UITF Fall 2022 Schedule

From Ciswikidb
Jump to navigation Jump to search
Week 9/26
  • MeV HCO continues...
  • COMTRA install jobs complete by Fri. 9/28
Week 10/3
  • keV beam in evenings (source, Mott, spin setups)
  • start SRF cool down mid-week weekend
  • MeV HCO/UITF complete by Fri. 10/6
  • Take a short hiatus to clear head, re-charge batteries Sat/Sun
  • ...or if someone has the oompf MeV HCO w/ beam begins
Week of 10/10
  • Begin COMTRA
  • ~3 days (6 shifts) for e-beam restore + x-ray setup + final align magnet/detector
  • ~4 days (8 shifts) for polarimeter checkout + AP measurement + experiment systematic studies
  • ... we go into weekend, try to wrap up...
Week of 10/17
  • End COMTRA as early in week as possible, say hard deadline by Tue or Wed...
  • ...then vac work for leak check and weekend for pump down
Week of 10/24
  • Start KICKER
  • ...10/26 represents 3 weeks of cold booster
Week of 10/31
  • End KICKER
  • ...11/2 represents 4 weeks of cold booster
  • ...SRF warm up
  • Everything ends latest 11/4