Difference between revisions of "UITF Meeting with Allison and others to discuss schedule HDIce tests 3 5 2020"
Jump to navigation
Jump to search
Line 6: | Line 6: | ||
• Draft Schedule based on estimated readiness for CTF of LCLS-II CM in June and C75 in August | • Draft Schedule based on estimated readiness for CTF of LCLS-II CM in June and C75 in August | ||
− | [[File:HDIce test schedule.jpg|thumb|left| | + | [[File:HDIce test schedule.jpg|thumb|left|1000px]] |
NOTES | NOTES | ||
− | + | *Everything ready for UITF Run 0 commissioning | |
− | + | *Prior to UITF/HD-Ice Run 1: | |
− | + | *CATS items to be closed (Poelker/Ginsburg/Seryi/Smith) | |
− | + | *ERR Recommendations to be closed (Sandorfi/Rossi) | |
− | + | *Permission to operate from TJSO (Poelker/Ginsburg/Seryi/May) | |
− | + | *Progress on repair of the current LCLS-II cryomodule will determine whether it can be ready by June 16 for CTF. Any delay will require re-visiting the schedule for UITF/HD-Ice Run #3 | |
− | + | *Updates to be presented at the Planning & Coordination meeting on March 17 | |
− | + | *Re-convene this group for a status meeting in ~one month |
Revision as of 14:22, 8 March 2020
05 March 2020 UITF/HD-Ice Meeting: • Poelker, Ginsburg, Reilly, Lung, Rossi, Preble, May, Sandorfi, Smith
Schedule for CTF Demand: • Draft Schedule based on estimated readiness for CTF of LCLS-II CM in June and C75 in August
NOTES
- Everything ready for UITF Run 0 commissioning
- Prior to UITF/HD-Ice Run 1:
- CATS items to be closed (Poelker/Ginsburg/Seryi/Smith)
- ERR Recommendations to be closed (Sandorfi/Rossi)
- Permission to operate from TJSO (Poelker/Ginsburg/Seryi/May)
- Progress on repair of the current LCLS-II cryomodule will determine whether it can be ready by June 16 for CTF. Any delay will require re-visiting the schedule for UITF/HD-Ice Run #3
- Updates to be presented at the Planning & Coordination meeting on March 17
- Re-convene this group for a status meeting in ~one month