Difference between revisions of "UITF Meeting with Allison and others to discuss schedule HDIce tests 3 5 2020"

From Ciswikidb
Jump to navigation Jump to search
 
(2 intermediate revisions by the same user not shown)
Line 11: Line 11:
 
*Everything ready for UITF Run 0 commissioning
 
*Everything ready for UITF Run 0 commissioning
 
*Prior to UITF/HD-Ice Run 1:
 
*Prior to UITF/HD-Ice Run 1:
*CATS items to be closed (Poelker/Ginsburg/Seryi/Smith)
+
**CATS items to be closed (Poelker/Ginsburg/Seryi/Smith)
*ERR Recommendations to be closed (Sandorfi/Rossi)
+
**ERR Recommendations to be closed (Sandorfi/Rossi)
*Permission to operate from TJSO (Poelker/Ginsburg/Seryi/May)
+
**Permission to operate from TJSO (Poelker/Ginsburg/Seryi/May)
 
*Progress on repair of the current LCLS-II cryomodule will determine whether it can be ready by June 16 for CTF.  Any delay will require re-visiting the schedule for UITF/HD-Ice Run #3
 
*Progress on repair of the current LCLS-II cryomodule will determine whether it can be ready by June 16 for CTF.  Any delay will require re-visiting the schedule for UITF/HD-Ice Run #3
 
*Updates to be presented at the Planning & Coordination meeting on March 17
 
*Updates to be presented at the Planning & Coordination meeting on March 17
 
*Re-convene this group for a status meeting in ~one month
 
*Re-convene this group for a status meeting in ~one month

Latest revision as of 14:27, 8 March 2020

05 March 2020 UITF/HD-Ice Meeting: • Poelker, Ginsburg, Reilly, Lung, Rossi, Preble, May, Sandorfi, Smith

Schedule for CTF Demand: • Draft Schedule based on estimated readiness for CTF of LCLS-II CM in June and C75 in August

HDIce test schedule.jpg

NOTES

  • Everything ready for UITF Run 0 commissioning
  • Prior to UITF/HD-Ice Run 1:
    • CATS items to be closed (Poelker/Ginsburg/Seryi/Smith)
    • ERR Recommendations to be closed (Sandorfi/Rossi)
    • Permission to operate from TJSO (Poelker/Ginsburg/Seryi/May)
  • Progress on repair of the current LCLS-II cryomodule will determine whether it can be ready by June 16 for CTF. Any delay will require re-visiting the schedule for UITF/HD-Ice Run #3
  • Updates to be presented at the Planning & Coordination meeting on March 17
  • Re-convene this group for a status meeting in ~one month