Phase 1 Commissioning Schedule
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Week 0, May 17th-23rd
DAY Shift | Monday 5/17 |
Tuesday 5/18 |
Wednesday 5/19 |
Thursday 5/20 |
Friday 5/21 |
Sat 5/22 |
Sun 5/23 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
Hot Checkout No Beam |
AM: Hot Checkout PM: PSS Certs |
830-9a: Cryo tour (3ppl) 0I02 harp repair PM: PSS Certs |
0I02 harp repair float: PSS certs |
AM: 0I02 reconnects PM: PSS Certs Begin Beam Commissioning! |
Beam Off | Beam Off | First beam of 2021 |
Shift Leader | Hot Checkout No Beam |
Suleiman | Grames | Poelker | Suleiman | Beam Off | Beam Off | |
Scientist #2 | Hot Checkout No Beam |
Bruker | Bruker | Hernandez-Garcia | Mamun | Beam Off | Beam Off | |
Ops Inj Support | Hot Checkout No Beam |
PSS TD: Forman | PSS TD: Moser | PSS TD: Forman Moser |
Beam Off | Beam Off | ||
SSO / AM Sweeper | Hot Checkout No Beam |
SSG / Forman / Moser | Beam Off | Beam Off | ||||
Other MCC Work, Group, +Persons in MCC | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | |||
SWING Shift | 5/17 | 5/18 | 5/19 | 5/20 | 5/21 | 5/22 | 5/23 | |
Beam Commissioning Plan / ATLis | Hot Checkout No Beam |
0I02 harp repair | 0I02 harp repair | 0I02 harp repair | Trickle Beam to first Viewer 60Hz Noise Snooping / Cable Shielding |
Beam Off | Beam Off | |
Shift Leader | Hot Checkout No Beam |
Beam Off | Beam Off | |||||
Scientist #2 | Hot Checkout No Beam |
Beam Off | Beam Off | |||||
Ops Inj Support | Hot Checkout No Beam |
Law | Beam Off | Beam Off | ||||
SSO | Hot Checkout No Beam |
Anthony | Beam Off | Beam Off | ||||
Other MCC Work, Group, +Persons in MCC | NL Lock-Up/Commissioning, SSG, +2 | NL Lock-Up/Commissioning, SSG, +2 | NL Lock-Up/Commissioning, SSG, +2 | NL Lock-Up/Commissioning, SSG, +2 | NL Lock-Up/Commissioning, SSG, +2 | |||
CCOC / PD | Merz / Aiken | Merz / Aiken | Merz / Frierson | Merz / Frierson | Merz / Frierson | Merz / Frierson | Merz / Frierson |
Week 1, May 24th-30th
CEBAF PSS Certifications Week 1/3
italics = less certain
DAY Shift | Monday 5/24 |
Tuesday 5/25 |
Wednesday 5/26 |
Thursday 5/27 |
Friday 5/28 |
Sat 5/29 |
Sun 5/30 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
Initial Beam Threading Gun->PCup, 130keV, TM (22180) PSS Kicker Cert (22061) |
Initial Beam Threading Gun->PCup, 130keV, CW (22180) PSS Kicker Cert (22061) |
Element Centering Gun->PCup, 130keV, CW (22180) Early Injector Orbit Data (22181) PSS Kicker Cert (22061) |
AM: Polarity Checks AM: Solenoid, Quad Centering Gun->PCup, 130keV, CW (22180) Early Injector Orbit Data (22181) PM: Prebuncher RF Elements Setup, 130keV, CW (22190) |
Prebuncher setup -- 22190 RF Elements Setup /or\ 22184 Spot Move Knobs 2p: 22061 PSS Kicker Cert |
22084 AIPINJ: 130/200 keV E/B calibrations for V-Wien and H-Wien 22080 AIPINJ: 130/200 keV HVPS vs. PCUP current monitor calibration 22184 Efficacy of Knobs chosen for spot move correction 22441 Commissioning V-Wien, H-Wien, Spin Flipper Solenoids and Autosteer Knobs |
