Difference between revisions of "Phase 1 - HCO & Commissioning"

From Ciswikidb
Jump to navigation Jump to search
(24 intermediate revisions by 2 users not shown)
Line 95: Line 95:
  
 
== System Readiness / HCO Schedule (April '21) ==  
 
== System Readiness / HCO Schedule (April '21) ==  
<div class="mw-collapsible mw-collapsed">
+
<div class="mw-collapsible">
 
 
 
 
'''3/30:''' Delays in Injector upgrade installation work => delay of HCO / System re-connects, ~week
 
  
 +
'''For detailed plans for a given day, discussed at 830 toolbox meeting every weekday, see [[CIS Phase 1 work plans]]'''
  
 
'''Format:''' time: System (# of people)
 
'''Format:''' time: System (# of people)
Line 107: Line 105:
 
! style="background-color: #eca1a6" | '''April''' !! style="background-color:#eca1a6" | Mon  !! style="background-color:#eca1a6" |  Tue !! style="background-color:#eca1a6" |  Wed !! style="background-color:#eca1a6" |  Thu !! style="background-color:#eca1a6" |  Fri !! style="background-color:#ada397" |  Sa !! style="background-color:#ada397" |  Su
 
! style="background-color: #eca1a6" | '''April''' !! style="background-color:#eca1a6" | Mon  !! style="background-color:#eca1a6" |  Tue !! style="background-color:#eca1a6" |  Wed !! style="background-color:#eca1a6" |  Thu !! style="background-color:#eca1a6" |  Fri !! style="background-color:#ada397" |  Sa !! style="background-color:#ada397" |  Su
 
|- style="background-color:#d6cbd3"  
 
|- style="background-color:#d6cbd3"  
| ! style="background-color:#eca1a6" | ''12th - 16th'' || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Afternoon: Magnet Hook-Ups (2x) || !! style="background-color:#ada397" | Magnet Hook-Ups (2x) || !! style="background-color:#ada397" | Magnet Hook-Ups (2x)
+
| ! style="background-color:#eca1a6" | '''12th - 16th''' || Morning: Valve Controls (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: Valve Controls (1x) <br> Morning: ItoV, Pico, FSD (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: Valve Controls (1x) <br> Morning: ItoV, Pico, FSD (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: ItoV, Pico, FSD (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: ItoV, Pico, FSD (1x) <br> Afternoon: Magnet Hook-Ups (2x) || !! style="background-color:#ada397" | Magnet Hook-Ups (2x) || !! style="background-color:#ada397" | Magnet Hook-Ups (2x)
 
|- style="background-color:#bdcebe"  
 
|- style="background-color:#bdcebe"  
| ! style="background-color:#eca1a6" | ''19th - 23rd''  || Morning: ItoV/Pico/GunFSD (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: ItoV/Pico/GunFSD (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: ItoV/Pico/GunFSD (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) ||  Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) || 6a-noon: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) || !! style="background-color:#ada397" | Magnet Hook-Ups/HCO (2x) <br> || !! style="background-color:#ada397" | Magnet Hook-Ups/HCO (2x)
+
| ! style="background-color:#eca1a6" | '''19th - 23rd'''  || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) ||  Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) || Morning: BPMs (1x) <br> Morning: Viewers (1x) <br> Morning: Harps (1x) <br> Afternoon: Magnet Hook-Ups (2x) || !! style="background-color:#ada397" | Magnet Hook-Ups/HCO (2x) <br> || !! style="background-color:#ada397" | Magnet Hook-Ups/HCO (2x)
 
|- style="background-color:#d6cbd3"
 
|- style="background-color:#d6cbd3"
| ! style="background-color:#eca1a6" | <br> ''26th - 30th'' || Morning: Magnet HCO/Hook-Ups (2x) <br> ''Swings: PSS beamline Certs?'' || 8a-4p: DC Power (2x) <br> ''Swings: PSS beamline Certs?'' || 8a-4p: DC Power (2x) <br> ''Swings: PSS beamline Certs?'' || 8a-4p: DC Power (2x) || 8a-4p: DC Power (2x) || !! style="background-color:#ada397" | Sa || !! style="background-color:#ada397" | Su
+
| ! style="background-color:#eca1a6" | '''26th - 30th''' || Magnet HCO (2x) <br> I&C Float || Magnet HCO (2x) <br> I&C Float || Magnet HCO (2x) <br> 2B Alignment <br> ''Swings: PSS beamline Certs'' || Magnet HCO (2x) <br> 2B Alignment <br> ''Swings: PSS beamline Certs'' || Magnet HCO (2x) || !! style="background-color:#ada397" | Magnet HCO (2x) || !! style="background-color:#ada397" | Magnet HCO (2x)
 
|- style="background-color:#bdcebe"
 
|- style="background-color:#bdcebe"
 
|}
 
|}
  
 
* BPM = Francis
 
* BPM = Francis
 +
* Valve Controls = Ketchum
 
* ItoV, Picoammeters, Gun FSD Interlocks = Francis
 
* ItoV, Picoammeters, Gun FSD Interlocks = Francis
 
* Viewers = Norris
 
* Viewers = Norris
 
* Harps = Dela Cruz
 
* Harps = Dela Cruz
* DC Power = Coleman, others in group; heavily in afternoons
+
* Magnet / DC Power = Coleman
 
