Vacuum chamber

From Ciswikidb
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Done

  • Remove WP-1250 NEG cartridges
  • Remove posts for woven metal screen and replace with something suitable for high vacuum
  • Add (tack weld?) fixtures to the vacuum chamber for S&A tooling
  • Send vacuum chamber to S&A for fiducial (locate top flange, and anode flange with repost to chamber z-axis.
  • Clean vacuum chamber (wipe off with iso-propanol, removed foreign objects, etc)
  • Consider replacing the WP-1250 NEG cartridges with modern UHV 1400 NEG wafer modules (~12 week delivery)
    • If using UHV 1400 NEG wafer modules, no screen is necessary
    • Marcy to calculate how many UHV 1400 NEG wafer modules are needed, based on this, we'll develop a scheme to mount them. No need for a shield screen if e go with this modern NEG wafer modules. Need to figure out how to win them inside the vacuum chamber, and likely built a new power supply.
  • If the old WP-1250 modules stay:
    • Bubba to finish new woven metal screen
    • Devise a better method to hold the screen in place
    • Devise a reliable method to prevent electrical short in the NEG cartridges electrical connections for full activation with current
  • Re-install extractor gauge


vacuum qualification of chamber

  • Gun chamber cleaned, blown down with ionized nitrogen
  • UHV1400 pumps installed and connected to feedthrough
  • First bake: 48 hours at 250C. No NEG activation. Leak in extractor gauge opened on ramp down
  • Second bake: 24 hours at 250C after vent for extractor swap. P vs. T data taken for ~2 weeks
  • Third bake: 48 hours at 250C, NEG activated for 1 hour at 500C while chamber at 200C. Vacuum tests underway 31march2022


Steps for completion

  • Finish vacuum qualification (~April 15)
  • Fabricate and install shield screen
    • Finalize design (April 8)
    • Order parts: standoffs, more screen, shimstock strips? (April 8)
    • clean and heat treat materials (April 18 or 25)
    • install screen (April 25 or May 2)
  • Send gun assembly to clean room for inversion, nitrogen blow-down. week of May 2?
  • Install spider and anode, align
  • Install electrode, align


Back to 18" Photogun page