Difference between revisions of "Reza's thoughts on bunchlength measurement at UITF"

From Ciswikidb
Jump to navigation Jump to search
(Created page with "Checking the bunch length system with 200keV beam and No choppers Requirements: At minimum we need the following #- Beam through bunch length cavity #- More than 5uA tune bea...")
 
(No difference)

Latest revision as of 10:38, 22 February 2021

Checking the bunch length system with 200keV beam and No choppers

Requirements: At minimum we need the following

  1. - Beam through bunch length cavity
  2. - More than 5uA tune beam
  3. - 200 keV energy or higher
  4. - Bunch length less than 30 degree of 1497 (typical low current beam at the gun)

Procedure:

  1. ) With choppers and buncher off, thread the 200 keV beam from gun up through the bunch length cavity.
  2. ) Setup more than 5uA tune beam (preferably to a beam dump or Fcup).
  3. ) Check the bunch length system by answering the following questions
  4. ) Do you see the bunch length output signal? If not stop and investigate.
  5. ) Does the bunch length signal change as the gun laser phase changes (multiples of 5 degrees, up to +/- 50 deg)? If not stop and investigate. Does the amount of change make sense?
  6. ) Does the bunch length signal changes as the 6 GHz reference signal phase is change (+/- 180 deg)? If not investigate.
  7. ) When all questions above have positive answer, the test is complete and system is checked for hardware.