23 April 2021
13:21 | Phase 1 - HCO & Commissioning (10 changes | history) . . (+13,604) . . [Moser (10×)] | |
13:21 (cur | prev) . . (+8,667) . . Moser (Talk | contribs) (→Beam Commissioning Schedule) | ||
13:10 (cur | prev) . . (-8) . . Moser (Talk | contribs) (→Beam Commissioning Schedule) | ||
13:04 (cur | prev) . . (0) . . Moser (Talk | contribs) (→System Readiness / HCO Schedule (April '21)) | ||
13:01 (cur | prev) . . (+3,422) . . Moser (Talk | contribs) (→Beam Commissioning Schedule) | ||
12:55 (cur | prev) . . (+3,374) . . Moser (Talk | contribs) (→Beam Commissioning Schedule) | ||
12:37 (cur | prev) . . (+600) . . Moser (Talk | contribs) (→Beam Commissioning Schedule) | ||
12:27 (cur | prev) . . (+324) . . Moser (Talk | contribs) (→Beam Commissioning Schedule) | ||
12:24 (cur | prev) . . (-58) . . Moser (Talk | contribs) (→Beam Commissioning Schedule) | ||
12:11 (cur | prev) . . (+19) . . Moser (Talk | contribs) (→Beam Commissioning Schedule) | ||
12:08 (cur | prev) . . (-2,736) . . Moser (Talk | contribs) (→Beam Commissioning Schedule) |
09:03 | WF Wien Filters (200 kV upgrade) (3 changes | history) . . (+14) . . [Chgarcia (3×)] | |
09:03 (cur | prev) . . (-24) . . Chgarcia (Talk | contribs) (→Field maps for GPT simulations) | ||
09:02 (cur | prev) . . (+24) . . Chgarcia (Talk | contribs) (→Field maps for GPT simulations) | ||
09:01 (cur | prev) . . (+14) . . Chgarcia (Talk | contribs) (→Link to Gabriel's CST Electric field maps and GPT simulations) |
09:02 | (Upload log) . . Chgarcia (Talk | contribs) uploaded File:Wien field maps documentation.pdf |
08:27 | CIS Phase 1 work plans (2 changes | history) . . (+585) . . [Moser (2×)] | |
08:27 (cur | prev) . . (+538) . . Moser (Talk | contribs) (→Week 30 (Apr 26 - Apr 30)) | ||
08:13 (cur | prev) . . (+47) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) |
22 April 2021
19:21 | Phase 1 - HCO & Commissioning (8 changes | history) . . (+677) . . [Moser (8×)] | |
19:21 (cur | prev) . . (-14) . . Moser (Talk | contribs) (→Beam Commissioning Planning) | ||
19:21 (cur | prev) . . (+7) . . Moser (Talk | contribs) | ||
19:20 (cur | prev) . . (+2) . . Moser (Talk | contribs) | ||
19:19 (cur | prev) . . (+10) . . Moser (Talk | contribs) (→Beam Commissioning (May 3 - Jul 2)) | ||
13:17 (cur | prev) . . (+1) . . Moser (Talk | contribs) (→System Readiness / HCO Schedule (April '21)) | ||
13:17 (cur | prev) . . (+28) . . Moser (Talk | contribs) (→System Readiness / HCO Schedule (April '21)) | ||
13:16 (cur | prev) . . (-51) . . Moser (Talk | contribs) (→System Readiness / HCO Schedule (April '21)) | ||
13:16 (cur | prev) . . (+694) . . Moser (Talk | contribs) (→System Readiness / HCO Schedule (April '21)) |
19:16 | CIS Phase 1 work plans (7 changes | history) . . (+3,513) . . [Moser (7×)] | |
19:16 (cur | prev) . . (+2,683) . . Moser (Talk | contribs) | ||
18:59 (cur | prev) . . (+5) . . Moser (Talk | contribs) (→Week 30 (Apr 26 - Apr 30)) | ||
16:26 (cur | prev) . . (+328) . . Moser (Talk | contribs) (→Week 30 (Apr 26 - Apr 30)) | ||
13:55 (cur | prev) . . (+318) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
13:49 (cur | prev) . . (+79) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
13:45 (cur | prev) . . (+28) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
13:44 (cur | prev) . . (+72) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) |
16:20 | Phase 1 (diff | hist) . . (+242) . . Moser (Talk | contribs) (→ATLIS Tasks) |