+
* 2B Alignment = S&A, Gould
 +
* PSS = Kowal
  
 
</div>
 
</div>
Line 127: Line 127:
 
<div class="mw-collapsible mw-collapsed">
 
<div class="mw-collapsible mw-collapsed">
  
'''[https://jeffersonlab.sharepoint.com/sites/CEBAFInjectorSetupProceduresDevelopment Injector Procedures Workspace]'''
+
=== Documents, Links, Important Dates ===
* [[media:BeamDrivers_Pt2_3.16.21.pdf]]
+
 
 +
Links:
 +
* [https://wiki.jlab.org/ciswiki/index.php/January_25,_2021_-_Weekly_Commissioning_Meetings 1/25/21 Beam Drivers Preliminary Meeting]
 +
* [https://jeffersonlab.sharepoint.com/sites/CEBAFInjectorSetupProceduresDevelopment Injector Procedures Workspace]
 +
 
 +
Documents:
 +
* 3/16/21 Beam Drivers Meeting Slides [[media:BeamDrivers_Pt2_3.16.21.pdf]]
 +
* Injector Group Beam Commissioning Slides [[file:BeamINJphase1v5.pptx]]
  
 +
* Commissioning Checklist (Grames) [[file:210401_Phase1_Commissioning.docx]]
 +
* (incomplete / in-progress) Commissioning Checklist, ATLiss added [[file:210407 Phase1 Commissioning.docx]]
 +
* Preliminary Commissioning Test Plan Layout [[file:3.31.21 BeamCommissioningPlanLayout AIPINJ-1 firstpass.ods]]
  
=== Important Dates ===
+
Dates:
<div class="mw-collapsible mw-collapsed">
+
''updated 4/7/21''
''updated 3/15/21''
 
 
* '''Finalize commissioning plan: April 5th'''
 
* '''Finalize commissioning plan: April 5th'''
 
* Injector HCO/SR Complete: 5/2
 
* Injector HCO/SR Complete: 5/2
Line 142: Line 151:
 
* Resumption of Physics: Mid-August
 
* Resumption of Physics: Mid-August
  
 
</div>
 
  
 
=== ATLis Testplans ===
 
=== ATLis Testplans ===
 
<div class="mw-collapsible mw-collapsed">
 
<div class="mw-collapsible mw-collapsed">
''updated 3/29/21''
+
''updated 4/7/21''
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21911 21911 Gun high voltage conditioning]
+
 
 +
General / Catch-All Test Plans
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22060 22060 Beam Commissioning AIPINJ Phase I (general ATLis)]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21170 Injector Upgrade - Phase 1 Installation (Gun to Chopper)]
 +
 
 +
 
 +
With-Beam Hardware Commissioning Test Plans
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22061 22061 PSS Kicker Tests @ 130keV & 200keV]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22080 22080 AIPINJ: 130/200 keV HVPS vs. PCUP current monitor calibration]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22082 22082 AIPINJ: 130/200 keV lifetime measurements]
 +
* Transmission vs Gun HV
 +
 +
 
 +
Beam Commissioning
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22180 22180 Gun to Chopper Commissioning _130keV / 200keV beam to PCup]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22181 22181 Early Injector Orbit Data Collection Rev. April/May 2021]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22182 22182 Set up beam from PCup to FC1 at 130keV]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22183 22183 Beam steer from FC1 to FC2]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22184 22184 Efficacy of Knobs chosen for spot move correction]
 +
 
