=== Mar 13, 2023 ===
+
= Thursday, Mar 16, 2023 =
 +
==== Starting Monday....CIS coordinators ====
 +
* Will attend the 8am meeting(s), join the 8:30am zoom afterwards...
 +
** 3/20 - 4/3: Joe
 +
** 4/3 - 4/17: Carlos
 +
** 4/17 - 5/1: Marcy
 +
** 5/1 -  5/15: Riad
 +
 
 +
==== UITF status ====
 +
* Recap from yesterday, plans for today...
 +
* UITF now in stasis, future plans under discussion
 +
 
 +
==== CEBAF jobs ====
 +
* CEBAF SAD end date maybe still in review....
 +
* Marcy's schedule...
 +
* Harp/viewer vacuum test result...?
 +
 
 +
= Thursday, Mar 16, 2023 =
 +
 
 +
==== UITF status ====
 +
* Recap from yesterday, plans for today...
 +
 
 +
==== CEBAF jobs ====
 +
* Harp/viewer vacuum tests today?
 +
 
 +
= Wednesday, Mar 15, 2023 =
 +
==== Machine shop jobs ====
 +
* HV chamber base plate modification (signed) - https://mis.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331529
 +
* Fabricate new gun feet (signed) - https://mis.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331530
 +
 
 +
==== UITF jobs ====
 +
* Plans for today and tomorrow...
 +
 
 +
==== CEBAF jobs ====
 +
* All materials present during beam operations should be surveyed - https://logbooks.jlab.org/entry/4108499
 +
* Matt's SAD details [[media:SAD 2023_injector_weeks_1_2.docx]]
 +
* Week #1
 +
: CIS stay out of S&A way Mon/Tue, DC (or CIS) can remove 2I gun magnets after they're gone, latest Wed 9am
 +
: CIS will label/stage ~5 things in ISB on Mon/Tue for INSTALL to crane to tunnel on Tue/Wed
 +
: CIS will make QE/laser retro checks on Mon/Tue after S&A done, need 4-laser RF on
 +
: CIS disconnect IP's & vent VBV0I02-VBV0I07 (choppers) for repair 0I02 viewer/harp with I&C, Wed or Thu (RF lock out chopper RF by Tue)
 +
 
 +
* Week #2
 +
: CIS works under clean hood to remove present HV chamber from gun table
 +
: CIS works with S&A and INSTALL and ME to temporarily move gun table off to side, locate/anchor new gun feet to floor, and put table back
 +
: CIS works with S&A under clean hood to install/align 200 kV HV chamber and NEG tube
 +
: By end of week #2 CIS can accomodate "dirty" work.
 +
 
 +
==== Drury's SRF job in nutshell ====
 +
: 3/27 Warm up quarter
 +
: 4/12 - 4/18 prep the quarter for removal
 +
: 4/19 - remove quarter from injector
 +
: 4/20 -  install bracing for microphonics mitigation
 +
: 4/21 - install booster
 +
: 4/24 - 4/28 prep booster for 4K cool down
 +
: 5/1 - Cool down booster
 +
 
 +
= Tuesday, Mar 14, 2023 =
 +
==== UITF jobs ... ====
 +
* Yesterday's run down...
 +
* Today, what's happening...
 +
* When does Vince get the plate...?
 +
 
 +
==== CEBAF jobs ... ====
 +
* Neil would like list of things to crane, should be prepped prior day for:
 +
** Tue 3/21 (...)
 +
** Wed 3/22 (...)
 +
* Viewer/harp ...
 +
** Which day to vent?
 +
** Will ask Nate for help, yes?
 +
 
 +
= Monday, Mar 13, 2023 =
 
==== UITF jobs ... ====
 
==== UITF jobs ... ====
 
* Max status
 
* Max status
Line 5: Line 76:
 
* HV cable disconnect
 
* HV cable disconnect
 
* Magnet, bpms, bias, rad probe disconnects
 
* Magnet, bpms, bias, rad probe disconnects
 +
* Modify base plate - https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331529
  
 
==== CEBAF jobs next week ... ====
 
==== CEBAF jobs next week ... ====
Line 15: Line 87:
 