22084 AIPINJ: 130/200 keV E/B calibrations for V-Wien and H-Wien 22080 AIPINJ: 130/200 keV HVPS vs. PCUP current monitor calibration 22184 Efficacy of Knobs chosen for spot move correction 22441 Commissioning V-Wien, H-Wien, Spin Flipper Solenoids and Autosteer Knobs |
Weekday lock-ups at ~0645. Weekdays PSS Certs @330p, no Inj commissioning |
Shift Leader | <8a: Grames 8a-4p: Kazimi |
<8a: Grames 8a-4p: Wang |
<8a: Grames 8a-4p: Hofler |
<8a: Grames 8a-noon: Wang noon-4p: Kazimi |
<8a: Moser 8a-4p: Kazimi |
8a-4p Suleiman |
8a-4p Suleiman | |
Scientist #2 | 8a-4p: Wang | 8a-4p: Hofler | 8a-4p: Wang | 8a-4p: Hofler | 8a-4p: {Wang, Hofler} | Bruker Mamun |
Bruker Mamun | |
Ops Inj Support | Law | Law | Law | Law | Law | Law | ||
SSO / AM Sweeper | Garcia / Law | Garcia / Law | Garcia / Law | Garcia / Law | Law / Moser | Merz / Carlino | Deir / Carlino | |
Other MCC Work, Group, +Persons in MCC | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | NL PSS Commissioning, SSG, +2 | |||
SWING Shift | 5/24 | 5/25 | 5/26 | 5/27 | 5/28 | 5/29 | 5/30 | |
Beam Commissioning Plan / ATLis | PSS Certification | PSS Certification | PSS Certification | PSS Certification | PSS Certification | No Beam | No Beam | |
Shift Leader | PSS Certification | PSS Certification | PSS Certification | PSS Certification | PSS Certification | |||
Scientist #2 | PSS Certification | PSS Certification | PSS Certification | PSS Certification | PSS Certification | |||
Ops Inj Support | PSS Certification | PSS Certification | PSS Certification | PSS Certification | PSS Certification | |||
SSO | PSS TD | Aiken | Aiken | Aiken | Aiken | Aiken | |||
Other MCC Work, Group, +Persons in MCC | SSG | SSG | SSG | SSG | SSG | |||
CCOC / PD | Merz / Frierson | Merz / Frierson | Carlino / Frierson | Carlino / Frierson | Carlino / Frierson | Carlino / Frierson | Carlino / Frierson |
Week 2, May 31st🇺🇸 - June 6th
CEBAF PSS Certifications Week 2/3
DAY Shift | Monday 5/31 Memorial Day 🇺🇸 |
Tuesday 6/1 |
Wednesday 6/2 |
Thursday 6/3 |
Friday 6/4 |
Sat 6/5 |
Sun 6/6 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
No Beam | AM: 22182 Set up beam from PCup to FC1 at 130keV, TM 22084 130keV Wien E/B cals PM: Prebuncher - 22190 RF Elements Setup 2p: 22061 PSS Kicker @130keV |
7a-9a: 22084 130keV Wien E/B cals 9a-noon: 22441 Wien Autosteer Knobs noon-2p: 22190 Prebuncher Characterization 2p-330p: 22061 PSS Kicker |
AM: 22441 Wien Autosteer Knobs PM: 22181 Early Injector FOPT Data |
0I02 Harp Install No Beam |
No Beam | No Beam | Weekday lock-ups at ~0645. Weekdays PSS Certs @330p, no Inj commissioning |
Shift Leader | No Beam | <8a: CIS 8a-noon: Wang noon-4p: Kazimi |
7a-9a: Suleiman 9a-noon: Law noon-4p: Kazimi |
<8a: Grames 8a-noon: Law noon-4p: Hofler |
No Beam | No Beam | No Beam | |
