• Draft Schedule based on estimated readiness for CTF of LCLS-II CM in June and C75 in August
 
• Draft Schedule based on estimated readiness for CTF of LCLS-II CM in June and C75 in August
  
[[File:HDIce test schedule.jpg|thumb|left|100px]]
+
[[File:HDIce test schedule.jpg|thumb|left|1000px]]
  
 
NOTES
 
NOTES
Everything ready for UITF Run 0 commissioning
+
*Everything ready for UITF Run 0 commissioning
Prior to UITF/HD-Ice Run 1:
+
*Prior to UITF/HD-Ice Run 1:
o CATS items to be closed (Poelker/Ginsburg/Seryi/Smith)
+
*CATS items to be closed (Poelker/Ginsburg/Seryi/Smith)
o ERR Recommendations to be closed (Sandorfi/Rossi)
+
*ERR Recommendations to be closed (Sandorfi/Rossi)
o Permission to operate from TJSO (Poelker/Ginsburg/Seryi/May)
+
*Permission to operate from TJSO (Poelker/Ginsburg/Seryi/May)
Progress on repair of the current LCLS-II cryomodule will determine whether it can be ready by June 16 for CTF.  Any delay will require re-visiting the schedule for UITF/HD-Ice Run #3
+
*Progress on repair of the current LCLS-II cryomodule will determine whether it can be ready by June 16 for CTF.  Any delay will require re-visiting the schedule for UITF/HD-Ice Run #3
Updates to be presented at the Planning & Coordination meeting on March 17
+
*Updates to be presented at the Planning & Coordination meeting on March 17
Re-convene this group for a status meeting in ~one month
+
*Re-convene this group for a status meeting in ~one month

Revision as of 14:22, 8 March 2020

05 March 2020 UITF/HD-Ice Meeting: • Poelker, Ginsburg, Reilly, Lung, Rossi, Preble, May, Sandorfi, Smith

Schedule for CTF Demand: • Draft Schedule based on estimated readiness for CTF of LCLS-II CM in June and C75 in August

HDIce test schedule.jpg

NOTES

  • Everything ready for UITF Run 0 commissioning
  • Prior to UITF/HD-Ice Run 1:
  • CATS items to be closed (Poelker/Ginsburg/Seryi/Smith)
  • ERR Recommendations to be closed (Sandorfi/Rossi)
  • Permission to operate from TJSO (Poelker/Ginsburg/Seryi/May)
  • Progress on repair of the current LCLS-II cryomodule will determine whether it can be ready by June 16 for CTF. Any delay will require re-visiting the schedule for UITF/HD-Ice Run #3
  • Updates to be presented at the Planning & Coordination meeting on March 17
  • Re-convene this group for a status meeting in ~one month