UITF Meeting - June 15, 2018
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Tasks before running beam to HDIce for target commissioning
- Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company)
- Suggest we use the Vacuum Group to build the MeV beamline (my group can help)
- Cryo: install the helium return line, or be content to vent the helium to the test lab
- SRF, need a point of contact for all things related to QCM operation, it's still confusing to me who to talk to
- Electrical engineering: design and build the PSS BCM, our "credited control" to limit beam current/loss and prevent accidental exposure to xrays
- Electrical engineering: stripline BPMs, get them to work (not the pA BPMs were were talking about today)
- Magnet group: give us a third trim card rack
- RF group: klystrons, high power amplifier, solid state amp, water skids
- SSG to incorporate high power RF interlocks into PSS, recertify
- Vashek: finish specifying the shielding requirements, then we start moving lead
- RCG to install all CARMs and electronics
- R&D related to low current BPMs, suggest Andy take this on, with help from Engineering
- Operations Group should augment Joe's modeling, using a particle tracking code
- Safety: OSP for buncher, OSP for MeV beam, PSS BCM credited control documentation, UITF Accelerator Operations Directive, Conduct of Operations, Accelerator Readiness review, lots of documents, lots of reviews
- Gun group needs to build a new photogun
- Need to operate the UITF on a daily basis.....
- Need access to liquid helium for weeks long periods of time (i.e., competition with LCLS)