Recent Updates

Planning, planning, planning...

Major Phase 2 Beamline Components

SRF Booster
media:parts list old and new phase2 beamline.xls

ATLIS Tasks

  • Install gun which reaches 200 kV reliably w/o field emission
  • Replace both Wien 20A SCE with lower noise power supplies
  • Install and test Lakshmi's DR dipole
  • Install 12 GeV harp
  • (done) Requested to Anthony 2nd roll-around cart
  • Requested to Steve brighter lights from laser room to gate (like we have by gun)