Difference between revisions of "Sep 08, 2021 - Group Meeting"
From Ciswikidb
Line 3: | Line 3: | ||
Phase 1 Region | Phase 1 Region | ||
* Install 200 kV w/o field emission | * Install 200 kV w/o field emission | ||
− | * Replace DR dipole => PO | + | * Replace DR dipole => PO written week of Aug 30 for new DM at CEBAF, UITF and 2 spare coils |
* Replace noisy Wien 20A SCE | * Replace noisy Wien 20A SCE | ||
* Repair leaky PCUP LCW fitting | * Repair leaky PCUP LCW fitting |
Revision as of 08:55, 7 September 2021
2022 Winter SAD ATLIS Tasks
Phase 1 Region
- Install 200 kV w/o field emission
- Replace DR dipole => PO written week of Aug 30 for new DM at CEBAF, UITF and 2 spare coils
- Replace noisy Wien 20A SCE
- Repair leaky PCUP LCW fitting
- Remake A2 joint
- Replace harp
- Install & 200 kV kicker
- Phase 2 Region
- Possibly install solenoid/valve downstream of chopper => MMF mapping solenoids in Sep. Do we have 2-3/4" pneumatic beam line valve?
- Install bright lighting => Walked area with FM. Waiting for follow-up.
CEBAF 200 kV Gun
- Carlos - Status of small gun HV limits, CEBAF and UITF
- Carlos - GTS gun HV design, i.e. reaching >200 kV w/o field emission
- Gabriel - Picking the anode to eliminate kick