- 10:48, 13 April 2021 diff hist +18 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 10:47, 13 April 2021 diff hist +148 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 10:45, 13 April 2021 diff hist +152 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 08:20, 13 April 2021 diff hist +30 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 20:37, 12 April 2021 diff hist +14 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 20:35, 12 April 2021 diff hist +10 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 20:33, 12 April 2021 diff hist +174 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 20:19, 12 April 2021 diff hist +37 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 19:46, 12 April 2021 diff hist +20 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 17:17, 12 April 2021 diff hist -7 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 17:16, 12 April 2021 diff hist -25 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 17:08, 12 April 2021 diff hist +1 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 17:08, 12 April 2021 diff hist -5 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 17:06, 12 April 2021 diff hist +268 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 09:39, 12 April 2021 diff hist 0 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 09:21, 12 April 2021 diff hist +2 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 09:19, 12 April 2021 diff hist +85 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 09:16, 12 April 2021 diff hist +57 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 09:05, 12 April 2021 diff hist +253 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 08:28, 12 April 2021 diff hist +9 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 08:27, 12 April 2021 diff hist +41 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 08:19, 12 April 2021 diff hist +107 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 14:42, 9 April 2021 diff hist +13 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 14:42, 9 April 2021 diff hist +54 CIS Phase 1 work plans
- 14:41, 9 April 2021 diff hist 0 N File:InjSB Racks no pene.png current
- 14:38, 9 April 2021 diff hist +27 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 14:38, 9 April 2021 diff hist +27 Phase 1 - HCO & Commissioning →System Readiness / HCO Schedule (April '21)
- 14:37, 9 April 2021 diff hist -17 Phase 1 - HCO & Commissioning →System Readiness / HCO Schedule (April '21)
- 14:36, 9 April 2021 diff hist +110 Phase 1 - HCO & Commissioning →System Readiness / HCO Schedule (April '21)
- 14:36, 9 April 2021 diff hist +41 Phase 1 - HCO & Commissioning →System Readiness / HCO Schedule (April '21)
- 14:28, 9 April 2021 diff hist +18 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 14:20, 9 April 2021 diff hist +47 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 13:47, 9 April 2021 diff hist -4,630 CIS Phase 1 work plans
- 10:00, 9 April 2021 diff hist +291 CIS Phase 1 work plans →Penetration Work
- 17:31, 8 April 2021 diff hist +25 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 17:05, 8 April 2021 diff hist -8 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 07:49, 8 April 2021 diff hist +44 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 20:31, 7 April 2021 diff hist +41 Phase 1 - HCO & Commissioning →Beam Commissioning (May 3 - Jul 2)
- 20:30, 7 April 2021 diff hist 0 N File:210407 Phase1 Commissioning.docx current
- 20:30, 7 April 2021 diff hist -207 Phase 1 - HCO & Commissioning
- 18:06, 7 April 2021 diff hist +101 Phase 1 →ATLIS Tasks
- 17:05, 7 April 2021 diff hist -34 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 14:08, 7 April 2021 diff hist -1 Phase 1 - HCO & Commissioning →Activities
- 13:54, 7 April 2021 diff hist +1 Phase 1 - HCO & Commissioning →Activities
- 13:52, 7 April 2021 diff hist -1 Phase 1 - HCO & Commissioning →Activities
- 13:52, 7 April 2021 diff hist -67 Phase 1 - HCO & Commissioning →Activities
- 13:51, 7 April 2021 diff hist 0 N File:Beam commissioning by type.png current
- 13:50, 7 April 2021 diff hist +2 Phase 1 - HCO & Commissioning →Beam Commissioning (May 3 - Jul 2)
- 11:51, 7 April 2021 diff hist +47 Phase 1 - HCO & Commissioning →ATLis Testplans
- 11:49, 7 April 2021 diff hist +1,058 Phase 1 - HCO & Commissioning →ATLis Testplans
- 09:34, 7 April 2021 diff hist +435 Phase 1 - HCO & Commissioning →Beam Commissioning (May 3 - Jul 2)
