- 08:29, 20 October 2020 diff hist +363 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:21, 19 October 2020 diff hist +130 CEBAF Injector Upgrade →ATLIS Tasks
- 13:15, 19 October 2020 diff hist +142 CIS Phase 1 work plans →Fire System Work
- 13:10, 19 October 2020 diff hist +86 CIS Phase 1 work plans →Fire System Work
- 12:45, 19 October 2020 diff hist +26 CIS Phase 1 work plans
- 09:27, 16 October 2020 diff hist -35 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 08:59, 16 October 2020 diff hist +2 CIS Phase 1 work plans
- 17:10, 15 October 2020 diff hist 0 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23)
- 16:57, 15 October 2020 diff hist -14 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 16:55, 15 October 2020 diff hist -33 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23)
- 16:54, 15 October 2020 diff hist +9 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23)
- 16:54, 15 October 2020 diff hist -1 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23)
- 16:53, 15 October 2020 diff hist +306 CIS Phase 1 work plans
- 16:47, 15 October 2020 diff hist +414 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 09:07, 15 October 2020 diff hist +434 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 14:36, 14 October 2020 diff hist +111 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 14:25, 14 October 2020 diff hist +159 N Tunnel Photos Oct14 2020 Created page with " 1000px 1000px 1000px" current
- 14:22, 14 October 2020 diff hist +327 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 14:18, 14 October 2020 diff hist +1 CEBAF Injector Upgrade →Quick Links
- 14:17, 14 October 2020 diff hist 0 N File:Oct14 Chopper LookingUpstream.JPG current
- 14:17, 14 October 2020 diff hist 0 N File:Oct14 Ychamber LookingDownstream.JPG current
- 14:17, 14 October 2020 diff hist 0 N File:Oct14 Gun2 LookingDownstream.JPG current
- 14:13, 14 October 2020 diff hist +131 N Penetration135 Created page with "Entrance: IN03B17 Exit: Above middle of 0L03 cryomodule (first full zone) 1000px file:InjSB Racks.png"
- 14:12, 14 October 2020 diff hist +123 N Penetration108 Created page with "Entrance: IN03B04 Exit: Above harp IHA0L03, just before PSS fence 1000px file:InjSB Racks.png"
- 14:11, 14 October 2020 diff hist +121 N Penetration86 Created page with "Entrance: IN02B23 Exit: above MQJ0L02, just past plastic barrier 1000px file:InjSB Racks.png"
- 14:10, 14 October 2020 diff hist +107 N Penetration58 Created page with "Entrance: IN02B10 Exit: Above buncher cavity ~0I05 1000px File:InjSB Racks.png"
- 14:09, 14 October 2020 diff hist +1 PenetrationALH
- 14:08, 14 October 2020 diff hist +9 PenetrationALH
- 14:07, 14 October 2020 diff hist -1 PenetrationALH
- 14:06, 14 October 2020 diff hist +127 N PenetrationALH Created page with "Entrance: IN01B06 Exit: Above Laser hut, ~across for where Y-chamber would be. file:Pene108.JPG file:InjSB_Racks.png"
- 14:04, 14 October 2020 diff hist 0 N File:Pene108.JPG current
- 14:04, 14 October 2020 diff hist 0 N File:Pene135.JPG current
- 14:04, 14 October 2020 diff hist 0 N File:Pene86.JPG current
- 14:04, 14 October 2020 diff hist 0 N File:PeneLH.JPG current
- 14:04, 14 October 2020 diff hist 0 N File:Pene58.JPG current
- 13:58, 14 October 2020 diff hist +75 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 13:57, 14 October 2020 diff hist +2 CIS Phase 1 work plans
- 13:56, 14 October 2020 diff hist +156 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 13:51, 14 October 2020 diff hist 0 File:InjSB Racks.png Moser uploaded a new version of File:InjSB Racks.png current
- 13:50, 14 October 2020 diff hist 0 File:InjSB Racks.png Moser uploaded a new version of File:InjSB Racks.png
- 13:50, 14 October 2020 diff hist 0 File:InjSB Racks.png Moser uploaded a new version of File:InjSB Racks.png
- 09:05, 14 October 2020 diff hist +1 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 09:04, 14 October 2020 diff hist +445 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 17:00, 13 October 2020 diff hist +3 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23)
- 16:58, 13 October 2020 diff hist +135 CIS Phase 1 work plans
- 09:29, 13 October 2020 diff hist +358 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 20:11, 12 October 2020 diff hist +41 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18)
- 14:50, 12 October 2020 diff hist +52 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18)
