UITF first beam on a viewer by December 22 2017


Prep chamber and Gun:

  • Loaded fresh bulk GaAs cathodes on puck 22 and 14, plus one strained GaAs in storage manipulator.
  • Both gun and prep chamber baked after replacing Cs channels and NF3 leak valve.
  • Gun high voltage conditioning in progress
  • Successfully activated a bulk GaAs photocathode link Details here

What else to make “simple” beam?


Updates on Epics control of:

  • Valves
  • Magnets
  • UED
  • Viewers
    • B. Freeman: "So from the viewer screen I put one button that will launch my application (adviewer) with the first viewer. Use the drop down menu in the left hand corner to scroll through camera feeds. This will not be the final configuration of the viewer screen. I plan to add some more options for viewer applications. I will also document all of the URLs for each camera feed. But this should be enough to see the viewers. I have verified that they all work and connected to the "correct" viewer."
  • Video to control room, DONE!
  • Current monitoring at cup, dump and apertures. Cables connected to ammeters
  • Gun HV control: DONE!
  • UHV ion pumps: DONE!
  • Decarad (in progress)
  • Water flow signal to fsd card
  • What else to fsd card? BLM
    • Need to make sure all isolated structures are properly grounded (50 ohm termination) if not to be used during first beam tests.
  • RF to seed laser
  • Attenuator
  • Power meter
  • x/y stage
  • tune mode generator
  • SCAM
  • Epics screens

What else later? By Feb 5, hopefully sooner

  • BPMs
  • RF to buncher
  • RF to choppers
  • Water skids functional
  • OSP for buncher and choppers

By February 5, 2018

  • All cryo work complete
  • All High Power RF work complete
  • OSP for QCM approved
  • ODH assessment, vent can on relief stack, penetrations filled, etc,

To do:

  • Get another shed electrode made, since we will need this electrode for the gun we pull from the tunnel
  • GN2 manifolds, clean polyflo
  • Tools, tool boxes
  • Vacuum cabinet, with vacuum hardware
  • Aluminum foil
  • Dress ion pump cables

R&D at UITF

  • mA polarized beam lifetime tests, lifetime vs laser spot size (continue Joe’s work)
  • Other lifetime studies: vs gun voltage, vs active area (3, 5, 7 mm), vs color of light, vs photocathode thickness and cleave plane, bulk vs superlattice
  • Lifetime vs oxidant (NF3, N2O, O2)
  • GaAs activated with Cs and Li: bi-alkali lifetime tests
  • Wein as precipitator
  • GaAs/GaAsP with and without DBR, GaAsSb/AlGaAs, and GaAsSb/AlGaAsP photocathode lifetime tests
  • Add an H-cleaner to the prep chamber
  • Brock cavity bunchlength measurements, vs buncher power, pump/probe test