Difference between revisions of "Running Daily Phase 2 Minutes"

From Ciswikidb
Jump to navigation Jump to search
Line 3: Line 3:
 
:: ...found Gun2 has Bulk #32 puck for HV conditioning (i.e. don't need to bring one from UITF) - https://logbooks.jlab.org/entry/3876517
 
:: ...found Gun2 has Bulk #32 puck for HV conditioning (i.e. don't need to bring one from UITF) - https://logbooks.jlab.org/entry/3876517
 
:: ...things to do on Monday ... isolate laser, vacuum valves, disconnect electrical things, stow pucks, HV cable disconnect, move toward clean room
 
:: ...things to do on Monday ... isolate laser, vacuum valves, disconnect electrical things, stow pucks, HV cable disconnect, move toward clean room
:: ...Carlos' ATLIS here => * ATLIS => https://tasklists.jlab.org/atlis/tasks/108541
+
:: ...Here's ATLIS to use for logbook updates => * ATLIS => https://tasklists.jlab.org/atlis/tasks/108541
 
* Max
 
* Max
 
:: ...running final beam test, plans to wrap up today, latest Sunday
 
:: ...running final beam test, plans to wrap up today, latest Sunday

Revision as of 10:42, 10 March 2023

Mar 10, 2023

  • Joe
...found Gun2 has Bulk #32 puck for HV conditioning (i.e. don't need to bring one from UITF) - https://logbooks.jlab.org/entry/3876517
...things to do on Monday ... isolate laser, vacuum valves, disconnect electrical things, stow pucks, HV cable disconnect, move toward clean room
...Here's ATLIS to use for logbook updates => * ATLIS => https://tasklists.jlab.org/atlis/tasks/108541
  • Max
...running final beam test, plans to wrap up today, latest Sunday
...coordinating w/ DC Power and I&C to de-energize and disconnect cables to magnets and bpm's
  • Marcy
...polishing CEBAF install work plan gantt chart, will circulate and review on Monday
...coordinating w/ Vince for modification of "blue" HV chamber base plate next week
  • Steve
...has plan to work with Scott and to document racks/controls during SAD
...let's review laser plan with Shukui (replace Hall A mode-lock with temp regulating seed, continue developing/testing new board for later upgrade)