
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | SSO
 +
| Anthony
 +
| Anthony
 +
| Anthony
 +
| Anthony
 +
| Anthony
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | Other MCC Work, Group, +Persons in MCC
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | CCOC / PD
 +
| Aiken / Stavola
 +
| Aiken /  Stavola
 +
| Aiken (both)
 +
| Aiken
 +
| Aiken
 +
| Aiken
 +
| Aiken
 +
|
 +
|}
 +
 +
 +
'''Beam Commissioning Week #2'''
 +
 +
{| class="wikitable" style="text-align:center; background-color:#daebe8;"
 +
|- style="font-weight:bold; background-color:#87bdd8;"
 +
! style="background-color:#87bdd8;" | DAY Shift
 +
! style="background-color:#87bdd8;" | Monday <br />5/10
 +
! style="background-color:#87bdd8;" | Tuesday <br />5/11
 +
! style="background-color:#87bdd8;" | Wednesday<br />5/12
 +
! style="background-color:#87bdd8;" | Thursday <br />5/13
 +
! style="background-color:#87bdd8;" | Friday<br />5/14
 +
! style="background-color:#87bdd8;" | Sat<br />5/15
 +
! style="background-color:#87bdd8;" | Sun<br />5/16
 +
! style="background-color:#87bdd8;" | Notes
 +
|- style="background-color:#cfe0e8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Beam  Commissioning Plans / ATLis
 +
| 22182 | 22184
 +
| 22182, 22080
 +
| 22190
 +
| 22160
 +
| 22250
 +
|
 +
|
 +
|
 +
|- style="background-color:#cfe0e8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Scientist #1
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|- style="background-color:#cfe0e8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Scientist #2
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|- style="background-color:#cfe0e8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Ops Inj Support
 +
| Forman
 +
| Forman
 +
| Forman
 +
| Forman
 +
| Forman
 +
|
 +
|
 +
|
 +
|- style="background-color:#cfe0e8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | SSO / AM Sweeper
 +
| Carlino / Jones
 +
| Carlino / Jones
 +
| Carlino / Jones
 +
| Carlino / Jones
 +
| Carlino / Jones
 +
|
 +
|
 +
|
 +
|- style="background-color:#CFE0E8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Other MCC Work, Group, +Persons in MCC
 +
| style="background-color:#cfe0e8;" | NL PSS Commissioning, SSG, +2
 +
| NL PSS Commissioning, SSG, +2
 +
| NL PSS Commissioning, SSG, +2
 +
| NL PSS Commissioning, SSG, +2
 +
| NL PSS Commissioning, SSG, +2
 +
| style="background-color:#cfe0e8;" |
 +
| style="background-color:#cfe0e8;" |
 +
| style="background-color:#cfe0e8;" |
 +
|- style="font-weight:bold; background-color:#70aaaf;"
 +
| style="color:#000000;" | SWING Shift
 +
| style="color:#000000;" | 5/10
 +
| style="color:#000000;" | 5/11
 +
| style="color:#000000;" | 5/12
 +
| style="color:#000000;" | 5/13
 +
| style="color:#000000;" | 5/14
 +
| style="color:#000000;" | 5/15
 +
| style="color:#000000;" | 5/16
 +
| Notes
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | Beam Commissioning Plan / ATLis
 +
| 22182
 +
| 22190
 +
| 22190
 +
| 21923
 +
| 21923 | 22082
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | Scientist #1
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | Scientist #2
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | Ops Inj Support
 +
| Law
 +
| Law
 +
| Law
 +
| Law
 +
| Law
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | SSO
 +
| Deir
 +
| Deir
 +
| Deir
 +
| Deir
 +
| Deir
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | Other MCC Work, Group, +Persons in MCC
