Difference between revisions of "Phase 2"

From Ciswikidb
Jump to navigation Jump to search
(8 intermediate revisions by the same user not shown)
Line 11: Line 11:
 
:[[media:parts list old and new phase2 beamline.xls]]
 
:[[media:parts list old and new phase2 beamline.xls]]
  
==ATLIS Tasks==
+
==FY22 SAD ATLIS Tasks==
* Install harp
+
=== Vent VBV0I02 - VBV0I07 (Marcy, Phil)===
* Re-make A2 joint
+
* Monitor vacuum through QCM
* Take advantage to install new valve downstream chopper?
+
* Remake leaky A2 gaskets
* Replace both Wien 20A SCE with lower noise power supplies
+
* Remove top-hat from IYG0I02 (make sure YAG is good, spare on-hand?)
* Install Lakshmi's DR dipole
+
* Install IHA0I02, test before pumpdown, before bakeout
* Return gold target ladder, w/ larger nipple, original STAC5
+
 
* Install gun which reaches 200 kV reliably w/o field emission
+
=== Vent Mott chamber (Marcy, Phil, Scott) ===
* Requested to Steve brighter lights from laser room to gate (like we have by gun)
+
* Remove diamond ladder
 +
* Install/align gold ladder
 +
* Restore old controls
 +
* Long pump down
 +
 
 +
=== Beam Tests ===
 +
* (Shukui, Joe, Tomasz, Reza) Install, test and compare mode-locked vs. gain-switched fiber lasers  (bleedthrough, injector setup, operation)
 +
* (Dennis, Ken?, Alicia?) Use harp to study Wien optics and test match
 +
* (Dennis) Evaluate optics of new 15 deg DM dipole vs. existing DS dipole
 +
* (Max) Use BPM, Harp/lens to quantify beam deflection & Twiss vs. laser spot location
 +
* (Riad, Sarin) Use BPM's and Wiens to test different/new PS to suppress line noise
 +
* (Gabriel, Carlos) Do you need data for Wien paper?
 +
* (Jerry, Joe) Test 200 keV PSS kicker magnet
 +
* (Yan) Evaluate QCM

Revision as of 09:37, 3 November 2021

Recent Updates

Planning, planning, planning...

Major Phase 2 Beamline Components

SRF Booster
media:parts list old and new phase2 beamline.xls

FY22 SAD ATLIS Tasks

Vent VBV0I02 - VBV0I07 (Marcy, Phil)

  • Monitor vacuum through QCM
  • Remake leaky A2 gaskets
  • Remove top-hat from IYG0I02 (make sure YAG is good, spare on-hand?)
  • Install IHA0I02, test before pumpdown, before bakeout

Vent Mott chamber (Marcy, Phil, Scott)

  • Remove diamond ladder
  • Install/align gold ladder
  • Restore old controls
  • Long pump down

Beam Tests

  • (Shukui, Joe, Tomasz, Reza) Install, test and compare mode-locked vs. gain-switched fiber lasers (bleedthrough, injector setup, operation)
  • (Dennis, Ken?, Alicia?) Use harp to study Wien optics and test match
  • (Dennis) Evaluate optics of new 15 deg DM dipole vs. existing DS dipole
  • (Max) Use BPM, Harp/lens to quantify beam deflection & Twiss vs. laser spot location
  • (Riad, Sarin) Use BPM's and Wiens to test different/new PS to suppress line noise
  • (Gabriel, Carlos) Do you need data for Wien paper?
  • (Jerry, Joe) Test 200 keV PSS kicker magnet
  • (Yan) Evaluate QCM