Wednesday February 18, 2015
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
We will meet in TL 2221 on Wednesday February 18 at 3:30 pm EST.
For those calling in we'll use the Blue Jeans [1] audio conference system.
Phone number: 1-888-240-2560 Meeting ID: 3528502673# Meeting URL: http://bluejeans.com/3528502673
Agenda:
1- Bubble Chamber progress at Argonne
Notes from this meeting:
- Bubble Chamber:
- Chamber is filled with mercury but there is a little leak.
- Tasks:
- Bubble Chamber beamline commissioning (February - May)
- Review of equipment - Bubble Chamber (May)
- Bubble Chamber at JLab (June)
- Review of operational procedures for this equipment (June)
- Accelerator 2015 Schedule:
- Spring 2015 Beam 10.5 GeV commissioning: February 13 - May 04
- SRF helium process of North Linac (NL-CHL2): May 19 - July 12
- Utilities Infrastructure Modernization (UIM) power outage: July 12 - August 10
- SRF helium process of South Linac (SL-CHL1): August 10 - September 12
- CHL2 Commissioning with new Heat Exchanger: September 01 - September 30
- Cryo/RF Restoration: September 28 - October 26
- Fall 2015 Beam 12.0 GeV commissioning: October 26 - December 21
- Bubble Chamber 2015 Schedule:
- Install in JLab Injector (June)
- Bubble Chamber tests - No beam (July)
- Commissioning with beam (August - September)