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | CCOC / PD
 +
| Aiken (both)
 +
| Aiken
 +
| Merz / Aiken
 +
| Merz / Aiken
 +
| Merz / Aiken
 +
| Merz / Aiken
 +
| Merz / Aiken
 +
|
 +
|}
 +
 +
 +
'''Beam Commissioning Week #3'''
 +
 +
{| class="wikitable" style="text-align:center; background-color:#daebe8;"
 +
|- style="font-weight:bold; background-color:#87bdd8;"
 +
! style="background-color:#87bdd8;" | DAY Shift
 +
! style="background-color:#87bdd8;" | Monday <br />5/17
 +
! style="background-color:#87bdd8;" | Tuesday <br />5/18
 +
! style="background-color:#87bdd8;" | Wednesday<br />5/19
 +
! style="background-color:#87bdd8;" | Thursday <br />5/20
 +
! style="background-color:#87bdd8;" | Friday<br />5/21
 +
! style="background-color:#87bdd8;" | Sat<br />5/22
 +
! style="background-color:#87bdd8;" | Sun<br />5/23
 +
! style="background-color:#87bdd8;" | Notes
 +
|- style="background-color:#cfe0e8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Beam  Commissioning Plans / ATLis
 +
| TBD
 +
| TBD
 +
| TBD
 +
| TBD
 +
| TBD
 +
|
 +
|
 +
|
 +
|- style="background-color:#cfe0e8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Scientist #1
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|- style="background-color:#cfe0e8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Scientist #2
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|- style="background-color:#cfe0e8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Ops Inj Support
 +
| TBD: {Forman, Law, Moser}
 +
| TBD: {Forman, Law, Moser}
 +
| TBD: {Forman, Law, Moser}
 +
| TBD: {Forman, Law, Moser}
 +
| TBD: {Forman, Law, Moser}
 +
|
 +
|
 +
|
 +
|- style="background-color:#cfe0e8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | SSO / AM Sweeper
 +
| Gauthier / Moser
 +
| Gauthier / Moser
 +
| Gauthier / Moser
 +
| Gauthier / Moser
 +
| Gauthier / Moser
 +
|
 +
|
 +
|
 +
|- style="background-color:#CFE0E8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Other MCC Work, Group, +Persons in MCC
 +
| style="background-color:#cfe0e8;" | ''NL PSS Commissioning, SSG, +2''
 +
| ''NL PSS Commissioning, SSG, +2''
 +
| ''NL PSS Commissioning, SSG, +2''
 +
| ''NL PSS Commissioning, SSG, +2''
 +
| ''NL PSS Commissioning, SSG, +2''
 +
| style="background-color:#cfe0e8;" |
 +
| style="background-color:#cfe0e8;" |
 +
| style="background-color:#cfe0e8;" |
 +
|- style="font-weight:bold; background-color:#70aaaf;"
 +
| style="color:#000000;" | SWING Shift
 +
| style="color:#000000;" | 5/17
 +
| style="color:#000000;" | 5/18
 +
| style="color:#000000;" | 5/19
 +
| style="color:#000000;" | 5/20
 +
| style="color:#000000;" | 5/21
 +
| style="color:#000000;" | 5/22
 +
| style="color:#000000;" | 5/23
 +
| Notes
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | Beam Commissioning Plan / ATLis
 +
| TBD
 +
| TBD
 +
| TBD
 +
| TBD
 +
| TBD
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | Scientist #1
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | Scientist #2
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | Ops Inj Support
 +
| TBD: {Forman, Law, Moser}
 +
| TBD: {Forman, Law, Moser}
 +
| TBD: {Forman, Law, Moser}
 +
| TBD: {Forman, Law, Moser}
 +
| TBD: {Forman, Law, Moser}
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | SSO
 +
| Anthony
 +
| Anthony
 +
| Anthony
 +
| Anthony
 +
| Anthony
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | Other MCC Work, Group, +Persons in MCC
 +
| ''NL Lock-Up/Commissioning, SSG, +2''
 +
