10:00AM Run Meeting, Counting house meeting room (200C) | 10:00AM Run Meeting, Counting house meeting room (200C) | ||
Line 13: | Line 13: | ||
</gallery> | </gallery> | ||
− | * RTPC + FMT lifted to First | + | * RTPC + FMT lifted to First level<br/> |
<br/> | <br/> | ||
− | |||
==Plan:== | ==Plan:== |
Latest revision as of 09:56, 19 March 2020
Back to Run Group F | Daily Run Group F Coordination Meetings
10:00AM Run Meeting, Counting house meeting room (200C)
RC: Carlos Ayerbe
Summary of past 24h:
- RTPC + FMT work finished
- RTPC + FMT lifted to First level
Plan:
- Alignment of the RTPC with the beamline (ongoing).
- Cabling RTPC to the crate.
- Nathan B. indicates that should be cable to a different crate because there is no power supply available.
- Connect the RTPC to the gas panel.
- At 14h, PPE training by Bob Miller in the counting house.
- Javier sent an email reminding the 6ft (~2m) separation between shift workers and maybe the need to use Tyvek suites and masks.
- If everything is under control and on time, start taking cosmics all night.