== Recent Updates ==
 
 
*
 
 
 
==Planning, planning, planning...==
 
==Planning, planning, planning...==
 
* [[AIPINJ - Phase 2 Upgrade Meetings]]
 
* [[AIPINJ - Phase 2 Upgrade Meetings]]
Line 10: Line 6:
 
:[[SRF Booster]]
 
:[[SRF Booster]]
 
:[[media:parts list old and new phase2 beamline.xls]]
 
:[[media:parts list old and new phase2 beamline.xls]]
 
==FY22 SAD ATLIS Tasks==
 
 
===Schedule===
 
* CEBAF SAD runs from Feb 8 - Jun 8 (about 4 months)  [[media:210112_SAD_timeline.pdf]]
 
* Jason Willoughby is installing bright white task lighting w/ wall dimmer from laser hut to fc#2
 
* Install group may remove 5D line in prep for Phase 2 https://opsweb.acc.jlab.org/CSUEApps/atlis/task/22161
 
* Tunnel jobs during first ~month of SAD
 
:: Tomasz is upgrading RF https://opsweb.acc.jlab.org/CSUEApps/atlis/task/21376
 
:: CIS has two major vacuum jobs
 
* Beam base jobs follow, accomodating PSS
 
 
=== Vent VBV0I02 - VBV0I07 ===
 
* Marcy write ATLIS
 
* Coordinate groups to remove/stow items
 
* Coordinate with SRF before venting
 
* Dry run the entire sequence of jobs
 
* Prep all the parts for vacuum job in tunnel
 
* Vent through QCM
 
* Work w/ S&A to remake A2 gasket
 
* Rework IYG0I02, remove top-hat, align YAG screen per Dennis
 
* Work with S&A to align YAG screen
 
* Work with S&A to install, align IHA0I02
 
* Check viewer and harp before and after pump down, repeatedly, carefully
 
* Pump down and leak check
 
 
=== Vent Mott chamber  ===
 
* Joe write ATLIS
 
* Coordinate with S&A to check gold ladder fiducials
 
* Coordinate with Scott to disconnect diamond ladder controls
 
* Dry run the entire sequence in tunnel
 
* Prep all the parts before venting
 
* Vent chamber slowly for existing gold target
 
* Remove diamond ladder
 
* Rebuild lower section of Mott (tube + window)
 
* Last step install and align gold ladder
 
* Slow pump down, check motion controls of ladder, leak check
 
* Long pump down
 
 
=== Upgrade Gun2 loading chamber ===
 
* https://opsweb.acc.jlab.org/CSUEApps/atlis/task/19463
 
 
=== Beam Based Tests ===
 
* (Shukui, Joe, Tomasz, Reza) Install and test mode locked fiber laser https://opsweb.acc.jlab.org/CSUEApps/atlis/task/22830
 
* (Dennis, Ken, Alicia) Use harp to study Wien optics and test match
 
* (Dennis) Evaluate optics of Lakshmi's new 15 deg DM dipole vs. existing DS dipole
 
* (Max) Use BPM, Harp/lens to quantify beam deflection & Twiss vs. laser spot location
 
* (Riad, Sarin) Use BPM's and Wiens to test different/new PS to suppress line noise
 
* (Gabriel, Carlos) Do you need data for Wien paper?
 
* (Jerry, Joe) Test 200 keV PSS kicker magnet https://opsweb.acc.jlab.org/CSUEApps/atlis/task/22061
 
* (Yan) Evaluate QCM
 