UITF Meeting with Allison and others to discuss schedule HDIce tests 3 5 2020

From Ciswikidb
Revision as of 14:27, 8 March 2020 by Poelker (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

05 March 2020 UITF/HD-Ice Meeting: • Poelker, Ginsburg, Reilly, Lung, Rossi, Preble, May, Sandorfi, Smith

Schedule for CTF Demand: • Draft Schedule based on estimated readiness for CTF of LCLS-II CM in June and C75 in August

HDIce test schedule.jpg

NOTES

  • Everything ready for UITF Run 0 commissioning
  • Prior to UITF/HD-Ice Run 1:
    • CATS items to be closed (Poelker/Ginsburg/Seryi/Smith)
    • ERR Recommendations to be closed (Sandorfi/Rossi)
    • Permission to operate from TJSO (Poelker/Ginsburg/Seryi/May)
  • Progress on repair of the current LCLS-II cryomodule will determine whether it can be ready by June 16 for CTF. Any delay will require re-visiting the schedule for UITF/HD-Ice Run #3
  • Updates to be presented at the Planning & Coordination meeting on March 17
  • Re-convene this group for a status meeting in ~one month