Phase 1 - HCO & Commissioning

From Ciswikidb
Revision as of 06:38, 10 February 2021 by Grames (talk | contribs)
Jump to navigation Jump to search

Jobs Leading to HCO & Commissioning

15 deg dipole (MDR)
  • Install on beam line after bake out, then align, do we use shims?
  • Current sensor for HV interlock installed and tested, ready for DC power, to set limits, fault test
  • Current sensor for FSD installed and tested, calibrated for FSD card, ready for DC power, to set limits, fault test
  • Update drawings and documentation
Laser jobs
  • Complete outrigger box, install, test with laser room shutter, update LSOP
  • Flush chiller, decide on PM schedule, fill
  • Re-install Hall B amp in permanent location
  • Complete macropulse chassis upgrade (replace 18 VDC + booster with 24 VDC, add protection diode to shutters), test all beam modes
Wien HVPS
  • (done) Add placards to ISB racks
  • Install HV Switcher chassis at ISB, complete cabling between rack components
  • Drop/pull HV cables from HV switcher outputs to Wiens
Ion Pump Power Supplies
  • (done) Finalize IP names for songsheet
  • Complete mapping between all IP and power supplies (gun to choppers)
  • Complete UHV power supply upgrade, remove temp PS, spare PS on shelf (identify cabinet area for spares)
  • Work with software to reprogram UHV PS EPICS names, can we have unique identifier from old names?
  • Re-install (2) HV patch boxes, update box labels, pull HV drop cables to patch boxes, updated labels
Valves
  • Controls for (3) gate valves
Air, GN2, LCW
  • Move GN2 near gun lower, hook for air lines, caps for poly hose
  • Add 2nd GN2 near girder, hook for air lines, caps for poly hose
  • Fabricate, install air manifold for viewers and valves
  • (done) Re-install LCW manifold
Electrician jobs
  • Relocate floor outlets
  • Bond girders (Shaun has holes drilled on girders already for this)
  • Install cable tray