Scientist #2 | No Beam | 8a-noon: Law noon-4p: Hofler |
7a-9a: Bruker 9a-noon: Wang noon-4p: Hofler |
8a-noon: Wang noon-4p: Kazimi |
No Beam | No Beam | No Beam | |
Ops Inj Support | No Beam | Forman | Forman | Forman | No Beam | No Beam | No Beam | |
SSO / AM Sweeper | No Beam | Gauthier / Forman | Gauthier / Forman | Gauthier / Forman | No Beam | No Beam | No Beam | |
Other MCC Work, Group, +Persons in MCC | 1230-230p: JLab Video Tour Filming w/Satogata (Satogata, Robbins, Camera Guy) |
|||||||
SWING Shift | 5/31 🇺🇸 | 6/1 | 6/2 | 6/3 | 6/4 | 6/5 | 6/6 | |
Beam Commissioning Plan / ATLis | PSS Certification | PSS Certification | PSS Certification | Disconnects for 0I02 Harp PSS Certification |
PSS Certification | No Beam | No Beam | |
Shift Leader | PSS Certification | PSS Certification | PSS Certification | PSS Certification | PSS Certification | No Beam | No Beam | |
Scientist #2 | PSS Certification | PSS Certification | PSS Certification | PSS Certification | PSS Certification | No Beam | No Beam | |
Ops Inj Support | PSS Certification | PSS Certification | PSS Certification | PSS Certification | PSS Certification | No Beam | No Beam | |
SSO | PSS TD | Aiken | Aiken | Aiken | Aiken | Aiken | No Beam | No Beam | |
Other MCC Work, Group, +Persons in MCC | SSG | SSG | SSG | SSG | SSG | |||
CCOC / PD | Carlino / Frierson | Carlino / Frierson | Carlino / Merz | Carlino / Merz | Carlino / Merz | Carlino / Merz | Carlino / Merz |
Week 3, June 7th-13th
- 6/7 - 6/11: CEBAF PSS Certifications Week 3/3
- Days and Swings running 6/11,12,13. No Owls.
DAY Shift | Thursday 6/10 |
Friday 6/11 |
Sat 6/12 |
Sun 6/13 |
Notes/Goals |
---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
10a: PSS Kicker (22061) and Laser Certs 12p: CW to FC1 Setup (22182) |
CW to FC1 Setup (22182) | noon lock-up CW to FC1 Setup (22182) |
High current CW setup to FC1, Choppers Off. | |
Shift Leader | Wang | Wang | Wang | noon: Kazimi | |
Scientist #2 | Bruker | Law | Bruker | noon: Bruker | |
Ops Inj Support | CC: Forman | CC: Forman | CC: Forman | CC: Forman | |
SSO / AM Sweeper | Garcia / SSG | Garcia / Forman | Gauthier / Forman | Gauthier / Forman | |
Other MCC Work, Group, +Persons in MCC | SSG | SSG | |||
SWING Shift | 6/10 | 6/11 | 6/12 | 6/13 | |
Beam Commissioning Plan (ATLis) |
PSS Functional Tests | Prebuncher, Buncher Characterization (22190) |
Prebuncher, Buncher Characterization (22190) | PCup vs HVPS Calibration (22080) High-current CW evaluation | |
Shift Leader | No Beam | Kazimi | Kazimi | Grames | |
Scientist #2 | No Beam | Hofler | Hofler | ||
Ops Inj Support | No Beam | ||||
SSO | PSS TD: Aiken | Anthony | Mock | Mock | |
Other MCC Work, Group, +Persons in MCC | SSG | SSG | |||
CCOC / PD | Moser / Merz | Moser / Merz | Moser / Merz | Moser / Merz |
Week 4, June 14th-20th
- 6/18-20 Weekend -- 500keV limited
- Running without PSS kicker to FC2/ILD (same PSS mode) to be reviewed by SCMB Monday 6/21
