GTS meeting 11/25/19

Safety:

  • PSS: Certified
  • GTS OSP: Signed
  • Tgun OPS: Signed

Remaining Tasks:

  • Fix viewers
  • Connect first two corrector magnets
  • Install PCB for remote bias control with John Musson

Timeline:

  • Monday 25th- connect/test Magnets
  • Tuesday 25th- install/test PCB
  • Wednesday 27th- final checks on hot deck components
  • 28th-1st- Long Thanksgiving weekend
  • Monday 2nd- create first beam using radiation and vacuum as indicators