** Vent chopper, repair viewer/harp
 
** Vent chopper, repair viewer/harp
  
=== Mar 10, 2023 ===
+
= Friday, Mar 10, 2023 =
 
* Joe
 
* Joe
 
:: ...found Gun2 has Bulk #32 puck for HV conditioning (i.e. don't need to bring one from UITF) - https://logbooks.jlab.org/entry/3876517
 
:: ...found Gun2 has Bulk #32 puck for HV conditioning (i.e. don't need to bring one from UITF) - https://logbooks.jlab.org/entry/3876517

Latest revision as of 08:29, 17 March 2023

Thursday, Mar 16, 2023

Starting Monday....CIS coordinators

  • Will attend the 8am meeting(s), join the 8:30am zoom afterwards...
    • 3/20 - 4/3: Joe
    • 4/3 - 4/17: Carlos
    • 4/17 - 5/1: Marcy
    • 5/1 - 5/15: Riad

UITF status

  • Recap from yesterday, plans for today...
  • UITF now in stasis, future plans under discussion

CEBAF jobs

  • CEBAF SAD end date maybe still in review....
  • Marcy's schedule...
  • Harp/viewer vacuum test result...?

Thursday, Mar 16, 2023

UITF status

  • Recap from yesterday, plans for today...

CEBAF jobs

  • Harp/viewer vacuum tests today?

Wednesday, Mar 15, 2023

Machine shop jobs

UITF jobs

  • Plans for today and tomorrow...

CEBAF jobs

CIS stay out of S&A way Mon/Tue, DC (or CIS) can remove 2I gun magnets after they're gone, latest Wed 9am
CIS will label/stage ~5 things in ISB on Mon/Tue for INSTALL to crane to tunnel on Tue/Wed
CIS will make QE/laser retro checks on Mon/Tue after S&A done, need 4-laser RF on
CIS disconnect IP's & vent VBV0I02-VBV0I07 (choppers) for repair 0I02 viewer/harp with I&C, Wed or Thu (RF lock out chopper RF by Tue)
  • Week #2
CIS works under clean hood to remove present HV chamber from gun table
CIS works with S&A and INSTALL and ME to temporarily move gun table off to side, locate/anchor new gun feet to floor, and put table back
CIS works with S&A under clean hood to install/align 200 kV HV chamber and NEG tube
By end of week #2 CIS can accomodate "dirty" work.

Drury's SRF job in nutshell

3/27 Warm up quarter
4/12 - 4/18 prep the quarter for removal
4/19 - remove quarter from injector
4/20 - install bracing for microphonics mitigation
4/21 - install booster
4/24 - 4/28 prep booster for 4K cool down
5/1 - Cool down booster

Tuesday, Mar 14, 2023

UITF jobs ...

  • Yesterday's run down...
  • Today, what's happening...
  • When does Vince get the plate...?

CEBAF jobs ...

  • Neil would like list of things to crane, should be prepped prior day for:
    • Tue 3/21 (...)
    • Wed 3/22 (...)
  • Viewer/harp ...
    • Which day to vent?
    • Will ask Nate for help, yes?

Monday, Mar 13, 2023

UITF jobs ...

CEBAF jobs next week ...

  • Neil's jobs/when
  • 1st week of SAD
    • S&A first two days
    • Test laser retro, store puck, LTT laser
    • CIS move things to tunnel
    • Vent chopper, repair viewer/harp

Friday, Mar 10, 2023

  • Joe
...found Gun2 has Bulk #32 puck for HV conditioning (i.e. don't need to bring one from UITF) - https://logbooks.jlab.org/entry/3876517
...things to do on Monday ... isolate laser, vacuum valves, disconnect electrical things, stow pucks, HV cable disconnect, move toward clean room
...EH&S approved their part (but needs HV OSP in place if we go that route) => * ATLIS => https://tasklists.jlab.org/atlis/tasks/108541
  • Max
...running final beam test, plans to wrap up today, latest Sunday
...coordinating w/ DC Power and I&C to de-energize and disconnect cables to magnets and bpm's
  • Marcy
...polishing CEBAF install work plan gantt chart, will circulate and review on Monday
...coordinating w/ Vince for modification of "blue" HV chamber base plate next week
  • Steve
...has plan to work with Scott and to document racks/controls during SAD
...let's review laser plan with Shukui (replace Hall A mode-lock with temp regulating seed, continue developing/testing new board for later upgrade)