- tentative
OWL Shift | Monday 6/14 |
Tuesday 6/15 |
Wednesday 6/16 |
Thursday 6/17 |
Friday 6/18 |
Saturday 6/19 |
Sunday 6/20 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
No Beam | AutoSteer Knobs (22441) | AutoSteer Knobs (22441) | AutoSteer Knobs (22441) | AutoSteer Knobs (22441) | AutoSteer Knobs (22441) | AutoSteer Knobs (22441) | Orbit vs Wien HVPS-Off Config 0I02 YAG Emittance Measurement AutoSteer Knobs - Wien, further? Wien EvB Cal ToF vs Wien θ Early Injector setup training Parity DAQ Checkout |
Shift Leader | No Beam | Law | Law | Law | Law | Law | Law | |
Scientist #2 | No Beam | |||||||
Crew Chief | No Beam | Law | Law | Law | Law | Law | Law | |
SSO | No Beam | Deir | Deir | Deir | Deir | Garcia | Garcia | |
DAY Shift | 6/14 | 6/15 | 6/16 | 6/17 | 6/18 | 6/19 | 6/20 | |
Beam Commissioning Plan (ATLis) |
AM: Inj Open for Repairs -- 2I BPMs, A-slit, Prebuncher, PSS Kicker? PM: Orbit vs Wien HV Config (PS {disabled, off, disconnected}) |
Wien E/B Calibration (22084) | ToF vs Wien Angle (22330) /or\ Further Wien Studies (E/B Cal (22084), orbit deflection, XY-coupling) |
InjSteering Script Testing (22441) | FC1 High Current Setup (22182) | 8A-noon: MWF Noise Measurements vs Wien Angle Setting (22500) noon+: FC1 High Current Setup (22182) |
FC1 High Current Setup (22182) | |
Shift Leader | PM: Suleiman | Suleiman Hofler |
Poelker | Hofler | Wang | 8A-noon: Suleiman noon+: Wang |
Wang | |
Scientist #2 | PM: Hernandez-Garcia, Kazimi | Bruker, Mamun | Bruker | Joyce | noon+ : Bruker | |||
Crew Chief | Carlino | Richardson | Richardson | Richardson | Frierson | Frierson | Frierson | |
SSO | Gauthier | Anthony | Anthony | Gauthier | Gauthier | Gauthier | Gauthier | |
SWING Shift | 6/14 | 6/15 | 6/16 | 6/17 | 6/18 | 6/19 | 6/20 | |
Beam Commissioning Plan (ATLis) |
0I02 Yag Emittance Measurement (22590) | PQB BPM Calibration Run to FC1 | High Current (100uA) CW to FC1 w/Choppers (22182, 22190) | PSS Functional Tests No Beam |
FC1 High Current Setup (22182) AutoSteer Knobs (22441) |
FC1 High Current Setup (22182) AutoSteer Knobs (22441) |
4P-8P: Spot Move Tests (22184) 8P+: AutoSteer Knobs (22441) | |
Shift Leader | Turner | Amali, Caryn (remote) | Wang | Wang Law |
Wang Law |
4P-8P: Grames Law | ||
Scientist #2 | Mamun | Grames | Kazimi | |||||
Crew Chief | McCaughan | McCaughan | McCaughan | Moser | Moser | Moser | Moser | |
SSO | Mock | Mock | Mock | Mock | Mock | Anthony | Anthony |
Week 5, June 21st-27th
- SCMB reviewing proposal to run without PSS Kicker for FC2/ILD running (same PSS mode) Monday 6/21
- 500keV-limited (i.e. 1D/FC1) until SCMB approval
Monday Swing, may be able to run to FC2- ILD running contingent on SCMB approval and HCO completion
- SCMB Update 6/22 -- No FC2 running just yet. Current forecast, Friday Swing
- Update 6/25 -- TOSP signed, BA to FC2 approved. BA to ILD pending (HCO incomplete).
