=UITF to do list_for ARR=
 
=UITF to do list_for ARR=
  
1) Binder in control room that lists qualified Operators
+
#) Binder in control room that lists qualified Operators
2) Describe training
+
#) Describe training
3) Minimum staffing requirements
+
#) Minimum staffing requirements
4) Pre-Ops checklist, RadCon checklist?
+
#) Pre-Ops checklist, RadCon checklist?
5) How to notify in broad sense whether UITF is a “gun test stand” or “accelerator”?   
+
#) How to notify in broad sense whether UITF is a “gun test stand” or “accelerator”?   
6) Professional way to lock out the valve to QCM, the dipole to elevated beamline
+
#) Professional way to lock out the valve to QCM, the dipole to elevated beamline
7) Modifications UOD: a) specify that for keV ops, rad survey is not required. B) Break the page for staffing table
+
#) Modifications UOD: a) specify that for keV ops, rad survey is not required. B) Break the page for staffing table
  
  
Line 13: Line 13:
  
 
=Top of Cave1 and 2:=
 
=Top of Cave1 and 2:=
Move wooden boxes somewhere
+
* Move wooden boxes somewhere
Bolt down the channel for magnet rack#3
+
* Bolt down the channel for magnet rack#3
Crane up the magnet rack
+
* Crane up the magnet rack
Vacuum the top
+
* Vacuum the top
Tell crews to take their un-used stuff way (cables and tools, etc)
+
* Tell crews to take their un-used stuff way (cables and tools, etc)
Pick a time and ask Neil to reconfigure the helium vent barrier
+
* Pick a time and ask Neil to reconfigure the helium vent barrier
When the helium vent barrier is removed, HDIce to reconfigure their vent pipes
+
* When the helium vent barrier is removed, HDIce to reconfigure their vent pipes
Neil to add fall protection at the removable tile locations
+
* Neil to add fall protection at the removable tile locations
Neil to provide support posts for horizontal lifeline
+
* Neil to provide support posts for horizontal lifeline
Andy to purchase more moveable yellow railings
+
* Andy to purchase more moveable yellow railings
Somebody to provide a means to leave the north side of the roof
+
* Somebody to provide a means to leave the north side of the roof
 
=Inside the caves, waist height=
 
=Inside the caves, waist height=
Clean up and organize inside the caves, vacuum on order
+
* Clean up and organize inside the caves, vacuum on order
Attach magnets, cable up, software screens
+
* Attach magnets, cable up, software screens
Viewers, air and video
+
* Viewers, air and video
Cup and dumps: water and current monitoring, protection diodes, screens
+
* Cup and dumps: water and current monitoring, protection diodes, screens
Lead brick around dumps
+
* Lead brick around dumps
Lead brick in trenches, document and post
+
* Lead brick in trenches, document and post
Move laser table to GTS
+
* Move laser table to GTS
Harps, need them to work (harp screens, where are they)
+
* Harps, need them to work (harp screens, where are they?)
SF6 resistor tank
+
* SF6 resistor tank
11 L/s ion pump added to the dead chopper chamber pump
+
* 11 L/s ion pump added to the dead chopper chamber pump
Gun at 200kV w/o field emission
+
* Gun at 200kV w/o field emission (vent gun to remove electrode ~ August 10)
Activate a photocathode
+
* Activate a photocathode
Gabriel data
+
* Gabriel data
Lifetime with cesium
+
* Lifetime with cesium
Lifetime with cesium and lithium
+
* Lifetime with cesium and lithium
Beam through Brock cavity polarimeter
+
* Beam through Brock cavity polarimeter
Characterize the buncher using the Brock cavity bunchlength monitor
+
* Characterize the buncher using the Brock cavity bunchlength monitor
Get another Brock bunch length cavity and install it at dump
+
* Get another Brock bunch length cavity and install it at dump
Buy another scope and fast plugin
+
* Buy another scope and fast plugin (11801C or CSA803? or something newer?)
Ion pumps ON and attached to UHV supplies, with epics screens
+
* Ion pumps ON and attached to UHV supplies, with epics screens
Once harps are installed and Brock bunchlength cavity #2, light bake of beamline to obtain 100nA pressure?
+
* Once harps are installed and Brock bunchlength cavity #2, light bake of beamline to obtain 100nA pressure?
Does anyone have a plot of ion pump response versus beam loss?   
+
* Does anyone have a plot of ion pump response versus beam loss?   
Curt Yao cavity electronics
+
* Curt: Yao cavity electronics
Epics control of valves
+
* Epics control of valves
Waiting for the “good” valve chassis that lets me segment MPS into three zones
+
* Waiting for the “good” valve chassis that lets me segment MPS into three zones
Implement three-zone MPS with Marie Kissee
+
* Implement three-zone MPS with Marie Kissee
Official lock on QCM upstream valve?
+
* Official lock on QCM upstream valve?
Are we prepared to have epics control of QCM valves?
+
* Are we prepared to have epics control of QCM valves?
  
