Difference between revisions of "Phase 1 - HCO & Commissioning"

From Ciswikidb
Jump to navigation Jump to search
 
(216 intermediate revisions by 4 users not shown)
Line 1: Line 1:
==Jobs Leading to HCO & Commissioning ==
+
5/6/21 This page no longer in use.
  
; 15 deg dipole (Scott)
+
For Phase 1 HCO/SR: [[Phase 1 System Readiness]]
* Install on beam line after bake out, then align, do we use shims?
 
* Current sensor for HV interlock installed and tested, ready for DC power, to set limits, fault test
 
* Current sensor for FSD installed and tested, calibrated for FSD card, ready for DC power, to set limits, fault test
 
* Update drawings, document
 
  
; Laser jobs (Shukui/Scott)
+
For Phase 1 Beam Commissioning: [[Phase 1]]
* Complete outrigger box, install, test with laser room shutter, update LSOP
 
* Flush chiller, decide on PM schedule, fill
 
* Re-install Hall B amp in permanent location
 
* Complete macropulse chassis upgrade (replace 18 VDC + booster with 24 VDC, add protection diode to shutters), test all beam modes
 
* Update drawings, document
 
  
; Gun HVPS jobs (Carlos/Bubba/Scott)
 
  
 
+
[[File:404 dog.png|1000px]]
; Wien HVPS (Carlos)
 
* (done) Add placards to ISB racks
 
* Install HV Switcher chassis at ISB, complete cabling between rack components
 
* Drop/pull HV cables from HV switcher outputs to Wiens
 
* Update drawings, document
 
 
 
; Ion Pump Power Supplies (Scott, Marcy)
 
* (done) Finalize IP names for songsheet
 
* Complete mapping between all IP and power supplies (gun to choppers)
 
* Complete UHV power supply upgrade, remove temp PS, spare PS on shelf (identify cabinet area for spares)
 
* Work with software to reprogram UHV PS EPICS names, can we have unique identifier from old names?
 
* Re-install (2) HV patch boxes, update box labels, pull HV drop cables to patch boxes, updated labels
 
* Update drawings, document
 
 
 
; Vacuum (Marcy, Phil)
 
* Bake gun and beam line
 
* Activate NEG's
 
* Hi-pot any FE-er pumps
 
* Set voltage for all pumps
 
 
 
; Valves (Scott)
 
* Work with I&C and software, controls for (3) valves (note - confirm valve type different)
 
* Build, install, test (3) shut-override boxes for valves
 
* UHV vacuum fault (series, yes?) shuts all three gate valves, test
 
* Gun2 valve open required for HV enable; method to jumper/bypass for HV conditioning (i.e. valve closed, but HV enable OK)
 
* Update drawings, document
 
 
 
; Air, GN2, LCW (Phil, Bubba)
 
* Move GN2 near gun lower, hook for air lines, caps for poly hose
 
* Add 2nd GN2 near girder, hook for air lines, caps for poly hose
 
* Fabricate, install air manifold w/ cutoff for (8) viewers, (2) valves, (2) spares
 
* (done) Re-install LCW manifold
 
 
 
; Crash inhibit (Scott)
 
* Install, test crash inhibit for pcup and viewer (note - fail safe test, i.e. do NOT hook up air to BOTH devices)
 
* Install, test crash inhibit for harp and viewer (note - does this exist, would speak to I&C early on)
 
 
 
; Apertures & PCup (Phil, Scott)
 
* Scribe new aperture stops, bag, store in tunnel, throw away ALL old stops
 
* Install shoulder bolt on A1, test
 
* Attach current monitoring w/ inline I&C protection boxes
 
* Reconnect LCW, I&C check flow meters clear interlock
 
 
 
; Electrician jobs (Scott)
 
* Relocate floor outlets
 
* Bond girders (Shaun has holes drilled on girders already for this)
 
* Install cable tray
 
 
 
; Decarad (Carlos, Scott)
 
* Tally # of heads for gun (Carlos) and beam line (Alicia)
 
* Mount decarad chassis, dress signal/HV cables
 

Latest revision as of 21:06, 6 May 2021

5/6/21 This page no longer in use.

For Phase 1 HCO/SR: Phase 1 System Readiness

For Phase 1 Beam Commissioning: Phase 1


404 dog.png