==CIS Jobs Leading to HCO & Commissioning (Jan 1 - Apr 30) ==
+
5/6/21 This page no longer in use.
<div class="mw-collapsible mw-collapsed">
 
  
; 15 deg dipole (Scott)
+
For Phase 1 HCO/SR: [[Phase 1 System Readiness]]
* '''(Done/SW/JG - magnet is ready for install & yes, we will use shims)''' Install on beam line after bake out, then align, do we use shims?
 
* Current sensor for HV interlock installed and tested, ready for DC power, to set limits, fault test
 
* Current sensor for FSD installed and tested, calibrated for FSD card, ready for DC power, to set limits, fault test
 
* Update drawings, screens, document
 
  
; Laser jobs (Shukui/Scott)
+
For Phase 1 Beam Commissioning: [[Phase 1]]
* Complete outrigger box, install, test with laser room shutter, update LSOP
 
* Flush chiller, decide on PM schedule, fill
 
* Re-install/align Pockels cell
 
* Re-install Hall B amp in permanent location
 
* Complete macropulse chassis upgrade (replace 18 VDC + booster with 24 VDC, add protection diode to shutters), test all beam modes
 
* Update drawings, document
 
  
; Gun HVPS jobs (Carlos/Bubba/Scott)
 
* Prep for HV & conditioning (SF6, tank, DILO, cables), check HV interlock made up, HVPS setpoints/controls ready
 
* Regrease ceramic after bake
 
* Make sure back-up electrode is available
 
* Remove old HV parts (150kV glassman, old HV interlock chassis, VME interface card), once we can make HV again ... temp replace with Ortec bias PS (if needed)
 
* Pull additional Anode bias HV cable near Glassman rack, I think that's where we ultimately want to bias PS star ground to HVPS, also to patch to QE scan ammeter
 
* Develop HV commissioning plan/staffing
 
**[[Media:Gun2 Tee electrode 200kV HV codnitoning plan 2021 draft01.pptx]]
 
  
; Wien HVPS (Carlos, Scott, Riad)
+
[[File:404 dog.png|1000px]]
* '''(Done)''' Add placards to ISB racks
 
* Install HV Switcher chassis at ISB, complete cabling between rack components
 
* Drop/pull HV cables from HV switcher outputs to Wiens
 
* Wien EDM and InjSteer screens updates with HVPS and new PS epics values, tested, ready
 
* Update screens, drawings, document
 
 
 
; Ion Pump Power Supplies (<strike>Scott</strike>, Marcy, EES)
 
* '''(Done)''' Finalize IP names for songsheet [[media:210209_ion pump names.xlsx]]
 
* Complete mapping between all IP and power supplies (gun to choppers)
 
* Complete UHV power supply upgrade, remove temp PS, spare PS on shelf (identify cabinet area for spares): This is Jim Kortze & co., not planned for this down?
 
* Work with software to reprogram UHV PS EPICS names, can we have unique identifier from old names?
 
* Re-install (2) HV patch boxes, update box labels, pull HV drop cables to patch boxes, updated labels
 
* Update screens, drawings, document
 
 
 
; Vacuum (Marcy, Phil)
 
* '''(Done)'''Bake gun, fix scheme for Kr processing beforehand
 
* Bake aperture girder beam line, activate NEGs
 
* Bake wien and y chamber girders, activate NEGs
 
** Make cables to activate Y chamber NEG pumps during bakeout (draw up and send to Fab)
 
* Activate beam line NEGs for DP stations downstream of chopper
 
* Hi-pot any FE-er pumps
 
* Set voltage for all pumps
 
* Activate Prep NEG to overboard (done), bake if needed (Joe: see if cathode activates in prep chamber? No water in RGA scan)
 
 
 
; Valves (Scott, Phil)
 
* '''(Done)'''Work with I&C and software, controls for (3) valves (note - confirm valve type different)
 
* Build, install, test (3) shut-override boxes for valves
 
* UHV vacuum fault (series, yes?) shuts all three gate valves, test
 
* Gun2 valve open required for HV enable; method to jumper/bypass for HV conditioning (i.e. valve closed, but HV enable OK)
 
* Update drawings, document
 
 
 
; Air, GN2, LCW (Phil, Bubba)
 
* '''(Done)'''Move GN2 near gun lower, hook for air lines, caps for poly hose
 
* '''(Done)'''Add 2nd GN2 near girder, hook for air lines, caps for poly hose
 
* Fabricate, install air manifold w/ cutoff for (8) viewers, (2) valves, (2) spares
 
* (done) Re-install LCW manifold
 
 
 
; Crash inhibit (Scott, Phil)
 
* Install, test crash inhibit for pcup and viewer (note - fail safe test, i.e. do NOT hook up air to BOTH devices)
 
* Install, test crash inhibit for harp and viewer (note - does this exist, would speak to I&C early on)
 
 
 
; Apertures & PCup (Phil, Scott)
 
* Scribe new aperture stops, bag, store in tunnel, throw away ALL old stops
 
* Install shoulder bolt on A1, test
 
* Attach current monitoring w/ inline I&C protection boxes
 
* Reconnect LCW, I&C check flow meters clear interlock
 
 
 
; Electrician jobs (Scott)
 
* Relocate floor outlets (done)
 
* Bond girders (Shaun has holes drilled on girders already for this)
 
* Install cable tray
 
 
 
; Decarad (Carlos, Scott)
 
* Tally # of heads for gun (Carlos) and beam line (Alicia)
 
* Mount decarad chassis, dress signal/HV cables
 
 
 
</div>
 
 
 
==I&C/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30) ==
 
<div class="mw-collapsible mw-collapsed">
 
 
 
; I&C Jobs
 
* What to expect in tunnel?
 
