(Created page with " [https://logbooks.jlab.org/entry/3521527 200keV Beam to both UITF dumps!] UITF Schedule - Zimbra calendar resource now functional. Add uitf-schedule to your zimbra calendar...")
 
Line 1: Line 1:
 +
------
  
 +
[https://logbooks.jlab.org/entry/3521527 200keV Beam to both UITF dumps!]
  
[https://logbooks.jlab.org/entry/3521527 200keV Beam to both UITF dumps!]
+
------
  
 
UITF Schedule - Zimbra calendar resource now functional. Add uitf-schedule to your zimbra calendar to see cae lock-up dates/times, etc.  
 
UITF Schedule - Zimbra calendar resource now functional. Add uitf-schedule to your zimbra calendar to see cae lock-up dates/times, etc.  

Revision as of 08:44, 29 January 2018


200keV Beam to both UITF dumps!


UITF Schedule - Zimbra calendar resource now functional. Add uitf-schedule to your zimbra calendar to see cae lock-up dates/times, etc.

Choppers are being conditioned by Mark and Larry. Thanks! When do you estimate to complete conditioning for 200 keV beam (75 Watts RF power on choppers).

Magnets:

Valves When will the two MDC valves have status read back?

FSD Performed software functionality test in UITF control room last week. What else is needed for full functionality?

BPMs Cables installed and terminated. Status on hardware, firmware, and EPICS software?

CRYO From last meeting: Cool down transfer line and 1/4 cryo-module to 80 K. Any updates? Estimate time to complete?

RF Update on RF for Quarter Cryo Module? Estimate time to complete?


Epics screens Working with T. Larrieu and team on SAVE/RESTORE.

Matt is working on OSP for buncher and choppers


By February 5, 2018:

All cryo work complete All High Power RF work complete OSP for QCM approved ODH assessment, vent can on relief stack, penetrations filled, etc,