Line 25: | Line 25: | ||
* Somebody to provide a means to leave the north side of the roof | * Somebody to provide a means to leave the north side of the roof | ||
=Inside the caves, waist height= | =Inside the caves, waist height= | ||
− | + | * Clean up and organize inside the caves, vacuum on order | |
− | + | * Attach magnets, cable up, software screens | |
− | + | * Viewers, air and video | |
− | + | * Cup and dumps: water and current monitoring, protection diodes, screens | |
− | + | * Lead brick around dumps | |
− | + | * Lead brick in trenches, document and post | |
− | + | * Move laser table to GTS | |
− | + | * Harps, need them to work (harp screens, where are they) | |
− | + | * SF6 resistor tank | |
− | + | * 11 L/s ion pump added to the dead chopper chamber pump | |
− | + | * Gun at 200kV w/o field emission (vent gun to remove electrode ~ August 10) | |
− | + | * Activate a photocathode | |
− | + | * Gabriel data | |
− | + | * Lifetime with cesium | |
− | + | * Lifetime with cesium and lithium | |
− | + | * Beam through Brock cavity polarimeter | |
− | + | * Characterize the buncher using the Brock cavity bunchlength monitor | |
− | + | * Get another Brock bunch length cavity and install it at dump | |
− | + | * Buy another scope and fast plugin | |
− | + | * Ion pumps ON and attached to UHV supplies, with epics screens | |
− | + | * Once harps are installed and Brock bunchlength cavity #2, light bake of beamline to obtain 100nA pressure? | |
− | + | * Does anyone have a plot of ion pump response versus beam loss? | |
− | + | * Curt Yao cavity electronics | |
− | + | * Epics control of valves | |
− | + | * Waiting for the “good” valve chassis that lets me segment MPS into three zones | |
− | + | * Implement three-zone MPS with Marie Kissee | |
− | + | * Official lock on QCM upstream valve? | |
− | + | * Are we prepared to have epics control of QCM valves? | |
=Elevated Beamline= | =Elevated Beamline= | ||
− | + | * Re-arrange the components near HDIce (Phil, Marcy, Shaun, matt) | |
− | + | * Waiting for stepper stages, machine shop apertures | |
− | + | * Build the apertures and align them (need stepper motor controller, John help us!) | |
− | + | * BPMs in place, connected to receivers | |
− | + | * Pump down, leak check | |
− | + | * FEL style viewers working, modifications necessary? Cameras, video, air pressure | |
− | + | * Valves | |
− | + | * Ion pumps | |
− | + | * Decarad near the apertures | |
− | + | * Steering magnets from LERF | |
− | + | * Cup: water and current monitoring, protection diode, added to screens | |
=OSPs:= | =OSPs:= | ||
− | Tile removal | + | * Tile removal |
− | Commissioning plan/MeV OSP | + | * Commissioning plan/MeV OSP |
Revision as of 08:32, 20 May 2019
UITF to do list_for ARR
- ) Binder in control room that lists qualified Operators
- ) Describe training
- ) Minimum staffing requirements
- ) Pre-Ops checklist, RadCon checklist?
- ) How to notify in broad sense whether UITF is a “gun test stand” or “accelerator”?
- ) Professional way to lock out the valve to QCM, the dipole to elevated beamline
- ) Modifications UOD: a) specify that for keV ops, rad survey is not required. B) Break the page for staffing table
UITF to-do list
Top of Cave1 and 2:
- Move wooden boxes somewhere
- Bolt down the channel for magnet rack#3
- Crane up the magnet rack
- Vacuum the top
- Tell crews to take their un-used stuff way (cables and tools, etc)
- Pick a time and ask Neil to reconfigure the helium vent barrier
- When the helium vent barrier is removed, HDIce to reconfigure their vent pipes
- Neil to add fall protection at the removable tile locations
- Neil to provide support posts for horizontal lifeline
- Andy to purchase more moveable yellow railings
- Somebody to provide a means to leave the north side of the roof
Inside the caves, waist height
- Clean up and organize inside the caves, vacuum on order
- Attach magnets, cable up, software screens
- Viewers, air and video
- Cup and dumps: water and current monitoring, protection diodes, screens
- Lead brick around dumps
- Lead brick in trenches, document and post
- Move laser table to GTS
- Harps, need them to work (harp screens, where are they)
- SF6 resistor tank
- 11 L/s ion pump added to the dead chopper chamber pump
- Gun at 200kV w/o field emission (vent gun to remove electrode ~ August 10)
- Activate a photocathode
- Gabriel data
- Lifetime with cesium
- Lifetime with cesium and lithium
- Beam through Brock cavity polarimeter
- Characterize the buncher using the Brock cavity bunchlength monitor
- Get another Brock bunch length cavity and install it at dump
- Buy another scope and fast plugin
- Ion pumps ON and attached to UHV supplies, with epics screens
- Once harps are installed and Brock bunchlength cavity #2, light bake of beamline to obtain 100nA pressure?
- Does anyone have a plot of ion pump response versus beam loss?
- Curt Yao cavity electronics
- Epics control of valves
- Waiting for the “good” valve chassis that lets me segment MPS into three zones
- Implement three-zone MPS with Marie Kissee
- Official lock on QCM upstream valve?
- Are we prepared to have epics control of QCM valves?
Elevated Beamline
- Re-arrange the components near HDIce (Phil, Marcy, Shaun, matt)
- Waiting for stepper stages, machine shop apertures
- Build the apertures and align them (need stepper motor controller, John help us!)
- BPMs in place, connected to receivers
- Pump down, leak check
- FEL style viewers working, modifications necessary? Cameras, video, air pressure
- Valves
- Ion pumps
- Decarad near the apertures
- Steering magnets from LERF
- Cup: water and current monitoring, protection diode, added to screens
OSPs:
- Tile removal
- Commissioning plan/MeV OSP