Recent Updates
Planning, planning, planning...
Major Phase 2 Beamline Components
FY22 SAD ATLIS Tasks
Schedule
- CEBAF SAD runs from Feb 8 - Jun 8 (about 4 months) media:210112_SAD_timeline.pdf
- Tunnel jobs during first ~month of SAD
- Jason Willoughby is installing bright white task lighting w/ wall dimmer from laser hut to fc#2
- Tomasz is upgrading RF
- CIS has two major vacuum jobs
Vent VBV0I02 - VBV0I07 (Marcy, Phil)
- Monitor vacuum through QCM
- Remake leaky A2 gaskets
- Remove top-hat from IYG0I02 (make sure YAG is good, spare on-hand?)
- Install IHA0I02, test before pumpdown, before bakeout
Vent Mott chamber (Marcy, Phil, Scott)
- Remove diamond ladder
- Install/align gold ladder
- Restore old controls
- Long pump down
Beam Tests
- (Shukui, Joe, Tomasz, Reza) Install, test and compare mode-locked vs. gain-switched fiber lasers (bleedthrough, injector setup, operation)
- (Dennis, Ken, Alicia) Use harp to study Wien optics and test match
- (Dennis) Evaluate optics of Lakshmi's new 15 deg DM dipole vs. existing DS dipole
- (Max) Use BPM, Harp/lens to quantify beam deflection & Twiss vs. laser spot location
- (Riad, Sarin) Use BPM's and Wiens to test different/new PS to suppress line noise
- (Gabriel, Carlos) Do you need data for Wien paper?
- (Jerry, Joe) Test 200 keV PSS kicker magnet
- (Yan) Evaluate QCM