Phase 1 - HCO & Commissioning

From Ciswikidb
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

CIS Jobs Leading to HCO & Commissioning (Jan 1 - Apr 30)

15 deg dipole (Scott)
  • (Scott working with CAD/DCG) Update drawings and document
Laser jobs (Shukui/Scott)
  • (Shaun...) Complete outrigger box, install, test with laser room shutter
  • (Shukui) Update LSOP
  • (Shukui/Amali) Install/align Pockels cell
  • (Shukui) Re-install Hall B amp in permanent location
  • (Scott) Complete macropulse chassis upgrade, test all beam modes
Gun HVPS jobs (Carlos/Bubba/Scott)
Wien HVPS
  • (Tony/Carlos) Drop/pull HV cables from HV switcher outputs to Wiens
  • (Riad) InjSteer screens check/test with Gary and Michelle updates with HVPS and new PS epics values, tested, ready
  • (Carlos wrap up with engineering) drawings, document
Ion Pump Power Supplies media:210209_ion pump names.xlsx
  • (Scott) Re-install (2) HV patch boxes, update box labels, pull HV drop cables to patch boxes, updated labels
  • (Scott) Update screens, labels, drawings, document
Vacuum
  • (Marcy/Phil) A1/A2 : Install, leak check, bake, leak check
  • (Marcy/Phil) Wien : Install, leak check, bake, leak check
  • (Marcy) Add extractor gauge to y chamber port
  • (Marcy) Fab cable for Y-NEG activation
  • (Marcy/Phil) Activate DP can downstream FC#1
  • (Marcy) Set final IP voltages (no FE'ers)
  • (Joe test by 3/12) see if cathode activates in prep chamber. If not, bake (No water in RGA scan)
Valves
  • (Scott) HCO UHV vacuum fault
  • (Scott) Update drawings, labels, document
Air, GN2, LCW
  • (Phil/Bubba) Fabricate, install air manifold w/ cutoff for (8) viewers, (2) valves, (2) spares
  • (Ricky to fasten) Fasten LCW to pedestals
Crash inhibit
  • (Tony/Phil) Install, test crash inhibit for pcup and viewer (note - fail safe test, i.e. do NOT hook up air to BOTH devices)
  • (Tony/Phil) Install, test crash inhibit for harp and viewer (note - does this exist, would speak to I&C early on)
Apertures & PCup
  • (Scott after bake) Terminate A1 cable, drive motor, test shoulder bolt
  • (Phil) Put new scribed aperture stops in bag in tunnel
  • (Pete/Phil) Attach current monitoring w/ inline I&C protection boxes
  • (Pete/Phil) Reconnect LCW, I&C check flow meters clear interlock
Electrician jobs
  • (Electricians/Scott) Bond girders
  • (Scott working on this) Install cable tray on girders
Decarad
  • (Scott) Install/cable 1 chassis, (5) for Carlos, (5) for Joe

I&C/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30)

I&C Jobs
  • What to expect in tunnel?
    • Similar mechanical layout => Gun + 3 girders (Y + Wien + A1/A2)
    • There is now a 3D CAD model from gun to chopper, I can share pics or see Gary Hays or Shaun Gregory
    • Similar utilities => LCW (A1/A2) + Air (Bubba/Phil) + Cable tray (above/below) + 3 cable drops (Y, Laser, Chopper)

* BPMs = Pete estimates 1 person x 5 days for all of the BPM hook-up and pre-beam checkout jobs

    • 10 total - all unrotated
    • 3 new style => NEG coated large bore (2.5" ID); mapped by Musson (Kx/Ky values available)
    • 7 old style => 5.5" long end tapped
  • Viewers
    • 8 total - all chromox except ITV0I02 (YAG)
    • Crash inhibit #1 : ITV0I01 and Polarized Cup IFY0I01
    • Crash inhibit #2 : ITV0I02 and Harp IHA0I02
  • Harps
    • 1 total - IHA0I02 (YAG), on same cross as viewer ITV0I02 (requires crash inhibit)
  • Wien HV
    • Tony status update

* Current Monitoring - Pete estimates 1 person x 3 days for ItoV, Picoammeters, Gun FSD LCW waterflow interlocks)