- 14:35, 12 October 2020 diff hist +403 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18)
- 14:32, 12 October 2020 diff hist 0 N File:InjSB Racks.png
- 14:28, 12 October 2020 diff hist +715 CIS Phase 1 work plans
- 09:00, 12 October 2020 diff hist +72 CEBAF Injector Upgrade →Quick Links
- 13:51, 9 October 2020 diff hist 0 File:Oct2020 Moser.odp Moser uploaded a new version of File:Oct2020 Moser.odp current
- 12:59, 9 October 2020 diff hist -1 Weekly phone call - October 9, 2020 →Agenda current
- 12:59, 9 October 2020 diff hist -41 Weekly phone call - October 9, 2020 →Agenda
- 12:59, 9 October 2020 diff hist +2 Weekly phone call - October 9, 2020 →Agenda
- 12:58, 9 October 2020 diff hist -1 Weekly phone call - October 9, 2020 →Agenda
- 12:58, 9 October 2020 diff hist +59 Weekly phone call - October 9, 2020 →Agenda
- 12:57, 9 October 2020 diff hist 0 N File:Oct2020 Moser.odp
- 08:13, 9 October 2020 diff hist +46 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 08:13, 9 October 2020 diff hist +63 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 08:10, 9 October 2020 diff hist +96 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 19:55, 7 October 2020 diff hist +125 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 19:54, 7 October 2020 diff hist -422 CIS Phase 1 work plans
- 19:49, 7 October 2020 diff hist +422 CIS Phase 1 work plans
- 19:20, 7 October 2020 diff hist +115 CEBAF Injector Upgrade →ATLIS Tasks
- 09:15, 7 October 2020 diff hist +212 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 09:12, 7 October 2020 diff hist -1 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 09:09, 7 October 2020 diff hist 0 N File:InjSB-Oct7th.png current
- 08:29, 7 October 2020 diff hist +28 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 08:28, 7 October 2020 diff hist 0 N File:InjSB-10.7.20.jpg current
- 08:03, 7 October 2020 diff hist +17 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 19:54, 6 October 2020 diff hist +3 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 19:53, 6 October 2020 diff hist -1 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 19:53, 6 October 2020 diff hist +5 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 19:52, 6 October 2020 diff hist +123 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 19:34, 6 October 2020 diff hist -3 CEBAF Injector Upgrade →ATLIS Tasks
- 13:00, 6 October 2020 diff hist 0 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 12:59, 6 October 2020 diff hist +4 Unknown Pene for Choppers current
- 12:59, 6 October 2020 diff hist +2 Unknown Pene for Choppers
- 12:58, 6 October 2020 diff hist +14 Unknown Pene for Choppers
- 12:58, 6 October 2020 diff hist -1 Unknown Pene for Choppers
- 12:57, 6 October 2020 diff hist +3 Unknown Pene for Choppers
- 12:56, 6 October 2020 diff hist 0 N File:Inj Pen2W.jpg current
- 12:55, 6 October 2020 diff hist 0 N File:Inj Pen1.jpg current
- 12:55, 6 October 2020 diff hist +42 N Unknown Pene for Choppers Created page with "File:Example.jpg File:Example.jpg"
- 12:54, 6 October 2020 diff hist +51 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 12:52, 6 October 2020 diff hist +106 CEBAF Injector Upgrade
- 08:27, 6 October 2020 diff hist +428 CIS Phase 1 work plans
- 17:06, 5 October 2020 diff hist +6 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 16:49, 5 October 2020 diff hist +1 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 16:49, 5 October 2020 diff hist +256 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 08:05, 5 October 2020 diff hist -1,113 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 08:05, 5 October 2020 diff hist +1,112 N Tue 9/29 – Fri 10/1 Table Created page with "; <u>'''Tunnel Work'''</u> {| class="wikitable" |- ! Time !! Mon 9/28 !! Tue 9/29 !! Wed 9/30 !! Thu 10/1 !! F 10/2 |- | 4a - 8a || || I&C; 5a: Francis: BPMs, Cups, Apertu..." current
- 08:04, 5 October 2020 diff hist +2 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 08:04, 5 October 2020 diff hist -12 CIS Phase 1 work plans
- 08:55, 2 October 2020 diff hist +61 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 08:53, 2 October 2020 diff hist +29 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 08:51, 2 October 2020 diff hist +20 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 19:22, 1 October 2020 diff hist +20 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects