Difference between revisions of "UITF Meeting - January 29, 2018"
Jump to navigation
Jump to search
Line 19: | Line 19: | ||
*FSD | *FSD | ||
− | **Performed software functionality test in UITF control room last week. What else is needed for full functionality? | + | **Performed software functionality test in UITF control room last week. |
+ | **What else is needed for full functionality? | ||
+ | |||
*BPMs | *BPMs | ||
**Cables installed and terminated. | **Cables installed and terminated. | ||
**Status on hardware, firmware, and EPICS software? | **Status on hardware, firmware, and EPICS software? | ||
+ | ** We need them operational and reading in EPICS before running beam in Tune Mode | ||
*CRYO | *CRYO | ||
− | **From last meeting: Cool down transfer line and 1/4 cryo-module to 80 K. | + | **From last meeting: Cool down transfer line and 1/4 cryo-module to 80 K. |
− | ** | + | **Estimated time to complete? |
** Update: D. Bullard completed installation of guard vacuum relief vent outside the cave | ** Update: D. Bullard completed installation of guard vacuum relief vent outside the cave | ||
+ | ** UPDATES: cryogenic connections? | ||
*RF | *RF | ||
**Update on RF for Quarter Cryo Module? | **Update on RF for Quarter Cryo Module? | ||
**Estimate time to complete? | **Estimate time to complete? | ||
+ | ** UPDATES: Klystron connections? | ||
Revision as of 09:23, 29 January 2018
200keV Beam to both UITF dumps!
UITF Schedule - Zimbra calendar resource now functional. Add uitf-schedule to your zimbra calendar to see cae lock-up dates/times, etc.
UPDATES
- Choppers are being conditioned by Mark and Larry. Thanks!
- When do you estimate to complete conditioning for 200 keV beam (75 Watts RF power on choppers).
- Magnets:
- Address PS rack ITF03 which prevents using four magnets presently
- Need to add one more corrector pair between the gun and the solenoid
- EPICS magnet screen is complete and functional with field maps provided by Joe
- Insulate and strain relieve the two FD chopper solenoids (they're off now, M. Beck is working on it)
- Valves
- When will the two MDC valves have status read back?
- FSD
- Performed software functionality test in UITF control room last week.
- What else is needed for full functionality?
- BPMs
- Cables installed and terminated.
- Status on hardware, firmware, and EPICS software?
- We need them operational and reading in EPICS before running beam in Tune Mode
- CRYO
- From last meeting: Cool down transfer line and 1/4 cryo-module to 80 K.
- Estimated time to complete?
- Update: D. Bullard completed installation of guard vacuum relief vent outside the cave
- UPDATES: cryogenic connections?
- RF
- Update on RF for Quarter Cryo Module?
- Estimate time to complete?
- UPDATES: Klystron connections?
Epics screens
Working with T. Larrieu and team on SAVE/RESTORE.
Matt is working on OSP for buncher and choppers
By February 5, 2018:
All cryo work complete All High Power RF work complete OSP for QCM approved ODH assessment, vent can on relief stack, penetrations filled, etc,