Wednesday May 14, 2014
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
We will meet in TL 2236 on Wednesday May 14 at 3:30 pm EST.
For those calling in we'll use the ReadyTalk audio conference system.
1. Dial Toll-Free Number: 866-740-1260 (U.S. & Canada) 2. Enter 7-digit access code 4402297, followed by “#”
Agenda:
1- Bubble Chamber progress at Argonne
2- Electron line status
- Layout media:140514_BubbleLayout.pdf
- Radiator media:140513_Radiator.pdf
3- Schedule
- Planning meetings
- reviews
- install kick-off
- commissioning plan
- Electron Line
- dismantle 5D
- fab/buy/build
- install
- controls
- checkout
- Prep work for chamber
- tunnel resources
- service building resources
- control room resources
- Install of chamber
- ship estimate
- install/checkout goals
- commissioning/test goals
Notes from this meeting:
- Bubble Chamber is ready to be filled with N2O.
- Once ready, all safety documents must be forwarded to D. Meekins.
- The chamber will be shipped with mercury in place but not N2O.
- Magnet dipole is signed off and out for bids.
- The Hall Probe has arrived at JLab.
- Magnet Alignment Fixture is being fabricated by the Machine Shop.
- The collimator table and holders will be made of aluminum.
- The table should be wide enough to stack copper bricks to shield the back scattered gammas, if needed.
- Need a list from Argonne of all the resources needed to run the bubble chamber (cables, power, ...).
- Here is a sketch of the Injector Tunnel, Injector Service Building (ISB) and the Machine Control Center (MCC): media:JLab_sketch.pdf media:JLab_sketch.pptx