 +
 
 +
Optics/RF Test Plans
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21923 21923 Perform 130keV emittance measurements and matching as part of Injector Upgrade commissioning]  
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21923 21923 Perform 130keV emittance measurements and matching as part of Injector Upgrade commissioning]  
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22072 22072 Perform 200keV emittance measurements and matching as part of Injector Upgrade commissioning]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22072 22072 Perform 200keV emittance measurements and matching as part of Injector Upgrade commissioning]
 +
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=19784 19784 Test multiwire emittance measurement with beam]
 +
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/22160 22160 Measure optics at various coil fixture rotation angles for MDR1I02]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22190 22190 RF Elements Setup (Injector Upgrade Phase 1), Lasers phases, Prebuncher, and Choppers]
 +
 +
Spin/Wien Test Plans
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22090 22090 Mott Hot Checkout]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22091 22091 Spin Dance to Calibrate Upgraded CEBAF Injector 3D Spin Rotator]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22092 22092 Set 3D Spin Rotator: Flip-Right, Flip-Left, and Vertical Polarizarion]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22083 22083 AIPINJ: Test new hysteresis function for spin solenoids (MFG1I04A/B)]
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22084 22084 AIPINJ: 130/200 keV E/B calibrations for V-Wien and H-Wien]
 +
* Beam ToF vs Wien Setting, 130keV and 200keV
 +
 +
 +
Parity Quality Beam Test Plans
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22040 22040 cathode 45deg rotation and spot moves]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22040 22040 cathode 45deg rotation and spot moves]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22050 22050 130keV sensitivity test]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22050 22050 130keV sensitivity test]
Line 156: Line 198:
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22052 22052 Transmission test gun 200keV]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22052 22052 Transmission test gun 200keV]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22053 22053 RTP pos diff feedback convergence FC2 test]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22053 22053 RTP pos diff feedback convergence FC2 test]
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22061 22061 PSS Kicker Tests @ 130keV & 200keV]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22060 22060 Beam Commissioning AIPINJ Phase I (general ATLis)]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22090 22090 Mott Hot Checkout]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22091 22091 Spin Dance to Calibrate Upgraded CEBAF Injector 3D Spin Rotator]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22092 22092 Set 3D Spin Rotator: Flip-Right, Flip-Left, and Vertical Polarizarion]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22080 22080 AIPINJ: 130/200 keV HVPS vs. PCUP current monitor calibration]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22082 22082 AIPINJ: 130/200 keV lifetime measurements]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22083 22083 AIPINJ: Test new hysteresis function for spin solenoids (MFG1I04A/B)]
 
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22084 22084 AIPINJ: 130/200 keV E/B calibrations for V-Wien and H-Wien]
 
 
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22120 22120 Chopper scan 130keV]
 
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22120 22120 Chopper scan 130keV]
 
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22121 22121 Chopper scan 200keV]
 
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22121 22121 Chopper scan 200keV]
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=19784 19784 Test multiwire emittance measurement with beam]
+
 
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/22160 22160 Measure optics at various coil fixture rotation angles for MDR1I02]
+
 
  
 
</div>
 
</div>
Line 174: Line 207:
 
=== Activities ===
 
=== Activities ===
 
<div class="mw-collapsible">
 
<div class="mw-collapsible">
''updated 3/29/21''
+
''updated 4/7/21''
  
Quick-View:
+
Test Plans Grouped by Type:
  
[[File:Commissioning testplans Rev8.png | 600px]]
+
[[file:Beam commissioning by type.png | 1000px]]
  
  
Full details:
 
 
[[File:Beam commissioning full details rev8.png | 800px]]
 
 
 
</div>
 
 
</div>
 
</div>
  

Revision as of 14:38, 9 April 2021

CIS Jobs Leading to HCO & Commissioning (Jan 1 - Apr 30)

I&C/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30)

I&C Jobs
  • What to expect in tunnel?
    • Similar mechanical layout => Gun + 3 girders (Y + Wien + A1/A2)
    • There is now a 3D CAD model from gun to chopper, I can share pics or see Gary Hays or Shaun Gregory
    • Similar utilities => LCW (A1/A2) + Air (Bubba/Phil) + Cable tray (above/below) + 3 cable drops (Y, Laser, Chopper)

* BPMs = Pete estimates 1 person x 5 days for all of the BPM hook-up and pre-beam checkout jobs

    • 10 total - all unrotated
    • 3 new style => NEG coated large bore (2.5" ID); mapped by Musson (Kx/Ky values available)
    • 7 old style => 5.5" long end tapped
  • Viewers
    • 8 total - all chromox except ITV0I02 (YAG)
    • Crash inhibit #1 : ITV0I01 and Polarized Cup IFY0I01
    • Crash inhibit #2 : ITV0I02 and Harp IHA0I02
  • Harps
    • 1 total - IHA0I02 (YAG), on same cross as viewer ITV0I02 (requires crash inhibit)
  • Wien HV
    • Tony status update

* Current Monitoring - Pete estimates 1 person x 3 days for ItoV, Picoammeters, Gun FSD LCW waterflow interlocks)

