UITF Meeting - May 20, 2019

From Ciswikidb
Revision as of 08:27, 20 May 2019 by Poelker (talk | contribs) (Created page with "=UITF to do list_for ARR= 1) Binder in control room that lists qualified Operators 2) Describe training 3) Minimum staffing requirements 4) Pre-Ops checklist, RadCon checklis...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

UITF to do list_for ARR

1) Binder in control room that lists qualified Operators 2) Describe training 3) Minimum staffing requirements 4) Pre-Ops checklist, RadCon checklist? 5) How to notify in broad sense whether UITF is a “gun test stand” or “accelerator”? 6) Professional way to lock out the valve to QCM, the dipole to elevated beamline 7) Modifications UOD: a) specify that for keV ops, rad survey is not required. B) Break the page for staffing table


UITF to-do list

Top of Cave1 and 2:

• Move wooden boxes somewhere • Bolt down the channel for magnet rack#3 • Crane up the magnet rack • Vacuum the top • Tell crews to take their un-used stuff way (cables and tools, etc) • Pick a time and ask Neil to reconfigure the helium vent barrier • When the helium vent barrier is removed, HDIce to reconfigure their vent pipes • Neil to add fall protection at the removable tile locations • Neil to provide support posts for horizontal lifeline • Andy to purchase more moveable yellow railings • Somebody to provide a means to leave the north side of the roof

Inside the caves, waist height

• Clean up and organize inside the caves, vacuum on order • Attach magnets, cable up, software screens • Viewers, air and video • Cup and dumps: water and current monitoring, protection diodes, screens • Lead brick around dumps • Lead brick in trenches, document and post • Move laser table to GTS • Harps, need them to work (harp screens, where are they) • SF6 resistor tank • 11 L/s ion pump added to the dead chopper chamber pump • Gun at 200kV w/o field emission • Activate a photocathode • Gabriel data • Lifetime with cesium • Lifetime with cesium and lithium • Beam through Brock cavity polarimeter • Characterize the buncher using the Brock cavity bunchlength monitor • Get another Brock bunch length cavity and install it at dump • Buy another scope and fast plugin • Ion pumps ON and attached to UHV supplies, with epics screens • Once harps are installed and Brock bunchlength cavity #2, light bake of beamline to obtain 100nA pressure? • Does anyone have a plot of ion pump response versus beam loss? • Curt Yao cavity electronics • Epics control of valves • Waiting for the “good” valve chassis that lets me segment MPS into three zones • Implement three-zone MPS with Marie Kissee • Official lock on QCM upstream valve? • Are we prepared to have epics control of QCM valves?

Elevated Beamline

• Re-arrange the components near HDIce (Phil, Marcy, Shaun, matt) • Waiting for stepper stages, machine shop apertures • Build the apertures and align them (need stepper motor controller, John help us!) • BPMs in place, connected to receivers • Pump down, leak check • FEL style viewers working, modifications necessary? Cameras, video, air pressure • Valves • Ion pumps • Decarad near the apertures • Steering magnets from LERF • Cup: water and current monitoring, protection diode, added to screens


OSPs:

Tile removal Commissioning plan/MeV OSP