 
=Elevated Beamline=
 
=Elevated Beamline=
Re-arrange the components near HDIce (Phil, Marcy, Shaun, matt)
+
* Re-arrange the components near HDIce (Phil, Marcy, Shaun, matt)
Waiting for stepper stages, machine shop apertures
+
* Waiting for stepper stages, machine shop apertures
Build the apertures and align them (need stepper motor controller, John help us!)
+
* Build the apertures and align them (need stepper motor controller, John help us!)
BPMs in place, connected to receivers
+
* BPMs in place, connected to receivers
Pump down, leak check
+
* Pump down, leak check
FEL style viewers working, modifications necessary? Cameras, video, air pressure
+
* FEL style viewers working, modifications necessary? Cameras, video, air pressure
Valves
+
* Valves
Ion pumps
+
* Ion pumps
Decarad near the apertures
+
* Decarad near the apertures
Steering magnets from LERF
+
* Steering magnets from LERF
Cup: water and current monitoring, protection diode, added to screens
+
* Cup: water and current monitoring, protection diode, added to screens
  
  
 
=OSPs:=
 
=OSPs:=
Tile removal  
+
*      Tile removal  
Commissioning plan/MeV OSP
+
*      Commissioning plan/MeV OSP

Latest revision as of 08:37, 20 May 2019

UITF to do list_for ARR

  1. ) Binder in control room that lists qualified Operators
  2. ) Describe training
  3. ) Minimum staffing requirements
  4. ) Pre-Ops checklist, RadCon checklist?
  5. ) How to notify in broad sense whether UITF is a “gun test stand” or “accelerator”?
  6. ) Professional way to lock out the valve to QCM, the dipole to elevated beamline
  7. ) Modifications UOD: a) specify that for keV ops, rad survey is not required. B) Break the page for staffing table


UITF to-do list

Top of Cave1 and 2:

  • Move wooden boxes somewhere
  • Bolt down the channel for magnet rack#3
  • Crane up the magnet rack
  • Vacuum the top
  • Tell crews to take their un-used stuff way (cables and tools, etc)
  • Pick a time and ask Neil to reconfigure the helium vent barrier
  • When the helium vent barrier is removed, HDIce to reconfigure their vent pipes
  • Neil to add fall protection at the removable tile locations
  • Neil to provide support posts for horizontal lifeline
  • Andy to purchase more moveable yellow railings
  • Somebody to provide a means to leave the north side of the roof

Inside the caves, waist height

  • Clean up and organize inside the caves, vacuum on order
  • Attach magnets, cable up, software screens
  • Viewers, air and video
  • Cup and dumps: water and current monitoring, protection diodes, screens
  • Lead brick around dumps
  • Lead brick in trenches, document and post
  • Move laser table to GTS
  • Harps, need them to work (harp screens, where are they?)
  • SF6 resistor tank
  • 11 L/s ion pump added to the dead chopper chamber pump
  • Gun at 200kV w/o field emission (vent gun to remove electrode ~ August 10)
  • Activate a photocathode
  • Gabriel data
  • Lifetime with cesium
  • Lifetime with cesium and lithium
  • Beam through Brock cavity polarimeter
  • Characterize the buncher using the Brock cavity bunchlength monitor
  • Get another Brock bunch length cavity and install it at dump
  • Buy another scope and fast plugin (11801C or CSA803? or something newer?)
  • Ion pumps ON and attached to UHV supplies, with epics screens
  • Once harps are installed and Brock bunchlength cavity #2, light bake of beamline to obtain 100nA pressure?
  • Does anyone have a plot of ion pump response versus beam loss?
  • Curt: Yao cavity electronics
  • Epics control of valves
  • Waiting for the “good” valve chassis that lets me segment MPS into three zones
  • Implement three-zone MPS with Marie Kissee
  • Official lock on QCM upstream valve?
  • Are we prepared to have epics control of QCM valves?

Elevated Beamline

  • Re-arrange the components near HDIce (Phil, Marcy, Shaun, matt)
  • Waiting for stepper stages, machine shop apertures
  • Build the apertures and align them (need stepper motor controller, John help us!)
  • BPMs in place, connected to receivers
  • Pump down, leak check
  • FEL style viewers working, modifications necessary? Cameras, video, air pressure
  • Valves
  • Ion pumps
  • Decarad near the apertures
  • Steering magnets from LERF
  • Cup: water and current monitoring, protection diode, added to screens


OSPs:

  • Tile removal
  • Commissioning plan/MeV OSP