User talk:Mstefani
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
GTS meeting 11/25/19
Safety:
- PSS: Certified
- GTS OSP: Signed
- Tgun OPS: Signed
Remaining Tasks:
- Fix viewers
- Connect first two corrector magnets
- Install PCB for remote bias control with John Musson
Timeline:
- Monday 25th- connect/test Magnets
- Tuesday 25th- install/test PCB
- Wednesday 27th- final checks on hot deck components
- 28th-1st- Long Thanksgiving weekend
- Monday 2nd- create first beam using radiation and vacuum as indicators