| ''NL Lock-Up/Commissioning, SSG, +2''
 +
| ''NL Lock-Up/Commissioning, SSG, +2''
 +
| ''NL Lock-Up/Commissioning, SSG, +2''
 +
| ''NL Lock-Up/Commissioning, SSG, +2''
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | CCOC / PD
 +
| Merz / Aiken
 +
| Merz / Aiken
 +
| Merz / Frierson
 +
| Merz / Frierson
 +
| Merz / Frierson
 +
| Merz / Frierson
 +
| Merz / Frierson
 +
|
 +
|}
 +
 +
 +
'''CEBAF PSS Certifications''' <br> ''SCMB: Beam Commissioning Week #4?''
 +
 +
{| class="wikitable" style="text-align:center; background-color:#cfe0e8;"
 +
|- style="font-weight:bold; background-color:#87bdd8;"
 +
! style="background-color:#87bdd8;" | DAY Shift<br />*** dependent on SCMB approval ***
 +
! style="background-color:#87bdd8;" | Monday <br />5/24
 +
! style="background-color:#87bdd8;" | Tuesday <br />5/25
 +
! style="background-color:#87bdd8;" | Wednesday<br />5/26
 +
! style="background-color:#87bdd8;" | Thursday <br />5/27
 +
! style="background-color:#87bdd8;" | Friday<br />5/28
 +
! style="background-color:#87bdd8;" | Sat<br />5/29
 +
! style="background-color:#87bdd8;" | Sun<br />5/30
 +
! style="background-color:#87bdd8;" | Notes
 +
|-
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Beam  Commissioning Plans / ATLis
 +
| TBD
 +
| TBD
 +
| TBD
 +
| TBD
 +
| TBD
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Scientist #1
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Scientist #2
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Ops Inj Support
 +
| TBD: {Forman, Law, Moser}
 +
| TBD: {Forman, Law, Moser}
 +
| TBD: {Forman, Law, Moser}
 +
| TBD: {Forman, Law, Moser}
 +
| TBD: {Forman, Law, Moser}
 +
|
 +
|
 +
|
 +
|-
 +
| style="font-weight:bold; background-color:#b7d7e8;" | SSO / AM Sweeper
 +
| Garcia / Moser
 +
| Garcia / Moser
 +
| Garcia / Moser
 +
| Garcia / Moser
 +
| Garcia / Moser
 +
|
 +
|
 +
|
 +
|- style="background-color:#CFE0E8;"
 +
| style="font-weight:bold; background-color:#b7d7e8;" | Other MCC Work, Group, +Persons in MCC
 +
| style="background-color:#cfe0e8;" |
 +
|
 +
|
 +
|
 +
|
 +
| style="background-color:#cfe0e8;" |
 +
| style="background-color:#cfe0e8;" |
 +
| style="background-color:#cfe0e8;" |
 +
|- style="font-weight:bold; background-color:#70aaaf;"
 +
| style="color:#000000;" | SWING Shift
 +
| style="color:#000000;" | 5/24
 +
| style="color:#000000;" | 5/25
 +
| style="color:#000000;" | 5/26
 +
| style="color:#000000;" | 5/27
 +
| style="color:#000000;" | 5/28
 +
| style="color:#000000;" | 5/29
 +
| style="color:#000000;" | 5/30
 +
| Notes
 +
|- style="background-color:#daebe8;"
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | PSS CERTIFICATION
 +
| PSS Certification
 +
| PSS Certification
 +
| PSS Certification
 +
| PSS Certification
 +
| PSS Certification
 +
|
 +
|
 +
|
 +
|- style="font-style:italic; background-color:#daebe8;"
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000; font-style:normal;" | PSS Test Director
 +
| ''TBD Crew Chief''
 +
| ''TBD Crew Chief''
 +
| ''TBD Crew Chief''
 +
| ''TBD Crew Chief''
 +
| ''TBD Crew Chief''
 +
| style="font-style:normal;" |
 +
| style="font-style:normal;" |
 +
| style="font-style:normal;" |
 +
|- style="background-color:#daebe8;"
 +
| style="font-weight:bold; background-color:#96ceb4; color:#000000;" | CCOC / PD
 +
| Merz / Frierson
 +
| Merz / Frierson
 +
| Carlino / Frierson
 +
| Carlino / Frierson
 +
| Carlino / Frierson
 +
| Carlino / Frierson
 +
| Carlino / Frierson
 +
|
 +
|}
  
