Planning, planning, planning...

Major Phase 2 Beamline Components

SRF Booster
media:parts list old and new phase2 beamline.xls

2022 Winter SAD ATLIS Tasks

Phase 1 Region
  • 200 kV gun => building a second 18" gun appropriate for CEBAF, to condition to 300 kV, and operate at 200 kV
  • (Lakshmi) Replace DR dipole => PO written week of Aug 30 for new DM at CEBAF, UITF and 2 spare coils
  • (Sarin/Riad) Replace noisy Wien 20A SCE =>
  • (Phil) Repair leaky PCUP LCW fitting => labor, no M&S
  • (Marcy) Remake A2 joint => labor, no M&S
  • (Marcy) Replace harp => labor, no M&S
  • (Jerry) Install & test 200 kV kicker => waiting for Jerry's reply
Phase 2 Region
  • (Matt) Possibly install solenoid/valve downstream of chopper => MMF mapping solenoids in Sep. Do we have 2-3/4" pneumatic beam line valve?
  • (FM) Install bright lighting => Walked area with FM. Waiting for follow-up.
Non-AIPINJ Jobs
  • Test mode-locked laser
  • Return gold target ladder, w/ larger nipple, original STAC5
  • Store tunnel HV cables nicely, like we do now at UITF