12:49 | (Upload log) . . [Poelker; Sajini] | |
12:49 . . Sajini (Talk | contribs) uploaded File:IPAC2021 SajiniWijethunga.pdf | ||
12:30 . . Poelker (Talk | contribs) uploaded File:Phase2 beamline 4 22 21.png |
12:48 | CIS Conference and Workshop Proceedings (diff | hist) . . (+40) . . Sajini (Talk | contribs) |
N 12:30 | Phase2 ME meeting minutes 4 22 2021 (3 changes | history) . . (+2,273) . . [Poelker (3×)] | |
12:30 (cur | prev) . . (+57) . . Poelker (Talk | contribs) | ||
12:13 (cur | prev) . . (+3) . . Poelker (Talk | contribs) | ||
N | 12:13 (cur | prev) . . (+2,213) . . Poelker (Talk | contribs) (Created page with "phase2 ME design meeting minutes 4_22_2021 SHaun, Gary, Matt and Danny Gary made great progress on the phase2 layout, addressing most of the issues discussed last meeting. S...") |
11:57 | AIPINJ - Phase 2 Upgrade Meetings (diff | hist) . . (+43) . . Poelker (Talk | contribs) |
21 April 2021
20:43 | CIS Phase 1 work plans (7 changes | history) . . (+138) . . [Moser (7×)] | |
20:43 (cur | prev) . . (+21) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
20:34 (cur | prev) . . (-6) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
19:24 (cur | prev) . . (+79) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
19:21 (cur | prev) . . (+4) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
19:15 (cur | prev) . . (+40) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
10:58 (cur | prev) . . (-5) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
08:06 (cur | prev) . . (+5) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) |
09:43 | (Upload log) . . [Grames (2×)] | |
09:43 . . Grames (Talk | contribs) uploaded File:210421 Carlos PPB meeting.pdf | ||
08:16 . . Grames (Talk | contribs) uploaded File:210419 Magnet Wiring v6.docx |
09:43 | PPB - Apr 21, 2021 (diff | hist) . . (+40) . . Grames (Talk | contribs) |
08:26 | 2021-04-21 (3 changes | history) . . (-38) . . [Michaelm (3×)] | |
08:26 (cur | prev) . . (+75) . . Michaelm (Talk | contribs) (→Schedule) | ||
08:26 (cur | prev) . . (-77) . . Michaelm (Talk | contribs) (→Reports on Open Action Items:) | ||
08:25 (cur | prev) . . (-36) . . Michaelm (Talk | contribs) (→Schedule) |
08:21 | Phase 1 (5 changes | history) . . (+285) . . [Grames (5×)] | |
08:21 (cur | prev) . . (+49) . . Grames (Talk | contribs) | ||
08:19 (cur | prev) . . (+7) . . Grames (Talk | contribs) | ||
08:18 (cur | prev) . . (+40) . . Grames (Talk | contribs) | ||
08:16 (cur | prev) . . (+27) . . Grames (Talk | contribs) | ||
08:15 (cur | prev) . . (+162) . . Grames (Talk | contribs) |
20 April 2021
19:38 | CIS Phase 1 work plans (6 changes | history) . . (+793) . . [Moser (6×)] | |
19:38 (cur | prev) . . (+46) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
19:07 (cur | prev) . . (-28) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
18:56 (cur | prev) . . (+90) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
09:36 (cur | prev) . . (+651) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
08:11 (cur | prev) . . (-22) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
08:00 (cur | prev) . . (+56) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) |
18:30 | Phase 1 - HCO & Commissioning (17 changes | history) . . (+12,885) . . [Moser (17×)] | |
18:30 (cur | prev) . . (+98) . . Moser (Talk | contribs) (→Beam Commissioning (May 3 - Jul 2)) | ||
18:26 (cur | prev) . . (-51) . . Moser (Talk | contribs) (→Beam Commissioning (May 3 - Jul 2)) | ||