 
</div>
 
</div>

Latest revision as of 19:21, 22 April 2021

CIS Jobs Leading to HCO & Commissioning (Jan 1 - Apr 30)

I&C/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30)

I&C Jobs
  • What to expect in tunnel?
    • Similar mechanical layout => Gun + 3 girders (Y + Wien + A1/A2)
    • There is now a 3D CAD model from gun to chopper, I can share pics or see Gary Hays or Shaun Gregory
    • Similar utilities => LCW (A1/A2) + Air (Bubba/Phil) + Cable tray (above/below) + 3 cable drops (Y, Laser, Chopper)

* BPMs = Pete estimates 1 person x 5 days for all of the BPM hook-up and pre-beam checkout jobs

    • 10 total - all unrotated
    • 3 new style => NEG coated large bore (2.5" ID); mapped by Musson (Kx/Ky values available)
    • 7 old style => 5.5" long end tapped
  • Viewers
    • 8 total - all chromox except ITV0I02 (YAG)
    • Crash inhibit #1 : ITV0I01 and Polarized Cup IFY0I01
    • Crash inhibit #2 : ITV0I02 and Harp IHA0I02
  • Harps
    • 1 total - IHA0I02 (YAG), on same cross as viewer ITV0I02 (requires crash inhibit)
  • Wien HV
    • Tony status update

* Current Monitoring - Pete estimates 1 person x 3 days for ItoV, Picoammeters, Gun FSD LCW waterflow interlocks)

    • 3 total - same as before (PCUP, A1, A2)
    • PCUP identical as before, just a new location
    • A1 current monitoring as before, linear bellow motion now has STAC5 motor (so remote or manual; has 3 stop positions
    • A2 current monitoring as before, linear bellows manual as before; has 3 stop positions. Used by PSS group for kicker
  • Valves
    • 3 total - all have in-line EPICS shut over ride capability (CIS installs this box)
    • Gun valve - VBV2I01A (new name), otherwise same all metal gate valve
    • Beam line valve - VBV1I07 (same name), same all metal gate valve
    • Beam line valve - VBV0I02 (same name), but now all metal gate valve, requires cable terminations like VBV1I07
    • All 3 valves tied to UHV vacuum fault (100 uA limit)
Software Jobs
  • CED
    • Michele or Gary can gives us an update
  • Apps
    • Injector steering script getting upgrades for Wien/Solenoid controls, also needs update of correctors/bpms
    • Any script that refers to CED elements from Gun to Chopper will need name review, sounds like a big job
  • Screens
    • I guess many screens auto-updated from CED, that's great
    • Like with apps, will need name review; I guess system owners look at their own screens for oddities?
  • What else for software?

Magnet/DC-Power/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30)

DC/Magnet Jobs
Updated MHD field map due from JM/LL to GC
Updated MFX (SW/CW) field map due from RS to GC
Software Jobs
  • CED
  • Apps
  • Screens
  • What else for software?
Other magnet jobs
  • (JM) Complete magnet table I circulated
  • Done(JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
  • (RS/GC) FG solenoid special hysteresis for Gary
  • (RS/MJ) Magnet info for Inj Steer spin calculations
  • (JM/JG) Decision on spare DR fabrication and alignment
  • Done (LL/JK/JM) PSS kicker - does MMF have any responsibility here, maybe just PSS?
  • Done (LL/JM) Second QW measurement, what's the scope here?
  • Done (JM) When is the rotating coil stand ready?
  • (JM/LL) Reconciling MHD discrepancy
  • (LL) Report on QW
  • (LL) Report on HD
  • (LL) Report on PSS kicker


System Readiness / HCO Schedule (April '21)

For detailed plans for a given day and week, discussed at 830 toolbox meeting every weekday, see CIS Phase 1 work plans

Format: time: System (# of people)

