UITF Meeting - March 14, 2019

From Ciswikidb
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Injector Test Cave Shielding Installation Schedule (draft)

  1. March 18-19: SRF moves cryomodule on east side of UITF Roof to west side of UITF Roof
  2. March 20: Load up Gravel Bags to southeast corner UITF Roof, Move cap block on rubble pier north of ODH Vent to northeast corner UITF Roof.
  3. March 18-22: Shoreline to Demo Rubble pier north of ODH Vent (after cap block removal). Remove wood ledger that interferes with SEG Block installation. Install concrete brick in 3” x 10” gap on north roof plank. Install gravel bags southeast corner UITF.
  4. March 22: SRF remove 2 cryomodules from UITF Roof.
  5. March 25-26: Close off Test Lab northeast door. Physics sets first level SEG Blocks.
  6. March 25-26: Shoreline installs steel frame anchor bolts.
  7. March 27-29: Physics installs second and third level SEG Blocks. Water Line relocation by MRI.
  8. April 1-5: Shoreline installs steel frame. Test Lab northeast door opened up when done.
  9. April 8: Precast concrete is delivered and set in place.
  10. April 9: Shoreline to anchor precast.
  11. April 10: Physics to place ODH Vent south pier cap block onto roof and relocate ODH Vent “T”roof beam to north end of UITF Roof.
  12. April 11-12: SRF to move two cryomodules up to UITF Roof.
  13. April 15-16: Oneal Electric to restore power for welding receptacles and ground to ITC.
  14. April 17-18: Physics to place two cap blocks on piers north and south of ODH Vent. Place “T”roof beam over ODH Vent.
  15. April 19: Shoreline to place gravel bags north of ODH Vent north pier