OWL Shift | Monday 6/21 |
Tuesday 6/22 |
Wednesday 6/23 |
Thursday 6/24 |
Friday 6/25 |
Saturday 6/26 |
Sunday 6/27 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
AutoSteer Knobs (22441) | 8P-4A : AutoSteer (22441) 6A-11A: Adviewer 0I02 YAG Emittance Measurement Tool Development (22603) |
midnight - 6A: AutoSteer 6A: Open for HCO |
FC2 Setup (22183) | FC2 Setup (22183) | FC1/1D/500keV limited on weekday Day shifts -- NL Open for Work | ||
Shift Leader | Law | 8P-4A: Law 6A-11A: Freeman |
Law | Law | Law | |||
Scientist #2 | ||||||||
Crew Chief | Forman | Forman | Forman | Forman | Forman | Law | Law | |
SSO | Garcia | Garcia | Garcia | Garcia | Garcia | Garcia | Garcia | |
DAY Shift | 6/21 | 6/22 | 6/23 | 6/24 | 6/25 | 6/26 | 6/27 | |
Beam Commissioning Plan (ATLis) |
Perform 130keV emittance measurements (21923) (using 0I02 YAG) |
ToF vs HWien Angle (22330) | 6A-11A: Adviewer 0I02 YAG Emittance Measurement Tool Development (22603) noon-4P: Wien orbit checks, HV offset measurement |
Open, No Beam, Till ~(10A-noon) noon - 4P: 2I Steering Investigation |
8A-noon: rotatable 1/2 waveplate scans and BPM sensitivity (22120) 30 uA to FC1 noon - 4P: injSteeringScript |
FC2 Setup (22183) | FC2 Setup or continue high-current Wien | |
Shift Leader | Turner | Poelker | 6A-11A: Freeman noon-4P : Suleiman |
Bruker | 8A-noon: Amali noon - 4P: Hofler |
Wang | Wang | |
Scientist #2 | Mamun | Bruker | Bruker | Hofler | 8A-noon: Grames noon-4P: Joyce |
Bruker | ||
Crew Chief | Aiken | Aiken | Aiken | Aiken | Aiken | Freeman | Freeman | |
SSO | Gauthier | Frierson | Frierson | Gauthier | Gauthier | Jones | Jones | |
SWING Shift | 6/21 | 6/22 | 6/23 | 6/24 | 6/25 | 6/26 | 6/27 | |
Beam Commissioning Plan (ATLis) |
H-Wien Orbit Deflection Studies | Continuation of ToF Studies 8P-4A : AutoSteer (22441) |
Physics Run Wien Setup w/ High Current/Transmission (22182) | PSS Functional Tests No Beam After: Physics Run Wien Setup |
FC2 Setup (22183) | FC2 Setup (22183) | FC2 Setup (22183) | |
Shift Leader | Bruker | Grames 8P-4A: Law |
Wang | Wang | Kazimi | Hofler | Kazimi | |
Scientist #2 | Hofler, Bruker | Kazimi | Hofler, Bruker | |||||
Crew Chief | Moser | Moser | Moser | McCaughan | McCaughan | McCaughan | McCaughan | |
SSO | Anthony | Anthony | Anthony | Anthony | Anthony | Mock | Mock |
Week 6, June 28th-July 4th
Yan: tentatively available every day, DAY or SWING as needed.
Joe: available to heat/reactivate the cathode as necessary.