Updated 4/22

April/May Mon Tue Wed Thu Fri Sa Su
12th - 16th Morning: Valve Controls (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: Valve Controls (1x)
Morning: ItoV, Pico, FSD (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: Valve Controls (1x)
Morning: ItoV, Pico, FSD (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: ItoV, Pico, FSD (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: ItoV, Pico, FSD (1x)
Afternoon: Magnet Hook-Ups (2x)
Magnet Hook-Ups (2x) Magnet Hook-Ups (2x)
19th - 23rd Morning: BPMs (1x)
Morning: Viewers (1x)
Morning: Harps (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: BPMs (1x)
Morning: Viewers (1x)
Morning: Harps (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: BPMs (1x)
Morning: Viewers (1x)
Morning: Harps (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: Diagnostics Hook-ups
as possible; Leak Checks (CIS)
Bake Prep (all)
Afternoon: Leak Checks
Bake Prep (CIS)
Morning: Diagnostics Hook-ups
as possible
Bake Prep (all)
Afternoon: Bake Prep (all)
Magnet Hook-Ups/HCO (2x)?
Magnet Hook-Ups/HCO (2x)?
26th - 30th PCup-A1-region Bake
Opportunistic Hook-ups
as possible
PCup-A1-region Bake
Opportunistic Hook-ups
as possible
PCup-A1-region Bake
Opportunistic Hook-ups
as possible
PCup-A1-region Bake
Opportunistic Hook-ups
as possible
PCup-A1-region Bake
Opportunistic Hook-ups
as possible
Magnet HCO (2x)? Magnet HCO (2x)?
3rd - 7th TBD TBD TBD TBD TBD TBD TBD
10th - 14th TBD TBD TBD TBD TBD TBD TBD
  • BPM = Francis
  • Valve Controls = Ketchum
  • ItoV, Picoammeters, Gun FSD Interlocks = Francis
  • Viewers = Norris
  • Harps = Dela Cruz
  • Magnet / DC Power = Coleman
  • 2B Alignment = S&A, Gould
  • PSS = Kowal

Beam Commissioning Planning

Documents, Links, Important Dates

Links:

Documents:

Dates: updated 4/7/21

  • Finalize commissioning plan: April 5th
  • Injector HCO/SR Complete: 5/2
  • Injector Beam Commissioning Begins: 5/3
  • NL/Inj -> Stable 2K: 5/21
  • Full CEBAF PSS Certification: 5/24 - 6/11
  • End of SAD: 7/2
  • Resumption of Physics: Mid-August


ATLis Testplans

updated 4/7/21

General / Catch-All Test Plans


With-Beam Hardware Commissioning Test Plans


Beam Commissioning


Optics/RF Test Plans

Spin/Wien Test Plans


Parity Quality Beam Test Plans


Beam commissioning by type.png

Beam Commissioning Schedule

Beam Commissioning Week #1

DAY Shift Monday
5/3
Tuesday
5/4
Wednesday
5/5
Thursday
5/6
Friday
5/7
Sat
5/8
Sun
5/9
Notes
Beam Commissioning Plans / ATLis pre-beam checks, 22180 22180 22061, 22182 22182 22184
Scientist #1
Scientist #2
Ops Inj Support Forman Forman Forman Forman Forman
SSO / AM Sweeper Moser / Price Moser / Price Moser / Price Moser / Price Moser / Price
Other MCC Work, Group, +Persons in MCC NL PSS Commissioning, SSG, +2 NL PSS Commissioning, SSG, +2 NL PSS Commissioning, SSG, +2 NL PSS Commissioning, SSG, +2 NL PSS Commissioning, SSG, +2
SWING Shift 5/3 5/4 5/5 5/6 5/7 5/8 5/9 Notes
Beam Commissioning Plan / ATLis 22180 22180 22182 22182, 22181 22184
Scientist #1
Scientist #2
Ops Inj Support Law Law Law Law Law
SSO Anthony Anthony Anthony Anthony Anthony
Other MCC Work, Group, +Persons in MCC
CCOC / PD Aiken / Stavola Aiken / Stavola Aiken (both) Aiken Aiken Aiken Aiken