18:21 (cur | prev) . . (-29) . . Moser (Talk | contribs) (→Activities) | ||
18:16 (cur | prev) . . (-37) . . Moser (Talk | contribs) (→Activities) | ||
18:12 (cur | prev) . . (+2,964) . . Moser (Talk | contribs) (→Activities) | ||
18:05 (cur | prev) . . (+3,535) . . Moser (Talk | contribs) (→Activities) | ||
17:54 (cur | prev) . . (+3,165) . . Moser (Talk | contribs) (→Activities) | ||
17:44 (cur | prev) . . (-466) . . Moser (Talk | contribs) (→Activities) | ||
17:43 (cur | prev) . . (0) . . Moser (Talk | contribs) (→Activities) | ||
17:41 (cur | prev) . . (+245) . . Moser (Talk | contribs) (→Activities) | ||
17:40 (cur | prev) . . (+35) . . Moser (Talk | contribs) (→Activities) | ||
17:38 (cur | prev) . . (0) . . Moser (Talk | contribs) (→Activities) | ||
17:36 (cur | prev) . . (-35) . . Moser (Talk | contribs) (→Activities) | ||
17:34 (cur | prev) . . (+36) . . Moser (Talk | contribs) | ||
17:31 (cur | prev) . . (-153) . . Moser (Talk | contribs) (→Activities) | ||
17:25 (cur | prev) . . (+3,499) . . Moser (Talk | contribs) (→Activities) | ||
12:10 (cur | prev) . . (+79) . . Moser (Talk | contribs) (→Beam Commissioning (May 3 - Jul 2)) |
N 16:21 | PPB - Apr 21, 2021 (2 changes | history) . . (+493) . . [Grames (2×)] | |
16:21 (cur | prev) . . (+8) . . Grames (Talk | contribs) | ||
N | 16:13 (cur | prev) . . (+485) . . Grames (Talk | contribs) (Created page with "== Meeting Info == We will meet on Wed ('''UAS 9am''', JLab 11am, IJCLab 5pm) Bluejeans: https://bluejeans.com/164307983 Code to start the meeting 2864 ==Agenda == * C. Mu...") |
16:10 | PPB Meetings (diff | hist) . . (+65) . . Grames (Talk | contribs) |
15:48 | Spring 2021 - Rebuilding Photogun (diff | hist) . . (+58) . . Grames (Talk | contribs) |
15:17 | UITF Operations (9 changes | history) . . (+354) . . [Michaelm (9×)] | |
15:17 (cur | prev) . . (+38) . . Michaelm (Talk | contribs) | ||
15:12 (cur | prev) . . (+137) . . Michaelm (Talk | contribs) | ||
15:06 (cur | prev) . . (+39) . . Michaelm (Talk | contribs) | ||
14:59 (cur | prev) . . (+37) . . Michaelm (Talk | contribs) | ||
14:59 (cur | prev) . . (+33) . . Michaelm (Talk | contribs) | ||
14:57 (cur | prev) . . (0) . . Michaelm (Talk | contribs) | ||
14:56 (cur | prev) . . (0) . . Michaelm (Talk | contribs) | ||
14:56 (cur | prev) . . (+35) . . Michaelm (Talk | contribs) | ||
14:55 (cur | prev) . . (+35) . . Michaelm (Talk | contribs) |
13:36 | 2021-04-21 (3 changes | history) . . (+230) . . [Michaelm (3×)] | |
13:36 (cur | prev) . . (0) . . Michaelm (Talk | contribs) (→Reports on Open Action Items:) | ||
13:34 (cur | prev) . . (-12) . . Michaelm (Talk | contribs) (→Reports on Open Action Items:) | ||
13:26 (cur | prev) . . (+242) . . Michaelm (Talk | contribs) (→New items for discussion:) |
13:35 | (Upload log) . . [Michaelm; Moser] | |
13:35 . . Michaelm (Talk | contribs) uploaded File:Ww-longterm.4.20.21.pdf (4.20.21 version of long term schedule) | ||
12:07 . . Moser (Talk | contribs) uploaded File:Prelim sched beam commissioning.jpeg |
13:12 | To-do list (3 changes | history) . . (+50) . . [Michaelm (3×)] | |
13:12 (cur | prev) . . (+39) . . Michaelm (Talk | contribs) | ||
13:10 (cur | prev) . . (-3) . . Michaelm (Talk | contribs) | ||
13:09 (cur | prev) . . (+14) . . Michaelm (Talk | contribs) |
N 12:09 | Bubble Chamber Meeting Tuesday April 27, 2021 (diff | hist) . . (+310) . . Suleiman (Talk | contribs) (Created page with "We will meet on Tuesday April 27 at 11:00 am EST. == For those calling in we'll use the Blue Jeans [https://cc.jlab.org/bluejeans] audio conference system. == Phone number:...") |
