==Jobs Leading to HCO & Commissioning ==
 
==Jobs Leading to HCO & Commissioning ==
  
 
+
; 15 deg dipole (Scott)
; 15 deg dipole (MDR)
 
 
* Install on beam line after bake out, then align, do we use shims?
 
* Install on beam line after bake out, then align, do we use shims?
 
* Current sensor for HV interlock installed and tested, ready for DC power, to set limits, fault test
 
* Current sensor for HV interlock installed and tested, ready for DC power, to set limits, fault test
Line 8: Line 7:
 
* Update drawings, document
 
* Update drawings, document
  
; Laser jobs
+
; Laser jobs (Shukui/Scott)
 
* Complete outrigger box, install, test with laser room shutter, update LSOP
 
* Complete outrigger box, install, test with laser room shutter, update LSOP
 
* Flush chiller, decide on PM schedule, fill
 
* Flush chiller, decide on PM schedule, fill
Line 15: Line 14:
 
* Update drawings, document
 
* Update drawings, document
  
; Gun HVPS jobs
+
; Gun HVPS jobs (Carlos/Bubba/Scott)
  
  
; Wien HVPS
+
; Wien HVPS (Carlos)
 
* (done) Add placards to ISB racks
 
* (done) Add placards to ISB racks
 
* Install HV Switcher chassis at ISB, complete cabling between rack components
 
* Install HV Switcher chassis at ISB, complete cabling between rack components
Line 24: Line 23:
 
* Update drawings, document
 
* Update drawings, document
  
; Ion Pump Power Supplies
+
; Ion Pump Power Supplies (Scott, Marcy)
 
* (done) Finalize IP names for songsheet
 
* (done) Finalize IP names for songsheet
 
* Complete mapping between all IP and power supplies (gun to choppers)
 
* Complete mapping between all IP and power supplies (gun to choppers)
Line 32: Line 31:
 
* Update drawings, document
 
* Update drawings, document
  
; Valves
+
; Vacuum (Marcy, Phil)
 +
* Bake gun and beam line
 +
* Activate NEG's
 +
* Hi-pot any FE-er pumps
 +
* Set voltage for all pumps
 +
 
 +
; Valves (Scott)
 
* Work with I&C and software, controls for (3) valves (note - confirm valve type different)
 
* Work with I&C and software, controls for (3) valves (note - confirm valve type different)
 
* Build, install, test (3) shut-override boxes for valves
 
* Build, install, test (3) shut-override boxes for valves
Line 39: Line 44:
 
* Update drawings, document
 
* Update drawings, document
  
; Air, GN2, LCW
+
; Air, GN2, LCW (Phil, Bubba)
 
* Move GN2 near gun lower, hook for air lines, caps for poly hose
 
* Move GN2 near gun lower, hook for air lines, caps for poly hose
 
* Add 2nd GN2 near girder, hook for air lines, caps for poly hose
 
* Add 2nd GN2 near girder, hook for air lines, caps for poly hose
Line 45: Line 50:
 
* (done) Re-install LCW manifold
 
* (done) Re-install LCW manifold
  
; Crash inhibit
+
; Crash inhibit (Scott)
 
* Install, test crash inhibit for pcup and viewer (note - fail safe test, i.e. do NOT hook up air to BOTH devices)
 
* Install, test crash inhibit for pcup and viewer (note - fail safe test, i.e. do NOT hook up air to BOTH devices)
 
* Install, test crash inhibit for harp and viewer (note - does this exist, would speak to I&C early on)
 
* Install, test crash inhibit for harp and viewer (note - does this exist, would speak to I&C early on)
  
; Apertures & PCup
+
; Apertures & PCup (Phil, Scott)
 
* Scribe new aperture stops, bag, store in tunnel, throw away ALL old stops
 
* Scribe new aperture stops, bag, store in tunnel, throw away ALL old stops
 
* Install shoulder bolt on A1, test
 
* Install shoulder bolt on A1, test
Line 55: Line 60:
 
