UITF Fall 2022 Schedule

From Ciswikidb
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Week 9/26
  • MeV HCO continues...
  • COMTRA install jobs complete by Fri. 9/28
Week 10/3
  • keV beam in evenings (source, Mott, spin setups)
  • start SRF cool down mid-week weekend
  • MeV HCO/UITF complete by Fri. 10/6
  • Take a short hiatus to clear head, re-charge batteries Sat/Sun
  • ...or if someone has the oompf MeV HCO w/ beam begins
Week of 10/10
  • Begin COMTRA
  • ~3 days (6 shifts) for e-beam restore + x-ray setup + final align magnet/detector
  • ~4 days (8 shifts) for polarimeter checkout + AP measurement + experiment systematic studies
  • ... we go into weekend, try to wrap up...
Week of 10/17
  • End COMTRA as early in week as possible, say hard deadline by Tue or Wed...
  • ...then vac work for leak check and weekend for pump down
Week of 10/24
  • Start KICKER
  • ...10/26 represents 3 weeks of cold booster
Week of 10/31
  • End KICKER
  • ...11/2 represents 4 weeks of cold booster
  • ...SRF warm up
  • Everything ends latest 11/4