(Created page with "05 March 2020 UITF/HD-Ice Meeting: • Poelker, Ginsburg, Reilly, Lung, Rossi, Preble, May, Sandorfi, Smith Schedule for CTF Demand: • Draft Schedule based on estimated re...")
 
 
(5 intermediate revisions by the same user not shown)
Line 5: Line 5:
 
Schedule for CTF Demand:  
 
Schedule for CTF Demand:  
 
• Draft Schedule based on estimated readiness for CTF of LCLS-II CM in June and C75 in August
 
• Draft Schedule based on estimated readiness for CTF of LCLS-II CM in June and C75 in August
Customer Start Date End Date
+
 
UITF Run #0 Commissioning Mar 30 Apr 17
+
[[File:HDIce test schedule.jpg|thumb|left|1500px]]
UITF/HD-Ice Run #1 Commissioning May 7 May 22
 
UITF/HD-Ice ~1 week changeover May 23 May 29
 
UITF/HD-Ice Run #2 Unpolarized Target May 30 June 15
 
LCLS-II CM June 16 July 5
 
UITF/HD-Ice Run #3 Polarized Target July 6 Aug 2
 
float Aug 3 Aug 20
 
CEBAF C75 Aug 21 tbd
 
  
 
NOTES
 
NOTES
Everything ready for UITF Run 0 commissioning
+
*Everything ready for UITF Run 0 commissioning
Prior to UITF/HD-Ice Run 1:
+
*Prior to UITF/HD-Ice Run 1:
o CATS items to be closed (Poelker/Ginsburg/Seryi/Smith)
+
**CATS items to be closed (Poelker/Ginsburg/Seryi/Smith)
o ERR Recommendations to be closed (Sandorfi/Rossi)
+
**ERR Recommendations to be closed (Sandorfi/Rossi)
o Permission to operate from TJSO (Poelker/Ginsburg/Seryi/May)
+
**Permission to operate from TJSO (Poelker/Ginsburg/Seryi/May)
Progress on repair of the current LCLS-II cryomodule will determine whether it can be ready by June 16 for CTF.  Any delay will require re-visiting the schedule for UITF/HD-Ice Run #3
+
*Progress on repair of the current LCLS-II cryomodule will determine whether it can be ready by June 16 for CTF.  Any delay will require re-visiting the schedule for UITF/HD-Ice Run #3
Updates to be presented at the Planning & Coordination meeting on March 17
+
*Updates to be presented at the Planning & Coordination meeting on March 17
Re-convene this group for a status meeting in ~one month
+
*Re-convene this group for a status meeting in ~one month

Latest revision as of 14:27, 8 March 2020

05 March 2020 UITF/HD-Ice Meeting: • Poelker, Ginsburg, Reilly, Lung, Rossi, Preble, May, Sandorfi, Smith

Schedule for CTF Demand: • Draft Schedule based on estimated readiness for CTF of LCLS-II CM in June and C75 in August

HDIce test schedule.jpg

NOTES

  • Everything ready for UITF Run 0 commissioning
  • Prior to UITF/HD-Ice Run 1:
    • CATS items to be closed (Poelker/Ginsburg/Seryi/Smith)
    • ERR Recommendations to be closed (Sandorfi/Rossi)
    • Permission to operate from TJSO (Poelker/Ginsburg/Seryi/May)
  • Progress on repair of the current LCLS-II cryomodule will determine whether it can be ready by June 16 for CTF. Any delay will require re-visiting the schedule for UITF/HD-Ice Run #3
  • Updates to be presented at the Planning & Coordination meeting on March 17
  • Re-convene this group for a status meeting in ~one month