    • 3 total - same as before (PCUP, A1, A2)
    • PCUP identical as before, just a new location
    • A1 current monitoring as before, linear bellow motion now has STAC5 motor (so remote or manual; has 3 stop positions
    • A2 current monitoring as before, linear bellows manual as before; has 3 stop positions. Used by PSS group for kicker
  • Valves
    • 3 total - all have in-line EPICS shut over ride capability (CIS installs this box)
    • Gun valve - VBV2I01A (new name), otherwise same all metal gate valve
    • Beam line valve - VBV1I07 (same name), same all metal gate valve
    • Beam line valve - VBV0I02 (same name), but now all metal gate valve, requires cable terminations like VBV1I07
    • All 3 valves tied to UHV vacuum fault (100 uA limit)
Software Jobs
  • CED
    • Michele or Gary can gives us an update
  • Apps
    • Injector steering script getting upgrades for Wien/Solenoid controls, also needs update of correctors/bpms
    • Any script that refers to CED elements from Gun to Chopper will need name review, sounds like a big job
  • Screens
    • I guess many screens auto-updated from CED, that's great
    • Like with apps, will need name review; I guess system owners look at their own screens for oddities?
  • What else for software?

Magnet/DC-Power/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30)

DC/Magnet Jobs
Updated MHD field map due from JM/LL to GC
Updated MFX (SW/CW) field map due from RS to GC
Software Jobs
  • CED
  • Apps
  • Screens
  • What else for software?
Other magnet jobs
  • (JM) Complete magnet table I circulated
  • Done(JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
  • (RS/GC) FG solenoid special hysteresis for Gary
  • (RS/MJ) Magnet info for Inj Steer spin calculations
  • (JM/JG) Decision on spare DR fabrication and alignment
  • Done (LL/JK/JM) PSS kicker - does MMF have any responsibility here, maybe just PSS?
  • Done (LL/JM) Second QW measurement, what's the scope here?
  • Done (JM) When is the rotating coil stand ready?
  • (JM/LL) Reconciling MHD discrepancy
  • (LL) Report on QW
  • (LL) Report on HD
  • (LL) Report on PSS kicker


System Readiness / HCO Schedule (April '21)

For detailed plans for a given day, discussed at 830 toolbox meeting every weekday, see CIS Phase 1 work plans

Format: time: System (# of people)

April Mon Tue Wed Thu Fri Sa Su
12th - 16th Morning: Valve Controls (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: Valve Controls (1x)
Morning: ItoV, Pico, FSD (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: Valve Controls (1x)
Morning: ItoV, Pico, FSD (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: ItoV, Pico, FSD (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: ItoV, Pico, FSD (1x)
Afternoon: Magnet Hook-Ups (2x)
Magnet Hook-Ups (2x) Magnet Hook-Ups (2x)
19th - 23rd Morning: BPMs (1x)
Morning: Viewers (1x)
Morning: Harps (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: BPMs (1x)
Morning: Viewers (1x)
Morning: Harps (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: BPMs (1x)
Morning: Viewers (1x)
Morning: Harps (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: BPMs (1x)
Morning: Viewers (1x)
Morning: Harps (1x)
Afternoon: Magnet Hook-Ups (2x)
Morning: BPMs (1x)
Morning: Viewers (1x)
Morning: Harps (1x)
Afternoon: Magnet Hook-Ups (2x)
Magnet Hook-Ups/HCO (2x)
Magnet Hook-Ups/HCO (2x)
26th - 30th Magnet HCO (2x)
I&C Float
Magnet HCO (2x)
I&C Float
Magnet HCO (2x)
2B Alignment
Swings: PSS beamline Certs
Magnet HCO (2x)
2B Alignment
Swings: PSS beamline Certs
Magnet HCO (2x) Magnet HCO (2x) Magnet HCO (2x)
  • BPM = Francis
  • Valve Controls = Ketchum
  • ItoV, Picoammeters, Gun FSD Interlocks = Francis
  • Viewers = Norris
  • Harps = Dela Cruz
  • Magnet / DC Power = Coleman
  • 2B Alignment = S&A, Gould
  • PSS = Kowal

Beam Commissioning (May 3 - Jul 2)

Documents, Links, Important Dates

Links:

Documents:

Dates: updated 4/7/21

  • Finalize commissioning plan: April 5th
  • Injector HCO/SR Complete: 5/2
  • Injector Beam Commissioning Begins: 5/3
  • NL/Inj -> Stable 2K: 5/21
  • Full CEBAF PSS Certification: 5/24 - 6/11
  • End of SAD: 7/2
  • Resumption of Physics: Mid-August


ATLis Testplans

updated 4/7/21

General / Catch-All Test Plans


With-Beam Hardware Commissioning Test Plans


Beam Commissioning


Optics/RF Test Plans

Spin/Wien Test Plans


Parity Quality Beam Test Plans


Activities

updated 4/7/21

Test Plans Grouped by Type:

Beam commissioning by type.png


Celebration