- 09:34, 7 April 2021 diff hist 0 N File:3.31.21 BeamCommissioningPlanLayout AIPINJ-1 firstpass.ods current
- 09:30, 7 April 2021 diff hist 0 N File:BeamINJphase1v5.pptx current
- 09:27, 7 April 2021 diff hist 0 N File:210401 Phase1 Commissioning.docx current
- 09:25, 7 April 2021 diff hist -13 Phase 1 - HCO & Commissioning →System Readiness / HCO Schedule (April '21)
- 09:25, 7 April 2021 diff hist -9 Phase 1 - HCO & Commissioning →Beam Commissioning (May 3 - Jul 2)
- 09:21, 7 April 2021 diff hist +204 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 09:19, 7 April 2021 diff hist +18 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 09:17, 7 April 2021 diff hist -62 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 09:15, 7 April 2021 diff hist -19 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 18:02, 6 April 2021 diff hist +4 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 17:46, 6 April 2021 diff hist -10 Phase 1 - HCO & Commissioning →System Readiness / HCO Schedule (April '21)
- 17:46, 6 April 2021 diff hist -1,921 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 16:58, 6 April 2021 diff hist +26 Phase 1 - HCO & Commissioning →System Readiness / HCO Schedule (April '21)
- 16:53, 6 April 2021 diff hist -14 Phase 1 - HCO & Commissioning →System Readiness / HCO Schedule (April '21)
- 16:52, 6 April 2021 diff hist +20 Phase 1 - HCO & Commissioning →System Readiness / HCO Schedule (April '21)
- 16:46, 6 April 2021 diff hist +18 Phase 1 - HCO & Commissioning →System Readiness / HCO Schedule (April '21)
- 16:44, 6 April 2021 diff hist 0 Phase 1 - HCO & Commissioning →System Readiness / HCO Schedule (April '21)
- 16:44, 6 April 2021 diff hist -37 Phase 1 - HCO & Commissioning →System Readiness / HCO Schedule (April '21)
- 16:35, 6 April 2021 diff hist -63 CIS Phase 1 work plans →Week 28 (Apr 12 - Apr 16)
- 16:22, 6 April 2021 diff hist +96 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 16:19, 6 April 2021 diff hist +122 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 15:48, 6 April 2021 diff hist -37 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 08:50, 6 April 2021 diff hist +213 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 08:11, 6 April 2021 diff hist +13 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 20:12, 5 April 2021 diff hist +8 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 15:37, 5 April 2021 diff hist +25 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 10:13, 5 April 2021 diff hist -27 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 10:12, 5 April 2021 diff hist +26 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 10:10, 5 April 2021 diff hist +65 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 10:08, 5 April 2021 diff hist +339 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 09:54, 5 April 2021 diff hist -1 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 09:52, 5 April 2021 diff hist +174 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 08:24, 5 April 2021 diff hist +64 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 08:13, 5 April 2021 diff hist +1 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 08:12, 5 April 2021 diff hist +101 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 18:15, 2 April 2021 diff hist +6 CIS Phase 1 work plans →Penetration Work
- 18:15, 2 April 2021 diff hist 0 CIS Phase 1 work plans →Penetration Work
- 18:14, 2 April 2021 diff hist +216 CIS Phase 1 work plans →Penetration Work
- 18:12, 2 April 2021 diff hist +2 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 18:11, 2 April 2021 diff hist +84 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 18:11, 2 April 2021 diff hist -2 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 18:10, 2 April 2021 diff hist -2 CIS Phase 1 work plans →Week 27 (Apr 5 - Apr 9)
- 17:56, 2 April 2021 diff hist +93 CIS Phase 1 work plans
- 12:33, 2 April 2021 diff hist +1 Phase 1 - HCO & Commissioning →Beam Commissioning (May 3 - Jul 2)
- 12:32, 2 April 2021 diff hist +40 Phase 1 - HCO & Commissioning →Beam Commissioning (May 3 - Jul 2)
- 12:32, 2 April 2021 diff hist 0 N File:BeamDrivers Pt2 3.16.21.pdf current
- 08:20, 2 April 2021 diff hist +50 CIS Phase 1 work plans →Week 26 (Mar 29 - Apr 2)
- 09:01, 1 April 2021 diff hist +78 CIS Phase 1 work plans →Week 26 (Mar 29 - Apr 2)
- 08:57, 1 April 2021 diff hist +85 CIS Phase 1 work plans →Week 26 (Mar 29 - Apr 2)