OWL Shift | Monday 6/28 |
Tuesday 6/29 |
Wednesday 6/30 |
Thursday 7/1 |
Friday 7/2 |
Saturday 7/3 |
Sunday 7/4 🇺🇸 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
TBD | TBD | TBD | TBD | TBD | TBD | TBD | ILD running possible once HCO complete and BA granted |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Crew Chief | Law | Law | Law | Law | Forman | Forman | Forman | |
SSO | Deir | Deir | Deir | Deir | Deir | Garcia | Garcia | |
DAY Shift | 6/28 | 6/29 | 6/30 | 7/1 | 7/2 | 7/3 | 7/4 🇺🇸 | |
Beam Commissioning Plan (ATLis) |
TBD | Preparation for polarization study | TBD | TBD | TBD | TBD | TBD | |
Shift Leader | Wang | Suleiman (2 hours) | ||||||
Scientist #2 | ||||||||
Crew Chief | Aiken | Aiken | Freeman | Frierson | Merz | Merz | Merz | |
SSO | Gauthier | Gauthier | Gauthier | Jones | Jones | Aiken | Aiken | |
SWING Shift | 6/28 | 6/29 | 6/30 | 7/1 | 7/2 | 7/3 | 7/4 🇺🇸 | |
Beam Commissioning Plan (ATLis) |
TBD | TBD | TBD | TBD | TBD | TBD | TBD | |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Crew Chief | McCaughan | McCaughan | Moser | Moser | Moser | Carlino | Carlino | |
SSO | Mock | Mock | Mock | Mock | Mock | Anthony | Anthony |
Week 7, July 5th-July 11th
OWL Shift | Monday 7/5 |
Tuesday 7/6 |
Wednesday 7/7 |
Thursday 7/8 |
Friday 7/9 |
Saturday 7/10 |
Sunday 7/11 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
TBD | TBD | TBD | TBD | TBD | TBD | TBD | |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Crew Chief | Forman | Forman | Forman | Forman | Law | Law | Law | |
SSO | Garcia | Garcia | Garcia | Garcia | Garcia | Deir | Deir | |
DAY Shift | 7/5 | 7/6 | 7/7 | 7/8 | 7/9 | 7/10 | 7/11 | |
Beam Commissioning Plan (ATLis) |
TBD | TBD | TBD | TBD | TBD | TBD | TBD | |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Crew Chief | Merz | Merz | Merz | Merz | Frierson | Frierson | Frierson | |
SSO | Aiken | Aiken | Aiken | Aiken | Aiken | Gauthier | Gauthier | |
SWING Shift | 7/5 | 7/6 | 7/7 | 7/8 | 7/9 | 7/10 | 7/11 | |
Beam Commissioning Plan (ATLis) |
TBD | TBD | TBD | TBD | TBD | TBD | TBD | |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Crew Chief | Carlino | McCaughan | McCaughan | McCaughan | McCaughan | McCaughan | McCaughan | |
SSO | Anthony | Anthony | Anthony | Anthony | Anthony | Mock | Mock |
Week 8, July 12th-July 18th
OWL Shift | Monday 7/12 |
Tuesday 7/13 |
Wednesday 7/14 |
Thursday 7/15 |
Friday 7/16 |
Saturday 7/17 |
Sunday 7/18 |
Notes/Goals |
---|---|---|---|---|---|---|---|---|
Beam Commissioning Plan (ATLis) |
TBD | TBD | TBD | TBD | TBD | CEBAF Restoration? | CEBAF Restoration? | |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Crew Chief | Law | Law | Law | Law | Forman | Forman | Forman | |
SSO (+Op) | Deir | Deir | Deir | Deir | Deir | Freeman, Garcia | Freeman, Garcia | |
DAY Shift | 7/12 | 7/13 | 7/14 | 7/15 | 7/16 | 7/17 | 7/18 | |
Beam Commissioning Plan (ATLis) |
TBD | TBD | TBD | TBD | CEBAF Restoration? | CEBAF Restoration? | CEBAF Restoration? | |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Crew Chief | Frierson | Frierson | Frierson | Frierson | Merz | Merz | Merz | |
SSO (+Op) | Gauthier | Gauthier | Gauthier | Gauthier | Gauthier, Humphry | Jones, Humphry | Jones, Humphry | |
SWING Shift | 7/12 | 7/13 | 7/14 | 7/15 | 7/16 | 7/17 | 7/18 | |
Beam Commissioning Plan (ATLis) |
TBD | TBD | TBD | TBD | CEBAF Restoration? | CEBAF Restoration? | CEBAF Restoration? | |
Shift Leader | ||||||||
Scientist #2 | ||||||||
Crew Chief | Carlino | Carlino | Carlino | Carlino | Carlino | Carlino | Carlino | |
SSO (+Op) | Mock | Mock | Mock | Mock | McCaughan, Mock | McCaughan, Anthony | McCaughan, Anthony |