Beam Commissioning Week #2

DAY Shift Monday
5/10
Tuesday
5/11
Wednesday
5/12
Thursday
5/13
Friday
5/14
Sat
5/15
Sun
5/16
Notes
Beam Commissioning Plans / ATLis 22184 22182, 22080 22190 22160 22250
Scientist #1
Scientist #2
Ops Inj Support Forman Forman Forman Forman Forman
SSO / AM Sweeper Carlino / Jones Carlino / Jones Carlino / Jones Carlino / Jones Carlino / Jones
Other MCC Work, Group, +Persons in MCC NL PSS Commissioning, SSG, +2 NL PSS Commissioning, SSG, +2 NL PSS Commissioning, SSG, +2 NL PSS Commissioning, SSG, +2 NL PSS Commissioning, SSG, +2
SWING Shift 5/10 5/11 5/12 5/13 5/14 5/15 5/16 Notes
Beam Commissioning Plan / ATLis 22182 22190 22190 21923 22082
Scientist #1
Scientist #2
Ops Inj Support Law Law Law Law Law
SSO Deir Deir Deir Deir Deir
Other MCC Work, Group, +Persons in MCC
CCOC / PD Aiken (both) Aiken Merz / Aiken Merz / Aiken Merz / Aiken Merz / Aiken Merz / Aiken


Beam Commissioning Week #3

DAY Shift Monday
5/17
Tuesday
5/18
Wednesday
5/19
Thursday
5/20
Friday
5/21
Sat
5/22
Sun
5/23
Notes
Beam Commissioning Plans / ATLis TBD TBD TBD TBD TBD
Scientist #1
Scientist #2
Ops Inj Support TBD: {Forman, Law, Moser} TBD: {Forman, Law, Moser} TBD: {Forman, Law, Moser} TBD: {Forman, Law, Moser} TBD: {Forman, Law, Moser}
SSO / AM Sweeper Gauthier / Moser Gauthier / Moser Gauthier / Moser Gauthier / Moser Gauthier / Moser
Other MCC Work, Group, +Persons in MCC NL PSS Commissioning, SSG, +2 NL PSS Commissioning, SSG, +2 NL PSS Commissioning, SSG, +2 NL PSS Commissioning, SSG, +2 NL PSS Commissioning, SSG, +2
SWING Shift 5/17 5/18 5/19 5/20 5/21 5/22 5/23 Notes
Beam Commissioning Plan / ATLis TBD TBD TBD TBD TBD
Scientist #1
Scientist #2
Ops Inj Support TBD: {Forman, Law, Moser} TBD: {Forman, Law, Moser} TBD: {Forman, Law, Moser} TBD: {Forman, Law, Moser} TBD: {Forman, Law, Moser}
SSO Anthony Anthony Anthony Anthony Anthony
Other MCC Work, Group, +Persons in MCC NL Lock-Up/Commissioning, SSG, +2 NL Lock-Up/Commissioning, SSG, +2 NL Lock-Up/Commissioning, SSG, +2 NL Lock-Up/Commissioning, SSG, +2 NL Lock-Up/Commissioning, SSG, +2
CCOC / PD Merz / Aiken Merz / Aiken Merz / Frierson Merz / Frierson Merz / Frierson Merz / Frierson Merz / Frierson


CEBAF PSS Certifications
SCMB: Beam Commissioning Week #4?

DAY Shift
*** dependent on SCMB approval ***
Monday
5/24
Tuesday
5/25
Wednesday
5/26
Thursday
5/27
Friday
5/28
Sat
5/29
Sun
5/30
Notes
Beam Commissioning Plans / ATLis TBD TBD TBD TBD TBD
Scientist #1
Scientist #2
Ops Inj Support TBD: {Forman, Law, Moser} TBD: {Forman, Law, Moser} TBD: {Forman, Law, Moser} TBD: {Forman, Law, Moser} TBD: {Forman, Law, Moser}
SSO / AM Sweeper Garcia / Moser Garcia / Moser Garcia / Moser Garcia / Moser Garcia / Moser
Other MCC Work, Group, +Persons in MCC
SWING Shift 5/24 5/25 5/26 5/27 5/28 5/29 5/30 Notes
PSS CERTIFICATION PSS Certification PSS Certification PSS Certification PSS Certification PSS Certification
PSS Test Director TBD Crew Chief TBD Crew Chief TBD Crew Chief TBD Crew Chief TBD Crew Chief
CCOC / PD Merz / Frierson Merz / Frierson Carlino / Frierson Carlino / Frierson Carlino / Frierson Carlino / Frierson Carlino / Frierson

Celebration