Difference between revisions of "UITF Meeting - March 14, 2019"
Jump to navigation
Jump to search
(Created page with "Injector Test Cave Shielding Installation Schedule March 18-19: SRF moves cryomodule on east side of UITF Roof to west side of UITF Roof March 20: Load up Gravel Bags to so...") |
|||
Line 1: | Line 1: | ||
Injector Test Cave Shielding Installation Schedule | Injector Test Cave Shielding Installation Schedule | ||
− | March 18-19: SRF moves cryomodule on east side of UITF Roof to west side of UITF Roof | + | #March 18-19: SRF moves cryomodule on east side of UITF Roof to west side of UITF Roof |
− | March 20: Load up Gravel Bags to southeast corner UITF Roof, Move cap block on rubble pier north of ODH Vent to northeast corner UITF Roof. | + | #March 20: Load up Gravel Bags to southeast corner UITF Roof, Move cap block on rubble pier north of ODH Vent to northeast corner UITF Roof. |
− | March 18-22: Shoreline to Demo Rubble pier north of ODH Vent (after cap block removal). Remove wood ledger that interferes with SEG Block installation. Install concrete brick in 3” x 10” gap on north roof plank. Install gravel bags southeast corner UITF. | + | #March 18-22: Shoreline to Demo Rubble pier north of ODH Vent (after cap block removal). Remove wood ledger that interferes with SEG Block installation. Install concrete brick in 3” x 10” gap on north roof plank. Install gravel bags southeast corner UITF. |
− | March 22: SRF remove 2 cryomodules from UITF Roof. | + | #March 22: SRF remove 2 cryomodules from UITF Roof. |
− | March 25-26: Close off Test Lab northeast door. Physics sets first level SEG Blocks. | + | #March 25-26: Close off Test Lab northeast door. Physics sets first level SEG Blocks. |
− | March 25-26: Shoreline installs steel frame anchor bolts. | + | #March 25-26: Shoreline installs steel frame anchor bolts. |
− | March 27-29: Physics installs second and third level SEG Blocks. Water Line relocation by MRI. | + | #March 27-29: Physics installs second and third level SEG Blocks. Water Line relocation by MRI. |
− | April 1-5: Shoreline installs steel frame. Test Lab northeast door opened up when done. | + | #April 1-5: Shoreline installs steel frame. Test Lab northeast door opened up when done. |
− | April 8: Precast concrete is delivered and set in place. | + | #April 8: Precast concrete is delivered and set in place. |
− | April 9: Shoreline to anchor precast. | + | #April 9: Shoreline to anchor precast. |
− | April 10: Physics to place ODH Vent south pier cap block onto roof and relocate ODH Vent “T”roof beam to north end of UITF Roof. | + | #April 10: Physics to place ODH Vent south pier cap block onto roof and relocate ODH Vent “T”roof beam to north end of UITF Roof. |
− | April 11-12: SRF to move two cryomodules up to UITF Roof. | + | #April 11-12: SRF to move two cryomodules up to UITF Roof. |
− | April 15-16: Oneal Electric to restore power for welding receptacles and ground to ITC. | + | #April 15-16: Oneal Electric to restore power for welding receptacles and ground to ITC. |
− | April 17-18: Physics to place two cap blocks on piers north and south of ODH Vent. Place “T”roof beam over ODH Vent. | + | #April 17-18: Physics to place two cap blocks on piers north and south of ODH Vent. Place “T”roof beam over ODH Vent. |
− | April 19: Shoreline to place gravel bags north of ODH Vent north pier | + | #April 19: Shoreline to place gravel bags north of ODH Vent north pier |
Revision as of 10:39, 18 March 2019
Injector Test Cave Shielding Installation Schedule
- March 18-19: SRF moves cryomodule on east side of UITF Roof to west side of UITF Roof
- March 20: Load up Gravel Bags to southeast corner UITF Roof, Move cap block on rubble pier north of ODH Vent to northeast corner UITF Roof.
- March 18-22: Shoreline to Demo Rubble pier north of ODH Vent (after cap block removal). Remove wood ledger that interferes with SEG Block installation. Install concrete brick in 3” x 10” gap on north roof plank. Install gravel bags southeast corner UITF.
- March 22: SRF remove 2 cryomodules from UITF Roof.
- March 25-26: Close off Test Lab northeast door. Physics sets first level SEG Blocks.
- March 25-26: Shoreline installs steel frame anchor bolts.
- March 27-29: Physics installs second and third level SEG Blocks. Water Line relocation by MRI.
- April 1-5: Shoreline installs steel frame. Test Lab northeast door opened up when done.
- April 8: Precast concrete is delivered and set in place.
- April 9: Shoreline to anchor precast.
- April 10: Physics to place ODH Vent south pier cap block onto roof and relocate ODH Vent “T”roof beam to north end of UITF Roof.
- April 11-12: SRF to move two cryomodules up to UITF Roof.
- April 15-16: Oneal Electric to restore power for welding receptacles and ground to ITC.
- April 17-18: Physics to place two cap blocks on piers north and south of ODH Vent. Place “T”roof beam over ODH Vent.
- April 19: Shoreline to place gravel bags north of ODH Vent north pier