* Reconnect LCW, I&C check flow meters clear interlock
 
* Reconnect LCW, I&C check flow meters clear interlock
  
; Electrician jobs
+
; Electrician jobs (Scott)
 
* Relocate floor outlets
 
* Relocate floor outlets
 
* Bond girders (Shaun has holes drilled on girders already for this)
 
* Bond girders (Shaun has holes drilled on girders already for this)
 
* Install cable tray
 
* Install cable tray
  
; Decarad
+
; Decarad (Carlos, Scott)
 +
* Tally # of heads for gun (Carlos) and beam line (Alicia)
 +
*

Revision as of 09:44, 10 February 2021

Jobs Leading to HCO & Commissioning

15 deg dipole (Scott)
  • Install on beam line after bake out, then align, do we use shims?
  • Current sensor for HV interlock installed and tested, ready for DC power, to set limits, fault test
  • Current sensor for FSD installed and tested, calibrated for FSD card, ready for DC power, to set limits, fault test
  • Update drawings, document
Laser jobs (Shukui/Scott)
  • Complete outrigger box, install, test with laser room shutter, update LSOP
  • Flush chiller, decide on PM schedule, fill
  • Re-install Hall B amp in permanent location
  • Complete macropulse chassis upgrade (replace 18 VDC + booster with 24 VDC, add protection diode to shutters), test all beam modes
  • Update drawings, document
Gun HVPS jobs (Carlos/Bubba/Scott)


Wien HVPS (Carlos)
  • (done) Add placards to ISB racks
  • Install HV Switcher chassis at ISB, complete cabling between rack components
  • Drop/pull HV cables from HV switcher outputs to Wiens
  • Update drawings, document
Ion Pump Power Supplies (Scott, Marcy)
  • (done) Finalize IP names for songsheet
  • Complete mapping between all IP and power supplies (gun to choppers)
  • Complete UHV power supply upgrade, remove temp PS, spare PS on shelf (identify cabinet area for spares)
  • Work with software to reprogram UHV PS EPICS names, can we have unique identifier from old names?
  • Re-install (2) HV patch boxes, update box labels, pull HV drop cables to patch boxes, updated labels
  • Update drawings, document
Vacuum (Marcy, Phil)
  • Bake gun and beam line
  • Activate NEG's
  • Hi-pot any FE-er pumps
  • Set voltage for all pumps
Valves (Scott)
  • Work with I&C and software, controls for (3) valves (note - confirm valve type different)
  • Build, install, test (3) shut-override boxes for valves
  • UHV vacuum fault (series, yes?) shuts all three gate valves, test
  • Gun2 valve open required for HV enable; method to jumper/bypass for HV conditioning (i.e. valve closed, but HV enable OK)
  • Update drawings, document
Air, GN2, LCW (Phil, Bubba)
  • Move GN2 near gun lower, hook for air lines, caps for poly hose
  • Add 2nd GN2 near girder, hook for air lines, caps for poly hose
  • Fabricate, install air manifold w/ cutoff for (8) viewers, (2) valves, (2) spares
  • (done) Re-install LCW manifold
Crash inhibit (Scott)
  • Install, test crash inhibit for pcup and viewer (note - fail safe test, i.e. do NOT hook up air to BOTH devices)
  • Install, test crash inhibit for harp and viewer (note - does this exist, would speak to I&C early on)
Apertures & PCup (Phil, Scott)
  • Scribe new aperture stops, bag, store in tunnel, throw away ALL old stops
  • Install shoulder bolt on A1, test
  • Attach current monitoring w/ inline I&C protection boxes
  • Reconnect LCW, I&C check flow meters clear interlock
Electrician jobs (Scott)
  • Relocate floor outlets
  • Bond girders (Shaun has holes drilled on girders already for this)
  • Install cable tray
Decarad (Carlos, Scott)
  • Tally # of heads for gun (Carlos) and beam line (Alicia)