==ATLIS Tasks==
+
==2022 Winter SAD ATLIS Tasks==
* Install harp, remove top-hat from viewer
+
;Phase 1 Region
* Re-make A2 joint
+
* 200 kV gun => building a second 18" gun appropriate for CEBAF, to condition to 300 kV, and operate at 200 kV
* Take advantage to install new valve downstream chopper?
+
* (Lakshmi) Replace DR dipole =>  PO written week of Aug 30 for new DM at CEBAF, UITF and 2 spare coils
 +
* (Sarin/Riad) Replace noisy Wien 20A SCE =>
 +
* (Phil) Repair leaky PCUP LCW fitting => labor, no M&S
 +
* (Marcy) Remake A2 joint => labor, no M&S
 +
* (Marcy) Replace harp => labor, no M&S
 +
* (Jerry) Install & test 200 kV kicker => waiting for Jerry's reply
 +
 
 +
;Phase 2 Region
 +
* (Matt) Possibly install solenoid/valve downstream of chopper => MMF mapping solenoids in Sep.  Do we have 2-3/4" pneumatic beam line valve?
 +
* (FM) Install bright lighting => Walked area with FM.  Waiting for follow-up.
 +
 
 +
;Non-AIPINJ Jobs
 +
* Test mode-locked laser
 
* Return gold target ladder, w/ larger nipple, original STAC5
 
* Return gold target ladder, w/ larger nipple, original STAC5
* Replace both Wien 20A SCE with lower noise power supplies
+
* Store tunnel HV cables nicely, like we do now at UITF
* Install Lakshmi's DR dipole
 
* Install/test new kicker
 
* Test mode-locked laser
 
* Install gun which reaches 200 kV reliably w/o field emission
 
* Requested to Steve brighter lights from laser room to gate (like we have by gun)
 

Revision as of 13:58, 14 September 2021

Recent Updates

Planning, planning, planning...

Major Phase 2 Beamline Components

SRF Booster
media:parts list old and new phase2 beamline.xls

2022 Winter SAD ATLIS Tasks

Phase 1 Region
  • 200 kV gun => building a second 18" gun appropriate for CEBAF, to condition to 300 kV, and operate at 200 kV
  • (Lakshmi) Replace DR dipole => PO written week of Aug 30 for new DM at CEBAF, UITF and 2 spare coils
  • (Sarin/Riad) Replace noisy Wien 20A SCE =>
  • (Phil) Repair leaky PCUP LCW fitting => labor, no M&S
  • (Marcy) Remake A2 joint => labor, no M&S
  • (Marcy) Replace harp => labor, no M&S
  • (Jerry) Install & test 200 kV kicker => waiting for Jerry's reply
Phase 2 Region
  • (Matt) Possibly install solenoid/valve downstream of chopper => MMF mapping solenoids in Sep. Do we have 2-3/4" pneumatic beam line valve?
  • (FM) Install bright lighting => Walked area with FM. Waiting for follow-up.
Non-AIPINJ Jobs
  • Test mode-locked laser
  • Return gold target ladder, w/ larger nipple, original STAC5
  • Store tunnel HV cables nicely, like we do now at UITF