** Similar mechanical layout => Gun + 3 girders (Y + Wien + A1/A2)
 
** There is now a 3D CAD model from gun to chopper, I can share pics or see Gary Hays or Shaun Gregory
 
** Similar utilities => LCW (A1/A2) + Air (Bubba/Phil) + Cable tray (above/below) + 3 cable drops (Y, Laser, Chopper)
 
 
 
'''* BPMs = Pete estimates 1 person x 5  days for all of the BPM hook-up and pre-beam checkout jobs'''
 
** 10 total - all unrotated
 
** 3 new style => NEG coated large bore (2.5" ID); mapped by Musson (Kx/Ky values available)
 
** 7 old style => 5.5" long end tapped
 
 
 
* Viewers
 
** 8 total  - all chromox except ITV0I02 (YAG)
 
** Crash inhibit #1 : ITV0I01 and Polarized Cup IFY0I01
 
** Crash inhibit #2 : ITV0I02 and Harp IHA0I02
 
 
 
* Harps
 
** 1 total - IHA0I02 (YAG), on same cross as viewer ITV0I02 (requires crash inhibit)
 
 
 
* Wien HV
 
** Tony status update
 
 
 
'''* Current Monitoring - Pete estimates 1 person x 3 days for ItoV, Picoammeters, Gun FSD LCW waterflow interlocks)'''
 
** 3 total - same as before (PCUP, A1, A2)
 
** PCUP identical as before, just a new location
 
** A1 current monitoring as before, linear bellow motion now has STAC5 motor (so remote or manual; has 3 stop positions
 
** A2 current monitoring as before, linear bellows manual as before; has 3 stop positions.  Used by PSS group for kicker
 
 
 
* Valves
 
** 3 total - all have in-line EPICS shut over ride capability (CIS installs this box)
 
** Gun valve - VBV2I01A (new name), otherwise same all metal gate valve
 
** Beam line valve - VBV1I07 (same name), same all metal gate valve
 
** Beam line valve - VBV0I02 (same name), but now all metal gate valve, requires cable terminations like VBV1I07
 
** All 3 valves tied to UHV vacuum fault (100 uA limit)
 
 
 
* Ion pumps
 
** Marcy's final list [[media:210209_ion pump names.xlsx]]
 
 
 
; Software Jobs
 
* CED
 
** Michele or Gary can gives us an update
 
 
 
* Apps
 
** Injector steering script getting upgrades for Wien/Solenoid controls, also needs update of correctors/bpms
 
** Any script that refers to CED elements from Gun to Chopper will need name review, sounds like a big job
 
 
 
* Screens
 
** I guess many screens auto-updated from CED, that's great
 
** Like with apps, will need name review; I guess system owners look at their own screens for oddities?
 
 
 
* What else for software?
 
 
 
</div>
 
 
 
==Magnet/DC-Power/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30) ==
 
<div class="mw-collapsible mw-collapsed">
 
 
 
; DC/Magnet Jobs
 
* Spreadsheet updated after further feedback [[media:210301_Phase1_Magnet_Summary_v3.xlsx]]
 
* Spreadsheet updated at 3/1 SAD planning meeting [[media:210301_Phase1_Magnet_Summary_v2.xlsx]]
 
* Spreadsheet initially [[media:210301_Phase1_Magnet_Summary.xlsx]]
 
 
 
; Software Jobs
 
* CED
 
* Apps
 
* Screens
 
* What else for software?
 
 
 
; Other magnet jobs
 
*(JM) Complete magnet table I circulated
 
*(JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
 
*(RS/GC) FG solenoid special hysteresis for Gary
 
*(RS/MJ) Magnet info for Inj Steer spin calculations
 
*(JM/JG) Decision on spare DR fabrication and alignment
 
*(LL/JK/JM) PSS kicker -  does MMF have any responsibility here, maybe just PSS?
 
*(LL/JM) Second QW measurement, what's the scope here?
 
*(JM) When is the rotating coil stand ready?
 
*(JM/LL) Reconciling MHD discrepancy
 
*(LL) Report on QW
 
*(LL) Report on HD
 
*(LL) Report on PSS kicker
 
 
 
 
 
 
 
</div>
 
 
 
== Beam Commissioning (May 3 - Jul 2) ==
 
<div class="mw-collapsible mw-collapsed">
 
 
 
=== Important Dates ===
 
''updated 3/1/21''
 
* NL -> Stable 2K:
 
* Full CEBAF PSS Certification: 5/24 - 6/11
 
*
 
 
 
 
 
=== Activities ===
 
''updated 3/1/21''
 
 
 
[[File:Commissioning_Activities_Rev.png | 999px]]
 
 
 
=== ATLis Testplans ===
 
 
 
</div>
 
 
 
== Celebration ==
 
<div class="mw-collapsible mw-collapsed">
 
* [https://www.youtube.com/watch?v=3GwjfUFyY6M Our celebration song]
 