Difference between revisions of "UITF Meeting - January 29, 2018"

From Ciswikidb
Jump to navigation Jump to search
Line 7: Line 7:
  
 
*Choppers are being conditioned by Mark and Larry. Thanks!  
 
*Choppers are being conditioned by Mark and Larry. Thanks!  
*When do you estimate to complete conditioning for 200 keV beam (75 Watts RF power on choppers).  
+
**When do you estimate to complete conditioning for 200 keV beam (75 Watts RF power on choppers).  
  
 
*Magnets:  
 
*Magnets:  
Line 28: Line 28:
 
**From last meeting: Cool down transfer line and 1/4 cryo-module to 80 K. Any updates?
 
**From last meeting: Cool down transfer line and 1/4 cryo-module to 80 K. Any updates?
 
**Estimate time to complete?
 
**Estimate time to complete?
 +
** Update: D. Bullard completed installation of guard vacuum relief vent outside the cave
  
 
*RF
 
*RF

Revision as of 09:20, 29 January 2018


200keV Beam to both UITF dumps!


UITF Schedule - Zimbra calendar resource now functional. Add uitf-schedule to your zimbra calendar to see cae lock-up dates/times, etc.


UPDATES

  • Choppers are being conditioned by Mark and Larry. Thanks!
    • When do you estimate to complete conditioning for 200 keV beam (75 Watts RF power on choppers).
  • Valves
    • When will the two MDC valves have status read back?
  • FSD
    • Performed software functionality test in UITF control room last week. What else is needed for full functionality?
  • BPMs
    • Cables installed and terminated.
    • Status on hardware, firmware, and EPICS software?
  • CRYO
    • From last meeting: Cool down transfer line and 1/4 cryo-module to 80 K. Any updates?
    • Estimate time to complete?
    • Update: D. Bullard completed installation of guard vacuum relief vent outside the cave
  • RF
    • Update on RF for Quarter Cryo Module?
    • Estimate time to complete?


Epics screens Working with T. Larrieu and team on SAVE/RESTORE.

Matt is working on OSP for buncher and choppers


By February 5, 2018:

All cryo work complete All High Power RF work complete OSP for QCM approved ODH assessment, vent can on relief stack, penetrations filled, etc,