    • 3 total - same as before (PCUP, A1, A2)
    • PCUP identical as before, just a new location
    • A1 current monitoring as before, linear bellow motion now has STAC5 motor (so remote or manual; has 3 stop positions
    • A2 current monitoring as before, linear bellows manual as before; has 3 stop positions. Used by PSS group for kicker
  • Valves
    • 3 total - all have in-line EPICS shut over ride capability (CIS installs this box)
    • Gun valve - VBV2I01A (new name), otherwise same all metal gate valve
    • Beam line valve - VBV1I07 (same name), same all metal gate valve
    • Beam line valve - VBV0I02 (same name), but now all metal gate valve, requires cable terminations like VBV1I07
    • All 3 valves tied to UHV vacuum fault (100 uA limit)
Software Jobs
  • CED
    • Michele or Gary can gives us an update
  • Apps
    • Injector steering script getting upgrades for Wien/Solenoid controls, also needs update of correctors/bpms
    • Any script that refers to CED elements from Gun to Chopper will need name review, sounds like a big job
  • Screens
    • I guess many screens auto-updated from CED, that's great
    • Like with apps, will need name review; I guess system owners look at their own screens for oddities?
  • What else for software?

Magnet/DC-Power/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30)

DC/Magnet Jobs
Updated MHD field map due from JM/LL to GC
Updated MFX (SW/CW) field map due from RS to GC
Software Jobs
  • CED
  • Apps
  • Screens
  • What else for software?
Other magnet jobs
  • (JM) Complete magnet table I circulated
  • Done(JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
  • (RS/GC) FG solenoid special hysteresis for Gary
  • (RS/MJ) Magnet info for Inj Steer spin calculations
  • (JM/JG) Decision on spare DR fabrication and alignment
  • Done (LL/JK/JM) PSS kicker - does MMF have any responsibility here, maybe just PSS?
  • Done (LL/JM) Second QW measurement, what's the scope here?
  • Done (JM) When is the rotating coil stand ready?
  • (JM/LL) Reconciling MHD discrepancy
  • (LL) Report on QW
  • (LL) Report on HD
  • (LL) Report on PSS kicker


System Readiness / HCO Schedule (Apr 5 - Apr 30)

Format: time: System (# of people)

April Mon Tue Wed Thu Fri Sa Su
5th - 9th 5a-noon: BPMs (1x)
5a-noon: Viewers (1x)
8a-4p: DC Power (2x)
5a-noon: BPMs (1x)
5a-noon: Viewers (1x)
8a-4p: DC Power (2x)
5a-noon: BPMs (1x)
5a-noon: Viewers (1x)
8a-4p: DC Power (2x)
5a-noon: BPMs (1x)
8a-4p: DC Power (2x)
5a-noon: BPMs (1x)
8a-4p: DC Power (2x)
Sa Su
12th - 16th 5a-noon: ItoV/Pico/GunFSD (1x)
6a-noon: Harps (1x)
8a-4p: DC Power (2x)
5a-noon: ItoV/Pico/GunFSD (1x)
6a-noon: Harps (1x)
8a-4p: DC Power (2x)
5a-noon: ItoV/Pico/GunFSD (1x)
6a-noon: Harps (1x)
8a-4p: DC Power (2x)
6a-noon: Harps (1x)
8a-4p: DC Power (2x)
6a-noon: Harps (1x)
8a-4p: DC Power (2x)
8a-4p: DC Power (2x) 8a-4p: DC Power (2x)
19th - 23rd 8a-4p: DC Power (2x) 8a-4p: DC Power (2x) 8a-4p: DC Power (2x) 8a-4p: DC Power (2x) 8a-4p: DC Power (2x) Sa Su
26th - 30th Swings: PSS beamline Certs? Swings: PSS beamline Certs? Swings: PSS beamline Certs? R F Sa Su
  • BPM = Francis
  • ItoV, Picoammeters, Gun FSD Interlocks = Francis
  • Viewers = Norris
  • Harps = Dela Cruz
  • DC Power = Coleman, others in group; heavily in afternoons


Beam Commissioning (May 3 - Jul 2)

Important Dates

updated 3/15/21

  • Finalize commissioning plan: April 5th
  • Injector HCO/SR Complete: 5/2
  • Injector Beam Commissioning Begins: 5/3
  • NL/Inj -> Stable 2K: 5/21
  • Full CEBAF PSS Certification: 5/24 - 6/11
  • End of SAD: 7/2
  • Resumption of Physics: Mid-August

ATLis Testplans

updated 3/16/21

Activities

updated 3/17/21

Quick-View: Commissioning testplans Rev5.png


Full details: Beam commissioning full details rev5.png


Celebration