12:09 | Planning Meetings (diff | hist) . . (+59) . . Suleiman (Talk | contribs) |
19 April 2021
19:45 | AIPINJ - Layouts (diff | hist) . . (+123) . . Moser (Talk | contribs) (→Injector Quick Reference) |
19:41 | (Upload log) . . [Grames; Michaelm; Moser] | |
19:41 . . Moser (Talk | contribs) uploaded File:12GeV injector quick reference rev17 DRAFT-5.pdf | ||
17:31 . . Grames (Talk | contribs) uploaded File:210419 CIS HCO.docx | ||
10:10 . . Michaelm (Talk | contribs) uploaded File:UITFOperators.doc (Qualified UITF Operators as of 3/26/21) |
18:29 | CIS Phase 1 work plans (5 changes | history) . . (+1,052) . . [Moser (5×)] | |
18:29 (cur | prev) . . (+64) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
18:06 (cur | prev) . . (+2) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
13:53 (cur | prev) . . (+350) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
13:35 (cur | prev) . . (+623) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
08:22 (cur | prev) . . (+13) . . Moser (Talk | contribs) (→Week 28 (Apr 12 - Apr 16)) |
17:31 | Phase 1 - HCO & Commissioning (diff | hist) . . (+61) . . Grames (Talk | contribs) |
N 14:23 | 2021-04-21 (diff | hist) . . (+1,977) . . Michaelm (Talk | contribs) (Created page with "== Meeting Information == ==== Connecting ==== To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST. # To join via a Web Browser, go to the pag...") |
14:23 | Meeting minutes (diff | hist) . . (+25) . . Michaelm (Talk | contribs) (→Experimental Meetings) |
10:09 | UITF Operations (diff | hist) . . (+6) . . Michaelm (Talk | contribs) |
10:06 | GTS meeting 4 12 21 (diff | hist) . . (+39) . . Suleiman (Talk | contribs) |
16 April 2021
17:54 | CIS Phase 1 work plans (4 changes | history) . . (+264) . . [Moser (4×)] | |
17:54 (cur | prev) . . (+44) . . Moser (Talk | contribs) (→Week 29 (Apr 19 - Apr 23)) | ||
17:53 (cur | prev) . . (+12) . . Moser (Talk | contribs) (→Week 28 (Apr 12 - Apr 16)) | ||
17:52 (cur | prev) . . (+251) . . Moser (Talk | contribs) (→Week 28 (Apr 12 - Apr 16)) | ||
08:22 (cur | prev) . . (-43) . . Moser (Talk | contribs) (→Week 28 (Apr 12 - Apr 16)) |
14:13 | CIS Student Presentations (diff | hist) . . (-61) . . Chgarcia (Talk | contribs) |
N 14:08 | Theses (2 changes | history) . . (+145) . . [Chgarcia (2×)] | |
14:08 (cur | prev) . . (+21) . . Chgarcia (Talk | contribs) | ||
N | 14:01 (cur | prev) . . (+124) . . Chgarcia (Talk | contribs) (Created page with "* [https://drive.google.com/file/d/1FpWgPuf9JgBxLSfFNQE8-ZHq7Sncs88N/view Gabriel Palacios-Serrano PhD Dissertation defense]") |
13:58 | CIS Conference and Workshop Proceedings (3 changes | history) . . (+219) . . [Chgarcia (3×)] | |
13:58 (cur | prev) . . (-2) . . Chgarcia (Talk | contribs) | ||
13:57 (cur | prev) . . (+2) . . Chgarcia (Talk | contribs) | ||
13:55 (cur | prev) . . (+219) . . Chgarcia (Talk | contribs) |
13:56 | (Upload log) . . Chgarcia (Talk | contribs) uploaded File:Hernandez-Garcia IEEE-abstract JLab approved and conference accepted.docx |
12:16 | CIS Library (diff | hist) . . (+12) . . Grames (Talk | contribs) |
08:50 | To-do list (3 changes | history) . . (+227) . . [Michaelm (3×)] | |
08:50 (cur | prev) . . (+163) . . Michaelm (Talk | contribs) | ||
08:45 (cur | prev) . . (+59) . . Michaelm (Talk | contribs) | ||
08:43 (cur | prev) . . (+5) . . Michaelm (Talk | contribs) |